Ark Construction Co. v. City of Florissant

558 S.W.2d 418, 1977 Mo. App. LEXIS 2340
CourtMissouri Court of Appeals
DecidedSeptember 6, 1977
Docket37749
StatusPublished
Cited by12 cases

This text of 558 S.W.2d 418 (Ark Construction Co. v. City of Florissant) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ark Construction Co. v. City of Florissant, 558 S.W.2d 418, 1977 Mo. App. LEXIS 2340 (Mo. Ct. App. 1977).

Opinion

REINHARD, Judge.

Defendant City of Florissant appeals from a judgment in favor of plaintiff Ark Construction Company from a suit on a construction contract between the two parties. Plaintiff was awarded damages in the amount of Twelve Thousand Two Hundred Eighty Two and 89/100 Dollars ($12,282.89).

On the 14th day of August, 1973, plaintiff Ark Construction Company entered into a contract with the City of Florissant whereby plaintiff contractor was to construct sidewalks, curbs and do related work in Florval Drive, St. Celeste Drive and Marquette Drive in the City of Florissant, St. Louis County, Missouri, according to the plans and specifications set out in the contract. The total bid on the project for the various work as submitted by Ark and accepted by the City was Eleven Thousand Six Hundred Ninety-Two Dollars ($11,-692.00). Pursuant to change orders authorized under the contract for additional rock and additional asphalt, the contract price was increased to Twelve Thousand Two Hundred Eighty Two and 89/100 Dollars ($12,282.89).

The contract provided that the work under the contract was to be completed within ninety (90) calendar days from and includ *420 ing the date of commencement. The contract expressly stated that time was of the essence and that the time of completion was an essential condition of the agreement. Other provisions of the contract will be specifically discussed as they are relevant.

There is some uncertainty as to the date of commencement of work by Ark; however it appears from the evidence that the completion date was November 27, 1973. Plaintiff failed to complete the contract work prior to this date. As to its failure in completing the work within the first 90 days, plaintiff offered testimony that the city engineer, Doug Hopkins, after work on the project had begun, ordered various changes raising by four inches the grade of the sidewalks, altering the radii of the driveways to be laid, and various other changes. Plaintiff’s witnesses also testified that these various changes ordered by Hopkins took time and caused delay in the performance of the work. Paragraph 15 of General Conditions in the contract provided that:

“In giving instructions, the Engineer shall have authority to make minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the work, but otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order by the Engineer, and no claim for an addition to the Contract Sum shall be valid unless so ordered.”

Other than the written orders for more crushed rock and more asphalt no written change orders were issued.

The contract also provided that extensions of time for completion of the work could be granted pursuant to a written request for extension due to delays for various causes beyond the contractor’s control. Pursuant to this provision, on November 20, 1973, Ark requested a 10-day extension until December 7, 1973. This extension was granted by the defendant. As of December 7, 1973, plaintiff had not completed the work under the contract. Willie Smith, the President of Ark, testified that the failure to complete the work during this extension period was due to bad weather and delay in materials.

Sometime during the period in which the contract was still in force, the plaintiff subcontracted with Glenn Construction Co. to do some of the work on the sidewalks. It is unclear from the record whether Glenn performed its work prior to or after the December 7 completion date.

On December 19, 1973, the defendant sent plaintiff a letter stating that plaintiff was well past the time for completion provided in the contract and that the work was incomplete and unsatisfactory. The letter stated that, pursuant to the provisions of the contract, the City planned to terminate the contract and that the letter was to serve as notice to Ark that upon completion of the seven-day notice period, the City intended to hire another contractor to finish the project. Paragraph 22 of the General Conditions of the contract provided that the owner was to have the right to terminate the contract “[i]f the Contractor should * * * cease operations under this Contract at any time for the space of ten (10) days, or otherwise be guilty of a substantial violation of any provision of the Contract, * * * The provision further gave the owner the right, upon seven (7) days written notice, to take possession of the premises and finish the work by whatever method it might deem expedient. The paragraph also provided that upon such termination “the Contractor shall not be entitled to receive any further payment until the work is finished” and that “[i]f the unpaid balance of the Contract Sum shall exceed the expense of finishing the work, * * * such excess shall be paid to the Contractor.”

After the December 19th letter from the City to Ark, the next correspondence between these unusually non-communicative parties was in the form of a letter dated February 5, 1974, from the City to Ark terminating the contract pursuant to the provisions outlined in Paragraph 22 of the General Conditions. The defendant’s delay in terminating the contract after the December 19 letter is unexplained.

*421 On February 27, 1974, defendant contracted with Baumann Construction Company, Inc. for completion of the work on the project. Under the contract, Baumann was to remove 175 feet of sidewalk as laid by plaintiff and lower it to conform to the original plans. They were also to remove and repave 12 concrete drive approaches with four foot radii, lay some asphalt for proper drainage, place rock in the drives as needed, adjust a manhole, and perform various other landscaping and finishing activities. The price of the contract between Baumann and the defendant was Eight Thousand Six Hundred Fifty and 80/100 Dollars ($8,650.80). Full payment on this contract was made to Baumann.

On February 11, 1974, plaintiff instituted suit on the contract alleging performance of the contract and breach by defendant for failure to pay any sums under the contract. It further alleged that any delay in the performance of the work was due to the conduct of defendant. Plaintiff’s second count was in quantum meruit. Defendant denied full performance by plaintiff and sought as a set-off any sums reasonably expended by the City to complete the contract work according to the plans and specifications. Defendant also brought a counterclaim for liquidated damages pursuant to provisions in the contract. The trial judge dismissed plaintiffs Count II on quantum meruit at the close of all the evidence. A jury rendered a verdict for the full amount of the contract price for plaintiff, and found against defendant on both its set-off and counterclaim.

The defendant asserts that the trial court erred in failing to direct a verdict for defendant on plaintiff’s claim for recovery under the contract because plaintiff failed to show that it had complied with all the provisions of the contract. In reviewing the denial of a motion for a directed verdict at the close of plaintiff’s case and at the close of all the evidence, the appellate court is to view the evidence in the light most favorable to plaintiff, giving plaintiff all reasonable inferences therefrom and so viewing the evidence to determine whether a submissible case was made. Woodford v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bmk Corp. v. Clayton Corp.
226 S.W.3d 179 (Missouri Court of Appeals, 2007)
Ex Parte Woodward Const. & Design, Inc.
627 So. 2d 393 (Supreme Court of Alabama, 1993)
Winn-Senter Construction Co. v. Katie Franks, Inc.
816 S.W.2d 943 (Missouri Court of Appeals, 1991)
Fort Zumwalt School District v. Recklein
708 S.W.2d 754 (Missouri Court of Appeals, 1986)
Hart and Son Hauling, Inc. v. MacHaffie
706 S.W.2d 586 (Missouri Court of Appeals, 1986)
Berra v. Papin Builders, Inc.
706 S.W.2d 70 (Missouri Court of Appeals, 1986)
Statler Manufacturing, Inc. v. Brown
691 S.W.2d 445 (Missouri Court of Appeals, 1985)
Seuf, Inc. v. Bartlett
665 S.W.2d 31 (Missouri Court of Appeals, 1984)
Atkins v. Clark
644 S.W.2d 365 (Missouri Court of Appeals, 1982)
Fieser Services, Inc. v. Saline Sewer Co.
643 S.W.2d 92 (Missouri Court of Appeals, 1982)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
Dicon, Inc., a Corporation v. Marben Corporation
618 F.2d 40 (Eighth Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
558 S.W.2d 418, 1977 Mo. App. LEXIS 2340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ark-construction-co-v-city-of-florissant-moctapp-1977.