North St. Louis Planing Mill Co. v. Essex

137 S.W. 295, 157 Mo. App. 18, 1911 Mo. App. LEXIS 373
CourtMissouri Court of Appeals
DecidedMay 2, 1911
StatusPublished
Cited by9 cases

This text of 137 S.W. 295 (North St. Louis Planing Mill Co. v. Essex) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North St. Louis Planing Mill Co. v. Essex, 137 S.W. 295, 157 Mo. App. 18, 1911 Mo. App. LEXIS 373 (Mo. Ct. App. 1911).

Opinion

CAULFIELD, J.

(after stating the facts). — I. Appellant urges that the petition does not state facts sufficient to constitute a cause of action for several reasons.

(a) The first reason which he urges is that the plaintiff has failed to allege facts from which it may be concluded that it was one of the obligees designated in the bond as “all persons who may become entitled to liens under said contract dated October 4, 1905,” and therefore no privity is shown to exist between the plaintiff and defendants. Appellant’s- position is that, in order for plaintiff to have become “entitled” to a lien under-the contract, it must not only have shown, as it did, that it furnished material for the building at the instance of the original contractor, but must have shown that it gave notice to the owner, filed its lien account in time, etc. Appellant even insists that it must appear that in. due time the plaintiff had filed suit to enforce its lien..

[26]*26In making this contention, appellant fails to distinguish between those “entitled” to liens and those who have taken steps to “enforce” them. That distinction was recognized by us in Holland v. Cunliff, 96 Mo. App. 67, 75, 69 S. W. 737, where, through Judge Barclay, we «aid: “By the law of Missouri, a lien in favor of an artisan or other person who furnishes labor or materials to improve realty is imposed in certain circumstances on the interest in land subject to the lien from the time of the commencement of the building or improvement. [R. S. 1899, sec. 4209]. The lien is not, therefore ‘obtained through legal proceedings’ within the meaning of section €7f of the Bankrupt Law of 1898 (Act July 1, 1898, c. 541, 30 Stat. 565 [U. S. Comp. St. 1901, p. 3450]), although later legal proceedings are needful to secure the fruits of the lien already engrafted on the realty by the performance of the beneficial acts described(The italics are our own.) LaAV writers, when discussing the question of who are “entitled” to liens, g-enerally answer it by merely designating classes of persons according to the benefit they have bestoAved. Thus one text-writer informs us that “the earlier mechanics’ lien acts did not expressly name contractors among those entitled to liens.” [Boisot, Mechanics’ Liens, sec. 217.] And in another place, (section 220) he states that “a contractor for the labor of others in a mine, at a fixed rate for each man per day, is entitled to a lien for the labor furnished by him as an original contractor.” And he speaks of the giving of notice and the filing of the lien as steps in the enforcement of the lien rather as being necessary to “entitle” the claimant to it. It seems to us that the language in question is sufficient to include one who, like the plaintiff, had furnished material and might have enforced a mechanic’s lien therefor, without regard to whether he took the steps necessary to such enforcement or not. Indeed, to prevent the steps necessary to enforce the lien and save the OAVner the expepse and trouble incident thereto was evidently the very purpose of giving [27]*27those entitled to a lien the privilege of suing on the bond. It would avail the. lienor and benefit the owner little, if at all, to give the former the privilege of bringing a suit on the bond only after he had reduced his lien claim to judgment in a separate suit. To hold that the language of the bond contemplated that would be against reason.

(b) Appellant next aserts that the petition fails to state a cause of action because it shows that the principal- did not sign the bond. Our Supreme Court has held that a common law bond not signed by the principal is void as to the sureties where it shows on its face that it is not a complete instrument without such signature (Gay v. Murphy, 134 Mo. 98, l. c. 108, 34 S. W. 1091, 56 Am. St. Rep. 496), but the court seems by its reasoning clearly to recognize that the sureties would be bound where the bond shows their intention to bind themselves regardless of whether the principal signs or not; at least, we take it, such would be the case where the principal is already bound by the contract referred to. [1 Brandt, Suretyship and Guaranty, 2 sec. 170.] Here the petition discloses quite distinctly that the principal is bound by the contract referred to, and there is nothing in the description of the bond to indicate that it recites that it is signed by the principal .or that it calls for or contemplates such signature or appears incomplete without it. The language of the petition as to that is, that “said defendants, Henry A. Ohristophel and William H. Pearson (the building contractors), delivered to said Edward O. Roenigke (the owner and named obligee) a certain bond or writing obligatory signed and sealed on said day by defendants Louis Essex and Heinrich Schweitzer (the sureties) . . . by the.terms of which said contract and bond, said defendants Henry Ohristophel, William H. Pearson, Louis Essex, and Heinrich Schweitzer bound themselves,” etc. The latter part of this language beginning with “by the terms of which contract and bond” gave us some difficulty, for at first glance it would seem to imply that the [28]*28pleader intends to allege that by the terms of the bond the principals as well as the sureties purported to' bind themselves, which if true, would lead to the inevitable, .inference that the bond was incomplete on its face if the principals failed to sign. But, on carefully reading the-whole petition, Ave have concluded that, by alleging that, “by the terms of the contract and bond” the principals and sureties bound themselves, the pleader meant nothing more than that by reading the bond and contract together, as they should be read, the sureties by signing the bond and the principals by signing the contract referred to became bound. ■ While the petition would be subject to a motion to mate more definite and certain, and is not to be commended for use as a model of good pleading, we feel that it is sufficient in the respect mentioned.

(c) Appellant next contends that the petition is fatally defective because it does not show that the sureties authorized the principals to deliver the bond for them. It sufficiently appears from the petition that the principals had possession of the bond and delivered it to the obligee named, duly signed, and sealed by the sureties. The possession of the bond by the principal will be. presumed to be. rightful (Phillips v. Schall, 21 Mo. App. 38, 42); and, having rightful possession, his-delivery of it was binding upon the sureties, even without the assent of the latter, there being, so far as the petition discloses, nothing on the face of the bond, or in any of the attending circumstances, to indicate that there was any fact or circumstance which should preclude the acceptance of the bond. [State to Use v. Potter, 63 Mo. 212, 226, 21 Am. Rep. 440.]

Then, too, the petition alleges that by the terms of the contract and bond the sureties bound themselves, etc. This was sufficient in itself as an averment of execution and delivery by those alleged to have bound themselves by its terms. [State ex rel. Phillips v. Rush, 77 Mo. 586; Jacobs v. Curtiss, 67 Conn. 497, 35 Atl. 501]

[29]*29(d) Appellant also urges that the petition fails to state a cause of action because there is no consideration alleged for the contract. The promises or undertakings of the owner, Eoenigke, contained in the building contract, were a sufficient consideration for the promises or undertakings of Christophel & Pearson, the contractors (Byrd v. Fox, 8 Mo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ill-Mo Contractors, Inc. v. Aalcan Demolition & Contracting Co.
431 S.W.2d 165 (Supreme Court of Missouri, 1968)
BOLIVAR REORG. SCHOOL DIST., ETC. v. American Sur. Co.
307 S.W.2d 405 (Supreme Court of Missouri, 1957)
Greer v. Scearce
53 F. Supp. 807 (W.D. Missouri, 1944)
Silver v. Fidelity & Deposit Co. of Maryland
53 P.2d 459 (New Mexico Supreme Court, 1935)
Graff v. Continental Auto Insurance Underwriters
35 S.W.2d 926 (Missouri Court of Appeals, 1931)
Pritchard v. Mines
111 N.E. 804 (Indiana Court of Appeals, 1916)
Streator Clay Manufacturing Co. v. Henning-Vineyard Co.
176 Iowa 297 (Supreme Court of Iowa, 1916)
Roennigke v. Essig
151 S.W. 765 (Missouri Court of Appeals, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
137 S.W. 295, 157 Mo. App. 18, 1911 Mo. App. LEXIS 373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-st-louis-planing-mill-co-v-essex-moctapp-1911.