Richardson v. Collier Building Corp.

793 S.W.2d 366, 1990 Mo. App. LEXIS 706, 1990 WL 58110
CourtMissouri Court of Appeals
DecidedMay 8, 1990
DocketWD 42302
StatusPublished
Cited by11 cases

This text of 793 S.W.2d 366 (Richardson v. Collier Building Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richardson v. Collier Building Corp., 793 S.W.2d 366, 1990 Mo. App. LEXIS 706, 1990 WL 58110 (Mo. Ct. App. 1990).

Opinion

GAITAN, Presiding Judge.

Respondents Engineering Surveys & Services, Inc., and C.L. Richardson filed suit seeking payment for services under contract. The appellant counterclaimed for damages he alleged were incurred from a failure of the respondents to perform as contracted. The trial court held for respondent, Engineering Surveys & Services, Inc., and against respondent, C.L. Richardson, and against defendant on its counterclaim.

On appeal the appellant alleges the trial court erred by: (1) permitting the use of its project superintendent’s deposition and thereafter holding that said superintendent had authority to act for defendant; (2) permitting respondents to amend their pleadings to conform to the evidence; and (3) by permitting evidence of failure to mitigate damages and waiver of contract provisions. We affirm.

The facts herein, though extensive, are necessary to a full understanding of the *368 case. Appellant Collier Building Corporation (hereinafter Collier) is a Missouri corporation with offices in St. Charles, Missouri. Collier is in the business of acting as general contractor for building projects. Donald G. Collier, Jr. (hereinafter “Don Collier”), the general manager in charge of the day-to-day operations of Collier Building Corporation, also served as the project manager for the Vandiver Square project, the subject of this case. Don Collier has been involved in the construction business since 1973, and at the time of trial, had been involved in constructing 300 to 500 residential structures and 5 to 10 commercial buildings.

Before commencing the Vandiver Square project, Don Collier had been involved in construction projects entailing the use of “engineered fill,” with respect to which he knew the following: That fill has to be compacted to a certain standard to be sufficient to build upon; that the degree of compaction is generally ascertained by testing each layer or “lift” of fill as it is laid down; that problems can arise if soil is inadequately compacted; and that, depending on how the building is constructed, such problems can include shifting of the foundation, settling of sewer, water and electrical lines, and doors not opening properly. Don Collier also knew that the only way to ascertain the degree of compaction is through appropriate testing.

Don Collier purchased Vandiver Square with the idea of developing two buildings thereon. After the site was purchased, he contracted with Allstate Consultants to prepare a site development plan and obtain necessary approvals from the City of Columbia. Allstate Consultants is operated by Ron Shy (hereinafter “Shy”), a registered land surveyor, who has engineering degrees. Allstate performs site design, land surveying and subdivision design. On the Vandiver Square project, Allstate made a boundary survey of the property, prepared and filed preliminary and final plats with the city, designed an off-site sanitary sewer connection, and prepared a site and grading plan.

At Don Collier’s request, Shy prepared bid packages to go to soil contractors, one of which was given to C.L. Richardson (hereinafter “Richardson”). Don Collier telephoned Richardson on August 12, 1987, and asked him to pick up a bid package from Shy. No detailed soil compaction specifications were prepared for the project, but Shy’s office communicated to Richardson that the fill was to be compacted to 95% optimum compaction.

For soil compaction testing services, Shy referred Don Collier to respondent, Engineering Surveys and Services, Inc. (hereinafter “ES & S”) which is certified by the Missouri Board of Architects, Professional Engineers and Land Surveyors to practice engineering. Larry L. Hendren (hereinafter “Hendren”) is the president and a shareholder of ES & S. Hendren, who had 10 years of experience in soil testing, testified that Don Collier initially telephoned him about soil testing for the Vandiver Square project in late July or early August, 1987; Don Collier testified that the telephone call was on August 12, 1987.

On August 19, 1987, Don Collier went to Shy’s office and reviewed the bids from soil contractors. On August 20, 1987, Don Collier returned a telephone call from Hendren relative to ES & S’s proposal for soil testing on the Vandiver Square project. During that conversation, Don Collier told Hen-dren that Richardson would likely be the earth-moving contractor.

Richardson made his bid on the job from the plans provided by Shy. These plans included clearing the site of trees and buildings, and moving and compacting 15,-100 cubic yards of earth, with compaction to meet a 95% standard; all for the lump-sum price of $18,500. There was a dispute in the evidence whether Richardson was informed before the job that ES & S was to perform soil compaction tests. Richardson testified that he did not know Collier had hired ES & S to perform tests. Don Collier testified he told Richardson in early September that ES & S would do the testing and that Richardson should coordinate his efforts with Hendren. Shy testified he *369 never discussed with Richardson who had the testing contract.

On or about August 20, 1987, Hendren mailed to Don Collier ES & S’ proposal for providing soil testing services on the Vandi-ver Square project. The proposal contemplated field compaction tests being done over a period of time with each layer or “lift” of soil being tested after it had been placed and compacted. The proposal was received in Collier’s office on August 24, 1987. On September 9, 1987, Don Collier called Hendren and told him that Richardson had been awarded the earth-moving contract, and that he wanted ES & S to do the compaction testing pursuant to its proposal. Don Collier stated to Hendren that he thought Richardson was probably beginning the preliminary scraping, grubbing and demolition work, and that ES & S should proceed to obtain its soil samples in order to be ready for compaction testing when Richardson began filling operations.

There was a conflict in the evidence whether Hendren, on behalf of ES & S, made a special agreement with Don Collier to constantly monitor the site or coordinate with Richardson to ascertain when fill was being placed, in order that compaction tests could be performed at the proper intervals. Hendren testified he did not make such a special agreement. Don Collier testified to the contrary, stating that in the absence of a special agreement, the general rule is that the general contractor notifies subcontractors when their work on the job is needed.

On September 9, 1987, Collier hired Jim Ford (hereinafter “Ford”) to be the building superintendent on the Vandiver Square project. Ford, whose first day on the job was September 14, 1987, reported directly to Don Collier, and served as on-site representative of Collier for the construction project. In the early stages of the project, when the grading and foundation work was being done, Ford was the only Collier on-site employee present on a regular basis. Don Collier himself visited the site every other week. Ford worked only on the Van-diver Square project during its construction. Concurrent with his work on Vandi-ver Square, Don Collier also served as project manager for Fort Zumwalt Square in O’Fallon. According to Don Collier, with respect to minor problems, Ford had the authority to require workmen to change or modify the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Wallace v. Grasso
119 S.W.3d 567 (Missouri Court of Appeals, 2003)
A.G. Edwards & Sons, Inc. v. Drew
978 S.W.2d 386 (Missouri Court of Appeals, 1998)
Landvatter Ready Mix, Inc. v. Buckey
963 S.W.2d 298 (Missouri Court of Appeals, 1997)
McCrary v. Truman Medical Center, Inc.
943 S.W.2d 695 (Missouri Court of Appeals, 1997)
International Minerals & Chemical Corp. v. Avon Products, Inc.
889 S.W.2d 111 (Missouri Court of Appeals, 1994)
O'Connor v. State Farm Mutual Automobile Insurance Co.
831 S.W.2d 748 (Missouri Court of Appeals, 1992)
Safeco Insurance Co. of America v. Stone & Sons, Inc.
822 S.W.2d 565 (Missouri Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
793 S.W.2d 366, 1990 Mo. App. LEXIS 706, 1990 WL 58110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richardson-v-collier-building-corp-moctapp-1990.