Leverone v. Arancio

61 N.E. 45, 179 Mass. 439, 1901 Mass. LEXIS 593
Massachusetts Supreme Judicial Court·Decided September 3, 1901·Published·Cited by 26 cases

Opinion

Loring, J.

1. We are of opinion that the exception to the charge of the presiding judge, as to the plaintiff’s failure to comply with the following provisions of the specifications, must be sustained: “ Before any final estimate shall be allowed by the architect in charge, the contractor will be required to sign a certificate on said estimate that he will accept the same as a settlement in full for all claims against the owner on account of work done under this specification and contract. The contractor shall also sign and duly attest a statement, before final payment is made, that all claims for materials provided or labor performed on this property are paid and satisfied in full, and that there are no claims whatsoever against the owner of this property.”

The presiding judge instructed the jury “ as a matter of law, that it would be competent for the architect, as agent for the owner, to waive for the owner compliance with that stipulation on the part of the contractor that he would before final payment, give these certificates.” Even if there was evidence on which the jury could have found that the defendant had waived these provisions and also evidence on which it could have been found that the architect-was authorized to waive these provisions, it was error to instruct the jury as a matter of law that the architect could waive these provisions, and the only question was whether he had done so. The instruction, therefore, was wrong. An architect has no authority to waive an agreement by the owner as to the terms on which payment shall be made.

The provision of article 1 of the contract, that “ the contractor, under the direction and to the satisfaction of F. M. Churchill, architect, acting for the purposes of this contract as agent of the said owner, shall and will provide all the materials and perform all the work mentioned in the specifications and shown on the drawings,” does not go further than to make the architect the [443]*443agent of the owner in the matter of deciding whether the work done fulfilled the requirements of the specifications and drawings. Apart from an agreement to that effect an architect is not the general agent of the owner. See McIntosh v. Hastings, 156 Mass. 344; Adlard v. Muldoon, 45 Ill. 193; Glacius v. Black, 50 N. Y. 145. The provision in this contract did not give the architect authority to waive, in behalf of the owner, the terms on which the owner had stipulated in writing that the payments for the work were to be made when the work described had been done to the architect’s satisfaction.

We are further of opinion that the contractor must fulfil the requirements of these two clauses before he can bring suit. The fair meaning of these two clauses is (1) that the last instalment shall not be due until the plaintiff agrees that that instalment will be accepted by him in full settlement of all claims against the owner on account of work done under the contract, and makes a certificate to that effect on the architect’s certificate for that instalment; and (2) that the final instalment shall not be due until all claims for material provided or labor performed have been paid and satisfied in full and a written statement to that effect is made by the contractor. There was evidence that when this suit was brought there were outstanding claims for labor and materials, and there was no pretence that either the certificate or the statement mentioned above had been made.

The result is that this action was prematurely brought. Although these two provisions prevent the contractor from get- 0 ting credit directly from the material men and the workmen employed by him, there is nothing to prevent his borrowing the money due them from others, and paying them off with it; if he does so, and then makes the required written statement that nothing is due for material furnished or labor performed, and also makes certificate on the architect’s certificate for the final payment, that he accepts it, as stated therein, in full settlement of all claims “ on account of work done under this specification and contract,” he will be entitled, on proving what the jury found he proved in this case, to recover on the first count. He is entitled to recover on the second count, without making these certificates; the ground on which he is entitled to recover for that work, if he is entitled to recover for it without having got [444]*444an order from the architect for the extra work covered by that count, is that the work is done outside of the contract.

As the case must go back for a new trial, we will dispose of - the other questions which have been argued. It is doubtful whether all of these questions are open to the defendant, who made no requests for rulings, but contented himself with general exceptions to different parts of the charge. But we. have not stopped to consider the question whether they are open to the defendant or not.

2. The defendant’s contention is not well taken that he is entitled to a claim against the plaintiff by way of recoupment for damages caused by the work being suspended for some six weeks immediately after it was begun, and for '$22 expended by him in procuring a building permit to construct the new bay windows on Fulton Street. The delay in question -was caused by the fact that the permit for the construction of the new bay windows was not obtained until October 14, about six weeks after the contract was signed ; the contract was signed September 6, 1898.

It appeared in evidence that a permit for a bay window " “ would be issued only upon a personal application by the owner of the property ”; and further, there was evidence that the “ defendant had applied for a bay window permit and had failed to obtain one” some time before the contract was signed, and that “he applied a second time in August, 1898, also prior to the signing of the contract, so that when the contract was signed, the bay window permit had been applied for by the defendant, and was, after some delay, obtained on October 14, 1898.”

In the specifications, which are stated to be “ Specification for Material and Labor Required for Alterations on Building for J. Arando, Esq.,” the following provision is made under the heading “ Mason’s Specifications ” : “ Permits — All needed permits must be obtained from the proper authorities.” The work of constructing the bay windows is included under this heading of “ Mason’s Specifications.” The defendant contends that this clause makes the plaintiff liable for all damages which ensued, from the fact that the permit which had been applied for by the defendant for the second time before the contract was signed, [445]*445was not obtained until six weeks after that contract was signed, — on October 14, 1898. It is hardly necessary to say that if, by the proper construction of this provision of the specifications it is made the duty of the plaintiff to obtain the bay window permit, he has not undertaken, by agreeing to perform the work described in these specifications, to insure that the permit will be issued for a bay window without delay.

The further question of the expense of $22 admits of some doubt; but we are of opinion that this provision does not throw upon the plaintiff the duty of obtaining the bay window permit, which must be obtained on the personal application of the owner. It may be doubted whether it goes any further than to provide that no work must be done until a permit has been obtained.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Leverone v. Arancio, 61 N.E. 45, 179 Mass. 439, 1901 Mass. LEXIS 593 (Mass. 1901).

61 N.E. 45 (Leverone v. Arancio) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kaufman v. Leard
248 N.E.2d 480 (Massachusetts Supreme Judicial Court, 1969)
Henderson v. Cochran
100 S.E.2d 910 (Supreme Court of Georgia, 1957)
Garden City Floral Co. v. Hunt
255 P.2d 352 (Montana Supreme Court, 1953)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Bartol v. Simco Trading Co.
4 Mass. App. Div. 341 (Mass. Dist. Ct., App. Div., 1939)
Palace Cafe v. Hartford Fire Ins.
97 F.2d 766 (Seventh Circuit, 1938)
Keene v. Kelley
49 F.2d 874 (First Circuit, 1931)
Reynolds v. Cole
172 N.E. 91 (Massachusetts Supreme Judicial Court, 1930)
Eastern Advertising Co. v. Standard Nut Co.
162 N.E. 339 (Massachusetts Supreme Judicial Court, 1928)
Bray v. Hickman
161 N.E. 612 (Massachusetts Supreme Judicial Court, 1928)
Mills v. Dillon
157 N.E. 604 (Massachusetts Supreme Judicial Court, 1927)
O'Neil v. National Oil Co.
231 Mass. 20 (Massachusetts Supreme Judicial Court, 1918)
Hennebique Construction Co. v. Boston Cold Storage & Terminal Co.
119 N.E. 948 (Massachusetts Supreme Judicial Court, 1918)
J. Kennard & Sons Carpet Co. v. Houston Hotel Ass'n
197 S.W. 1139 (Court of Appeals of Texas, 1917)
King v. Thompson
101 A. 724 (Supreme Judicial Court of Maine, 1917)
Smith v. Board of Education
85 S.E. 513 (West Virginia Supreme Court, 1915)
City of Fall River v. Ætna Insurance
107 N.E. 367 (Massachusetts Supreme Judicial Court, 1914)
Jean v. Cawley
105 N.E. 1009 (Massachusetts Supreme Judicial Court, 1914)
H. J. Reedy Co. v. Harrison
24 Ohio C.C. Dec. 99 (Ohio Circuit Courts, 1911)
H. J. Reedy Co. v. Harrison
14 Ohio C.C. (n.s.) 271 (Hamilton Circuit Court, 1911)