BOLIVAR REORG. SCHOOL DIST., ETC. v. American Sur. Co.

307 S.W.2d 405
CourtSupreme Court of Missouri
DecidedNovember 12, 1957
Docket45866
StatusPublished
Cited by1 cases

This text of 307 S.W.2d 405 (BOLIVAR REORG. SCHOOL DIST., ETC. v. American Sur. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BOLIVAR REORG. SCHOOL DIST., ETC. v. American Sur. Co., 307 S.W.2d 405 (Mo. 1957).

Opinion

307 S.W.2d 405 (1957)

BOLIVAR REORGANIZED SCHOOL DISTRICT NO. I, POLK COUNTY, Missouri, Plaintiff-Respondent,
v.
AMERICAN SURETY COMPANY OF NEWYORK, a Corporation, Defendant-Appellant.

No. 45866.

Supreme Court of Missouri. Division No. 2.

November 12, 1957.
Motion for Rehearing or to Transfer Denied December 9, 1957.

*406 Clifford B. Kimberly, Kansas City, for appellant.

Richard C. Collins, T. H. Douglas, Elvin S. Douglas, Bolivar, for respondent.

Motion for Rehearing or to Transfer to Court en Banc Denied December 9, 1957.

BARRETT, Commissioner.

In this action on a bid bond the obligee, Bolivar Consolidated School District No. 1, has recovered a judgment against the surety in the sum of $13,396.50, comprised of the principal sum of $8,283.20 interest, $1,794.98, and for vexatious delay and refusal to pay a penalty of $828.32 and attorneys' fees of $2,500. The school district proposed to and finally did construct three buildings, an elementary school in Polk, an elementary school in Bolivar, and an auditorium-gymnasium in Bolivar. Accordingly, in September, 1952, through its architect, Dan R. Sanford & Sons, the school board issued an advertisement and notice to contractors for sealed bids for the construction of the three buildings. The notice stated that "Bids will be taken *407 on the basis of a single contract for each building * * * and a combined bid may be submitted for the three buildings to be built under one contract." The notice required that "A bid guaranty shall be submitted with each bid in an amount equal to five percent (5%) of the bid," either in the form of a certified check or "approved bid bond"—the check or bond to be considered as liquidated damages "for the failure of a bidder to whom a contract is awarded to execute the contract documents and surety bond." In compliance with the notice and instructions Ozark Construction Company submitted four bids, for the elementary school at Polk, $65,555, for the elementary school in Bolivar, $125,363, for the auditorium-gymnasium, $165,664, and a combined bid for the construction of all three buildings of $335,555.55. The bids were received and opened on the appointed date, September 25, 1952, and on October 2, 1952, the school board adopted a resolution accepting the $165,664 bid of the Ozark Construction Company to construct the auditorium-gymnasium. Ozark Construction Company was unable to furnish a performance or construction bond, was "in a financial bind," did not sign or execute the contract, and in the following December became bankrupt. A contract for the construction of the building was awarded to another contractor and upon the trial of this case the parties stipulated that the actual cost exceeded the bid of Ozark Construction Company more than $10,000.

Upon the contractor's default the school district instituted this action against the surety, American Surety Company, on Ozark's bid bond. When Ozark's bids were submitted, instead of a separate bid bond accompanying each bid, there was but a single bond. Since the bond recited that Ozark Construction Company was about to submit "a proposal for school buildings" and the guaranty was "if the said proposal is accepted, the American Surety Company denied liability on the bond. The company admits the execution of the bond but contends that it was issued and intended to cover the "combined bid" for all three buildings only and was not written or intended to cover the "single" contract or bid for the construction of the auditorium-gymnasium. In its answer the surety's defense is stated in this language, "that said bid bond was submitted with the last bid stated above which was a combined bid for all three of said buildings and had no connection with any other bid other than said combined bid," and it specifically denied executing a bond for Ozark's separate bid on the auditoriumgymnasium or for any of the bids on the individual or separate buildings. In its letter of November 20, 1952, in which it denied liability to the board, its resident manager explained its position in this language: "The bond which we furnished specified that it covered a proposal for school buildings and it accompanied a combination proposal for the construction of three school buildings. It is our information that this proposal was approximately $357,000. Your board did not accept this proposal and therefore it is our position that there is no liability under the bid bond for such proposal. It is also our position that there is no liability under this bid bond for any single building. The bond did not specify any single building. The instructions to bidders specify that each separate bid should be supported by a bid bond. We issued no bid bond supporting a proposal for the construction of any auditoriumgymnasium. When furnishing a bid bond covering a combination proposal the surety company does not contemplate that it will be subjected to the liability of guaranteeing that the bidder will enter into contract and furnish bond on some one of the buildings involved. This is because of the possibility that some building on which the bid was particularly low might be singled out and it appears that this is precisely what happened in this case." To further make plain and illuminate its defense in both the trial court and here, appellant's brief is quoted; *408 "the bond shows plainly that it covers a proposal for `School Buildings' and that one proposal only is contemplated is shown by the use of the word `proposal' in the last line" in which the surety agrees to pay the obligee damages suffered "not exceeding the sum of 5% of amount of proposal." In short, since the board did not accept the contractor's combined bid of $355,555.55 for all three buildings, it is urged that there was no award of a contract within the language and meaning of the bond, hence there was no liability for the contractor's default as to the single contract for the auditorium-gymnasium.

Upon this appeal it is urged that the court erred in admitting evidence to vary and interpret the plain, unambiguous language of the bond, and that it erred in awarding damages and attorneys' fees for vexatious delay. But the essential claim, as indicated, is that it is not liable on the bond in this action and that the fact should be declared by this court. The case was tried "upon the facts without a jury" and is reviewable here upon both the law and the evidence as in suits of an equitable nature (V.A.M.S. § 510.310), this court considering such evidence as it deems admissible and excluding from consideration evidence improperly admitted. Hussey v. Robison, Mo., 285 S.W.2d 603.

In support of its position the appellant invokes the general rules of construction, that its liability as a surety is measured and strictly limited to the terms of its contract and may not in the guise of construing or interpreting ambiguities be enlarged. City of St. Joseph ex rel. Consolidated Stone Co. v. Pfeiffer Stone Co., 224 Mo.App. 895, 26 S.W.2d 1018; Blanke Bro. Realty Co. v. American Surety Co., 297 Mo. 41, 247 S.W. 797; 72 C.J.S. Principal and Surety §§ 91, 94, pp. 569, 574.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kansas City NO Nelson Co. v. MID-WESTERN CONSTRUCTION CO. OF MO., INC.
782 S.W.2d 672 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
307 S.W.2d 405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolivar-reorg-school-dist-etc-v-american-sur-co-mo-1957.