Atkins v. Clark

644 S.W.2d 365, 1982 Mo. App. LEXIS 3356
CourtMissouri Court of Appeals
DecidedDecember 21, 1982
DocketWD 33253
StatusPublished
Cited by13 cases

This text of 644 S.W.2d 365 (Atkins v. Clark) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atkins v. Clark, 644 S.W.2d 365, 1982 Mo. App. LEXIS 3356 (Mo. Ct. App. 1982).

Opinion

MANFORD, Presiding Judge.

This is an action for breach of contract. Judgment awarding recovery of monies under the contract is affirmed in part and reversed in part. The cause was certified for assignment to the presiding circuit judge of the 9th judicial circuit. On March 9,1981, the case was assigned to the Honorable George S. Thompson, Associate Circuit Judge.

Three points are presented, which charge the trial court erred in its judgment because (1) the alternatively pleaded causes of action were barred by the statute of limitations; (2) interference with performance was neither pleaded nor proven, thus there was no basis for such finding by the trial court in support of the judgment; and (3) there was no evidence to support the trial court’s finding and assessment of damages.

Pertinent facts will be developed within the discussion and disposition of appellant’s charged error. It suffices to state at this point that the parties entered into a written contract on April 10, 1971 wherein respondent (hereinafter referred to as plaintiff) promised to construct a road, dig a new creek channel, relocate a bridge, fill a hole and complete incidental work in exchange for which appellant (hereinafter referred to as defendant) promised to pay the total sum of $4,200.00. The terms of payment provided for payment of $1,000.00 when plaintiff located his equipment upon the job site, $500.00 when the bridge was located, and the remaining sum ($2,700.00) to be paid in full sixty days after completion of the construction described in the contract.

*367 Plaintiff commenced work on the job. The first payments ($1,500.00) were made following plaintiff’s location of his equipment at the job site ($1,000.00) and the setting of the bridge ($500.00). Those events and amounts are not in dispute.

This action originated on January 22, 1981, and the petition was in three counts. Count three alleged the performance of other work not associated with the issues in the instant proceedings. This count was dismissed and trial proceeded on the two remaining counts. The first count charged a breach of contract by defendant and full performance by plaintiff, and sought recovery of the remaining balance of $2,700.00. Count two sounded in quantum meruit, alleging that plaintiff had partially performed, that defendant had prevented full performance, that the balance had not been paid, and that plaintiff was entitled to the full balance of $2,700.00. Defendant filed a general denial by way of an amended answer. Defendant then filed a motion to dismiss and a motion for summary judgment as to the remainder of plaintiffs petition (counts I & II). The basis for both motions was that the claims under both counts were barred by the five-year statute of limitations. Both motions were overruled and both counts tried to the court without a jury. The court entered judgment for plaintiff in the sum of $1,860.00. This appeal followed.

Under point (1), defendant charges that the trial court erred in failing to sustain his motion to dismiss or his motion for summary judgment because the claims of plaintiff were barred by the statute of limitations. Defendant contends specifically that plaintiff’s claim of damages does not rest upon a contract in writing for the payment of monies or property, and hence under our statutes (§§ 516.110/516.120), the claims were viable for only five years.

Suit was filed nine years, nine months and 12 days following execution of the contract. Defendant contends that disposition of this case squares with the ruling in Parker-Washington Co. v. Dennison, 267 Mo. 199, 183 S.W. 1041 (1916). We cannot agree.

Defendant contends correctly that Parker declared that since the contract had to be completed before any money was due, a plaintiff was left to sue for damages in implied assumpsit (and barred if not brought within five years). However, Parker also points out:

“In order to bring an ‘action upon any writing for the payment of money or property,’ it must appear in the statement of the cause of action that the money or property sued for is promised to be paid or given by the language of the writing, and that such promise does not arise only upon proof of extrinsic facts.” 183 S.W. loc. cit. at 1042.

In Parker, the payment of monies (if any) were to be ascertained only if certain conditions were met. The amount and determination of payment relied solely upon “proof of extrinsic facts.” This is not the situation herein.

Plaintiff sued on the contract in Count I, attaching to his petition the agreement between the parties. It is correct that plaintiff alleged full performance and sought full recovery of the balance of the $2,700.00. The contract in the instant case, without reliance on “proof of extrinsic facts”, clearly expresses a promise to pay a sum certain within the written terms of the agreement or contract. Neither Parker nor § 516.120 control. Rather, if an obligation to pay money is found by fair implication from the writing, an action thereon may be brought within ten years. South Side Realty Co. v. Hamblin, 387 S.W.2d 224 (Mo.App.1964). We find that the contract herein was a promise to pay a sum certain and the action could be maintained within ten years. Alternatively, as to plaintiff’s claim upon quantum meruit, it is found that the Statute of Limitations barred that claim. Point (1) is found to be without merit and is ruled against defendant.

Under point (2), defendant contends that the trial court erred in finding that he interfered with the completion of the work called for in the contract. Defendant’s contention rests upon two points. First, de *368 fendant urges that plaintiff never pleaded interference under Count I. Secondly, defendant contends that there is no evidence that defendant told the plaintiff not to do any of the work or that although others told the plaintiff certain work was forbidden, the evidence reveals that this fact was never communicated to defendant.

It is correct, as contended by defendant, that Count I of the petition does not allege interference by the defendant. The petition in Count II, however, does make such allegation, and declares, “and would have completed the same according to the terms of said contract, but that the defendant (sic) 1 was not permitted to do part of the work referred to in paragraph 1(a) ...”

Plaintiff counters defendant’s first attack on the court’s finding by pointing out that this action first arose in the associate circuit court, wherein formal pleadings are not required. See § 517.050, RSMo 1978. The case was then removed to the circuit court and tried to the court without a jury. Plaintiff further points out, by way of answer to defendant’s interrogatories, that he did not complete the work and that non-completion was the result of acts and omissions of the defendant.

What occurred is the issue of non-completion of the work because of defendant’s interference which was, in fact, not pleaded. Nor was the defense of the Statute of Limitations pleaded by the defendant. Nevertheless, the issue was actually tried to the court by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R. F. v. Texas Department of Family and Protective Services
390 S.W.3d 63 (Court of Appeals of Texas, 2012)
Richardson v. Collier Building Corp.
793 S.W.2d 366 (Missouri Court of Appeals, 1990)
McDonald County Mercantile Bank v. Harp
779 S.W.2d 21 (Missouri Court of Appeals, 1989)
State Automobile & Casualty Underwriters v. Johnson
766 S.W.2d 113 (Missouri Court of Appeals, 1989)
Slay Warehousing Co. v. Leggett
762 S.W.2d 63 (Missouri Court of Appeals, 1988)
Farm Bureau Town & Country Insurance Co. of Missouri v. Franklin
759 S.W.2d 361 (Missouri Court of Appeals, 1988)
Sur-Gro Finance, Inc. v. Smith
755 S.W.2d 439 (Missouri Court of Appeals, 1988)
Eckelkamp v. Eckelkamp
741 S.W.2d 312 (Missouri Court of Appeals, 1987)
St. Charles County v. McPeak
730 S.W.2d 611 (Missouri Court of Appeals, 1987)
Weber v. Knackstedt
707 S.W.2d 800 (Missouri Court of Appeals, 1986)
Statler Manufacturing, Inc. v. Brown
691 S.W.2d 445 (Missouri Court of Appeals, 1985)
Estate of Graves
684 S.W.2d 925 (Missouri Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
644 S.W.2d 365, 1982 Mo. App. LEXIS 3356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atkins-v-clark-moctapp-1982.