Hotchner v. Liebowits

341 S.W.2d 319, 1960 Mo. App. LEXIS 434
CourtMissouri Court of Appeals
DecidedDecember 20, 1960
Docket30458
StatusPublished
Cited by38 cases

This text of 341 S.W.2d 319 (Hotchner v. Liebowits) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hotchner v. Liebowits, 341 S.W.2d 319, 1960 Mo. App. LEXIS 434 (Mo. Ct. App. 1960).

Opinion

BRADY, Commissioner.

The respondents, husband and wife, brought this action against the appellant on the grounds that the residence which they purchased from appellant was not constructed in a clean, workmanlike manner as provided in the specifications, in that: (A) the footings were placed on ground having insufficient bearing resistance resulting in settling and cracking in the foundation, brickwork, and inside plaster; (B) the plastered walls, stone trim and bricks of the outer walls had cracked, shifted and become loosened and broken; (C) tiles on the kitchen floor had pulled apart; (D) the concrete floor in the basement and garage portions of the improvement had cracked, permitting water to come into the basement which did not remain dry for a period of a year after completion as guaranteed by the appellant; (E) the windows, doors, fireplace, concrete steps, walks and "other portions” of the house were faultily constructed; (F) the insulation specified was not furnished; and (G) the appellant failed to install a basement drain, failed to complete the installation of the heating and air-conditioning unit, and used galvanized iron instead of copper flashing. It was further alleged in a separate paragraph of the petition that the appellant knew, or should have known, of the insufficient bearing resistance of the subsoil on which he caused the footings to be placed, and that this would cause the improvements to settle with resulting serious fractures in the walls of the building. Respondents prayed judgment by reason of breach of contract in the amount of $5,000.

Appellant’s answer admitted the contract and denied the other allegations. The cause was tried to a jury with a resulting verdict in favor of respondents in the amount of $3,000. The appellant filed timely motion for new trial and perfected his appeal to this court.

The appellant sets forth eleven points in his brief, two of which have five subpoints, another of which has six subpoints, another has seven, and another of which has ten subpoints. However, one reading and considering these numerous contentions finds that they are often restatements of each other, and may be fairly regrouped into five main contentions. These are (1) that respondents failed to make a submissible case and therefore the trial court committed prejudicial error in overruling appellant’s motions for a directed verdict; (2) that the trial court prejudicially erred in giving certain instructions and in refusing others; (3) that the appellant’s objection to the hypothetical question asked of respondents’ expert witness David should have been sustained; (4) that the appellant’s motion to strike the testimony of the witness Hallauer should have been sustained; and (5) that the verdict was grossly excessive.

*323 For the purposes of our review, appellant’s motion for new trial having been overruled, the respondents’ verdict is final on factual issues provided it is supported by substantial evidence; and whether respondents made a submissible case is to be determined by a review of the probative facts not entirely unbelievable or opposed to the physical facts and from the standpoint most favorable to the respondents, including facts established by appellant’s evidence if they aid respondents’ case and providing they do not conflict with the respondents’ testimony or fundamental theory of the case, and as we are not privileged to weigh conflicting evidence, we are to give the respondents the benefit of all reasonable inferences and disregard appellant’s evidence insofar as it is unfavorable to the respondent. Capra v. Phillips Investment Co., Mo., 302 S.W.2d 924, and cases cited at loc. cit. page 929(1); Missouri Digest, Appeal and Error, ^930(1), 989, 1005(2).

With respect to the alleged failure of the appellant to do all of the things and furnish all the materials specified in the contract, it is clearly stated in the specifications which are in evidence that there were to be two drains in the basement floor. The respondent Sally Hotchner testified there was only one. This was also the testimony of the witness Hallauer. The appellant himself admitted upon cross-examination that the specifications called for copper flashing and he used aluminum. Since this evidence was in support of, and not in conflict with, respondents’ case, it is to be considered by us upon this inquiry. There was no testimony as to the allegation of failure to supply the specified insulation nor concerning the alleged failure to complete the heating and air-conditioning installation. As to the latter, the evidence was that this item was the subject of negotiation and agreement by the parties as a separate item outside of this contract. The appellant testified that insulation was furnished.

What was the evidence as to the alleged faulty construction of windows, doors, the fireplace, concrete steps and walks? The respondent Sally Hotchner testified that there was a “bad door” between the garage and basement, that the garage door was improperly installed, with the result that rain came in the two-inch opening left by this improper installation; that there was a window in the den that would not raise; that the appellant’s workmen had not properly anchored the legs of the ornamental iron posts on the porch; and that the first time they built a fire in the fireplace, the house filled with smoke and the fireplace opening had to be enlarged; that within three or four months after purchase of the house, the concrete walk at the rear of the house started to crack, and that the driveway began cracking about seven to eight months after purchase; that the tiles on the kitchen floor had become separated and cracked and broken; the witness Hallauer testified that he found some windows that were not operational; that the floor joists in the basement had been left so that there was a space between them and the foundation and the top of the basement wall; that the floor in the garage and driveway was checked and did not have a smooth finish.

With reference to the allegations of respondents’ petition alleging breach of the contract because of the faulty construction relating to the placement of the footings on ground having insufficient bearing resistance which resulted in the settling and cracking of the foundation, brickwork, inside walls, basement walls and floor, the respondent Sally Hotchner testified to a large crack as one came down the steps, that the basement wall on the east side of the house was cracked and water seeped through; that there was a large crack in the plaster at the west wall of the southeast bedroom; that the wall tile had cracked in the bathroom; that before they had moved into the house some bricks on the east wall had been removed and replaced because they had cracked, and that these cracks had returned about six months *324 after they moved in and were now getting worse; that there were cracks in the basement floor through which water seeped about six months after they moved in. There are several pictures which were admitted into evidence graphically showing these cracks. The cracks shown in the photographs occurring in the interior and exterior walls of the house were also testified to by the witness David, who also corroborated .the testimony as to the interior and exterior cracks in the southeast end of the building extending down to the footing line in the basement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Pickens
332 S.W.3d 303 (Missouri Court of Appeals, 2011)
Pope v. Pope
179 S.W.3d 442 (Missouri Court of Appeals, 2005)
Korte Construction Co. v. Deaconess Manor Ass'n
927 S.W.2d 395 (Missouri Court of Appeals, 1996)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
Trien v. CROASDALE CONST. CO., INC.
874 S.W.2d 478 (Missouri Court of Appeals, 1994)
McCutcheon v. Cape Mobile Home Mart, Inc.
796 S.W.2d 901 (Missouri Court of Appeals, 1990)
Richardson v. Collier Building Corp.
793 S.W.2d 366 (Missouri Court of Appeals, 1990)
Missouri Farmers Ass'n v. Cantrell
764 S.W.2d 749 (Missouri Court of Appeals, 1989)
Lowder v. Missouri Baptist College
752 S.W.2d 425 (Missouri Court of Appeals, 1988)
Iota Management Corp. v. Boulevard Investment Co.
731 S.W.2d 399 (Missouri Court of Appeals, 1987)
State ex rel. Empire District Electric Co. v. Public Service Commission
714 S.W.2d 623 (Missouri Court of Appeals, 1986)
Kozeny-Wagner, Inc. v. Shark
709 S.W.2d 149 (Missouri Court of Appeals, 1986)
Steffens v. Paramount Properties, Inc.
667 S.W.2d 725 (Missouri Court of Appeals, 1984)
Buder v. Martin
657 S.W.2d 667 (Missouri Court of Appeals, 1983)
Stegemann v. Helbig
625 S.W.2d 677 (Missouri Court of Appeals, 1981)
Sunny Baer Co., Inc. v. Slaten
623 S.W.2d 595 (Missouri Court of Appeals, 1981)
Hensic v. Afshari Enterprises, Inc.
599 S.W.2d 522 (Missouri Court of Appeals, 1980)
Busch & Latta Painting Corp. v. State Highway Commission
597 S.W.2d 189 (Missouri Court of Appeals, 1980)
Ribando v. Sullivan
588 S.W.2d 120 (Missouri Court of Appeals, 1979)
Matulunas v. Baker
569 S.W.2d 791 (Missouri Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
341 S.W.2d 319, 1960 Mo. App. LEXIS 434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hotchner-v-liebowits-moctapp-1960.