Jem Contracting, Inc. v. Morrison-Maierle, Inc.

2014 MT 21, 318 P.3d 678, 373 Mont. 391, 2014 WL 298742, 2014 Mont. LEXIS 37
CourtMontana Supreme Court
DecidedJanuary 28, 2014
DocketDA 13-0446
StatusPublished

This text of 2014 MT 21 (Jem Contracting, Inc. v. Morrison-Maierle, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jem Contracting, Inc. v. Morrison-Maierle, Inc., 2014 MT 21, 318 P.3d 678, 373 Mont. 391, 2014 WL 298742, 2014 Mont. LEXIS 37 (Mo. 2014).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 JEM Contracting, Inc. (JEM) appeals the order of the Eighteenth Judicial District Court, Gallatin County, granting summary judgment to defendant Morrison-Maierle, Inc. (MMI). The dispute arose out of a construction contract between JEM, as contractor, and defendants Gallatin County and Madison County (County Defendants) for a road improvement project. MMI was hired by County Defendants to provide engineering services and supervision on the project. JEM filed suit against MMI alleging detrimental reliance and fraudulent inducement for promises allegedly made during the job by MMI that JEM would be paid for unanticipated costs incurred during pulverization of the old road. MMI moved for summary judgment, arguing that JEM could not prove that it had been harmed by its alleged representations. The District Court granted MMI’s motion, dismissing all claims against it.

¶2 We affirm and address the following issues:

¶3 1. Did the District Court err by concluding that JEM was required to continue performance pending approval of a change order under a contract provision that JEM claims is void as against public policy?

¶4 2. Did the District Court err by granting summary judgment to MMI on the ground that JEM had failed to show it was harmed by the representations made by MMI?

FACTUAL AND PROCEDURAL BACKGROUND

¶5 Defendant Counties retained JEM to provide construction services on a road improvement project over a 3.6 mile stretch of road near Big Sky that passed through both counties. MMI was retained by the Defendant Counties to provide engineering services and to act as the owner’s representative on the project. No contract was entered directly between JEM and MMI.

¶6 JEM alleged that on June 21, 2010, the first day of the project, it encountered subsurface conditions that differed significantly from the plans and specifications upon which it had based its bid, and which *393 would require increased time and costs for pulverization of the old road surface. JEM discussed the discrepancy with MMI’s on-site representatives over the next few days, some of whom agreed with JEM that the conditions differed from the plans, and at least one who disagreed. JEM proceeded with the job and did not provide written notice to MMI of the alleged differing conditions until July 9, 2010. That same day, JEM and MMI met to discuss the situation. JEM alleged that MMI agreed in this meeting that the site conditions varied from the contract specifications and promised JEM it would be paid for the increased costs related to the differing subsurface conditions if JEM could find savings on the rest of the job to complete it within the contract price. Specific dollar costs were not discussed at this time as JEM did not know the amount of the change order it would be seeking.

¶7 On July 29, 2010, JEM submitted a claim for additional compensation. MMI reviewed the claim and determined that JEM had provided insufficient evidence to support its claim and additionally had failed to follow the notification procedure set out in the contract for nonconforming site conditions. JEM and MMI met to discuss the matter, and MMI again concluded that JEM had failed to provide sufficient evidence to substantiate its claim that site conditions differed from the plans. JEM presented its request directly to Defendant Counties on November 4, 2010. This request was reviewed by the counties’ administrative committee for the project and was denied.

¶8 JEM completed its work on the project, contending that it had found savings in the remaining work, as requested by MMI, to cover the increased cost of subsurface work. Nevertheless, Defendant Counties continued to deny JEM’s change order. The Counties also refused to release a portion of the retainage withheld from monthly progress payments under the contract pending “substantial completion” of the project, due to JEM’s failure to provide certain documents required by the contract. On June 13, 2011, JEM filed its complaint against Defendant Counties and MMI alleging breach of contract, detrimental reliance, quantum meruit, fraud by inducement, and punitive damages. JEM later clarified that the claims for breach of contract, quantum meruit, and punitive damages were made against Defendant Counties, while the claims for detrimental reliance and fraud by inducement were made only against MMI. JEM subsequently settled with Defendant Counties and dismissed its claims against them.

¶9 MMI moved for summary judgment, arguing that JEM’s claims of detrimental reliance and fraud by inducement failed because (1) JEM *394 failed to state cognizable claims for relief; (2) MMI’s alleged promises were nothing more than “agreements to agree;” and (3) the claims contradicted the clear and unambiguous terms of the contract. The District Court granted MMI’s motion. JEM appeals from the order granting summary judgment to MMI.

STANDARD OF REVIEW

¶10 We review a district court’s ruling on a motion for summary judgment de novo, applying the same M. R. Civ. P. 56 criteria as the district court. Dick Anderson Constr., Inc. v. Monroe Constr. Co., LLC, 2009 MT 416, ¶ 20, 353 Mont. 534, 221 P.3d 675. Summary judgment is appropriate when there are no genuine issues as to any material fact, and the moving party is entitled to judgment as a matter of law. M. R. Civ. P. 56(c)(3). All reasonable inferences which may be drawn from the evidence must be drawn in favor of the party opposing summary judgment. Dick Anderson, ¶ 20. We review the district court’s conclusion that the moving party is entitled to judgment as a matter of law for correctness. Dick Anderson, ¶ 21.

DISCUSSION

¶11 1. Did the District Court err by concluding that JEM was required to continue performance pending approval of a change order under a contract pi'ovision that JEM claims is void as against public policy ?

¶12 The contract between JEM and Defendant Counties (the Contract) contained the following provision:

6.18 Continuing Work
A. Contractor shall carry on the Work and adhere to the Progress Schedule during all disputes or disagreements with Owner. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by Paragraph 15.04 or as Owner and Contractor may otherwise agree in writing.

(Paragraph 6.18.) JEM asserts this provision is void under § 28-2-2116(2), MCA, which provides:

A provision, covenant, clause, or understanding that is in, collateral to, or affects a construction contract and that states that a party to the contract may not suspend performance under the contract or terminate the contract if another party to the contract fails to make prompt payments under the contract as provided in 28-2-2103 is against the public policy of this state and is void and unenforceable.

In turn, § 28-2-2103, MCA, requires that a construction contract *395 contain a procedure for monthly billing by the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knutson v. State
683 P.2d 488 (Montana Supreme Court, 1984)
In Re Estate of Kindsfather
2005 MT 51 (Montana Supreme Court, 2005)
Dick Anderson Construction, Inc. v. Monroe Construction Co.
2009 MT 416 (Montana Supreme Court, 2009)
Keil v. Glacier Park, Inc.
614 P.2d 502 (Montana Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
2014 MT 21, 318 P.3d 678, 373 Mont. 391, 2014 WL 298742, 2014 Mont. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jem-contracting-inc-v-morrison-maierle-inc-mont-2014.