Opinion

Deemer, J.

The motion to direct a verdict was' based upon the grounds;' first, that there was no evidence to shoAV that defendants owned the real estate or the building Avhich Avas being erected thereon, or that they were in any manner interested therein; second, that no negligence was charged in the petition as against them; third, that the evidence shows that the negligence, if any, was that of a fellow-servant of plaintiff; fourth, that the relation of master and servant did not exist as between plaintiff and these defendants; fifth, that plaintiff knew of the alleged defects in the construction of the floor, and voluntarily remained in his employment, without complaint or promise of repair;1 and sixth, that, by the exercise of ordinary care, he might have known of the defects; but that, notwitstanding, he voluntarily remained at his work, without complaint or promise of repair.

[512]*5121 2 [511]*511To determine the correctness of the ruling, a consideration of the facts as disclosed by the record is essential. The evidence establishes the following; In the year 1892, Unterkircher & Sons, a firm composed of P. F. Unterkircher, Fred L. Unterkircher, and Gleorge L. Unterkircher, desirous of erecting a brick livery barn upon a lot owned by P. F. Unterkircher, [512]*512entered into contracts with certain mechanics, among whom were Austin Hemphill and J. Iiummerum, for the construction of various parts of the work. Hummerum had a contract for the brick work, which, among other things, contained the following: “The entire work to be done in a good and workmanlike manner, under the direction of E. Kropp and P. F. Unterkircher & Sons, and to their entire satisfaction, approval, and acceptance. * * * In consideration of the faithful performance of the foregoing stipulations and agreements by said second party, the said P. P. Unterkircher & Sons, party of the first part, agree faithfully to have said work duly and fairly estimated by E. Kropp, architect, as rapidly as the work is completed * * * All the scaffolding to be furnished by the brick layer.” The portions of the contract omitted relate to the work to be done, amount and terms of payment, and other matters not necessary to be here set out. Hemphill had a contract' for. the carpenter work, which, among other things, provided: “Said work to be commenced on or before the twelfth day of December, 1892, and to be completed sixty days after the brick work is finished. The entire work to be done in a good, workman-like manner, under the direction of E. Kropp, architect, and P.P. Unterkircher & Sons, and to their entire satisfaction, approval, and acceptance. In consideration of the faithful performance of the foregoing stipulations and requirements by second party, the said P. P. Unterkircher & Sons, party of the first paid, agree faithfully to have said work duly and fairly estimated by E. Kropp, architect, as rapidly as the work is completed.” Contracts for the stone work, painting, and every other thing needed to complete the building, were made with other parties. The plaintiff is a brick layer, and was employed by Hummerum upon the building. At the [513]*513time of the accident the rear and the two side walls of the structure were completed up to the square of the second story, — above the windows of the second floor, where the joists were to be laid. The outside of the front wall was up to the level of the square, and. the workmen were then- engaged in backing it up; that is, filling up the inside course of the brick work. A scaffold had been erected so that the brick layers could reach and work upon this front wall. The floor of the scaffold had for its immediate support, short pieces ‘ of scantling, one end of which was set into the wall, the other nailed to uprights, which rested on the floor of the second story of the building. As the second floor was to be suspended from a truss in the roof, a temporary support was made for the joists, which was to be removed, and rods from above substituted, after the building was completed. The joists of this second floor were laid on girders, and the girders were held up by posts, which, as we have said, afforded temporary support. The support for the girders referred to was two pieces of two by ten, or two by twelve joists, put together and stood up on end, under the girders. It appears that these temporary posts, or supports, were not of sufficient strength to carry the second floor, with the material that was' being used for the completion of the brick walls; that one of them gave way, and precipitated the whole of the second floor, with all of the material, scaffolding, and men at work thereon, into the cellar, resulting in the injuries complained of. The second floor, with its supports, was erected by, or under the direction of, Hemphill,, the carpenter, with the knowledge, and implied consent, at least, of the defendants and their architects. The scaffolding on which plaintiff was working was built in the ordinary manner, on the inside of the building, by the brick-layer, and no fault can be attributed to him, unless it be that he did not discover the [514]*514condition of the supports, and did not notify plaintiff of the condition thereof, on the day of the accident. It appears, from the evidence, that Hummeruin’s attention was called to the fact that one of these supports was bent on the day plaintiff was injured. It may be that it Avas his duty to notify the workmen of this fact; but this we need not decide, for no attempt is made to charge him personally in this action. And we will not consider the matter further than to determine whether defendants should be held liable for his neglect. It further appears, from the testimony, that the attention of Kropp, the architect, was called to the insufficiency of the support for the girders some days before the accident; and it also appears that plantiff saw these supports, and knew how the floor of the second story was constructed and sustained. From these facts we are to determine whether either Hemp-hill or Hummerum was the servant of the defendants, or stood in such relation to them as that they should be held liable for the negligence of either.

[515]*5153 [514]*514Defendants contend that both the brick mason and the carpenter were independent contractors, for whose negligence they are not responsible; while plaintiff, on the other hand, insists that they were servants of the defendants, engaged in doing the work, which they undertook to do, under the control, direction and management of Kropp, the defendants’ architect, and that defendants are responsible for the negligence of either. Many rules have been laid down for the determination of the question as to who are independent contractors. But the best definition we have been able to find is that given in Powell v. Construction Co., 88 Tenn. 692 (18 S. W. Rep. 691): “An independent contractor is one who, exercising an independent employment, contracts to do a piece of work according to his own methods, and without being subject to the control of his employer, except as to the result of his work.” [515]*515Applying this test to the case at bar, it will be seen that each of these parties was exercising an independent employment; that he contracted to do a certain portion of the work according to his own methods, and without being subject to the control of his employer, except as to the results of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenwell v. Meredith Corporation
189 N.W.2d 901 (Supreme Court of Iowa, 1971)
Associated Engineers, Inc. v. Job
370 F.2d 633 (Eighth Circuit, 1966)
State v. Hawkeye Oil Company
110 N.W.2d 641 (Supreme Court of Iowa, 1961)
Garden City Floral Co. v. Hunt
255 P.2d 352 (Montana Supreme Court, 1953)
Bowser v. State Industrial Accident Commission
185 P.2d 891 (Oregon Supreme Court, 1947)
John Gabel Manufacturing Co. v. Murphy
62 N.E.2d 401 (Illinois Supreme Court, 1945)
Ozark Minerals Co. v. Murphy
51 N.E.2d 197 (Illinois Supreme Court, 1943)
Reynolds v. Skelly Oil Co.
287 N.W. 823 (Supreme Court of Iowa, 1939)
Mendel v. Fort Scott Hydraulic Cement Co.
78 P.2d 868 (Supreme Court of Kansas, 1938)
Hough v. Central States Freight Service, Inc.
269 N.W. 1 (Supreme Court of Iowa, 1936)
Heintz v. Iowa Packing Co.
268 N.W. 607 (Supreme Court of Iowa, 1936)
Niemann v. Iowa Electric Co.
253 N.W. 815 (Supreme Court of Iowa, 1934)
Martin v. Republic Steel Co.
146 So. 276 (Supreme Court of Alabama, 1933)
Helzer v. Wax
272 P. 556 (Oregon Supreme Court, 1928)
In Re Estate of Amond
210 N.W. 923 (Supreme Court of Iowa, 1926)
Central of Georgia Railway Co. v. Lawley
126 S.E. 273 (Court of Appeals of Georgia, 1925)
Loveless v. Town of Wilton
193 Iowa 1323 (Supreme Court of Iowa, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.W. 776, 97 Iowa 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/humpton-v-p-f-unterkircher-sons-iowa-1896.