Artcraft Cabinet, Inc. v. Watajo, Inc.

540 S.W.2d 918
CourtMissouri Court of Appeals
DecidedJuly 6, 1976
DocketKCD 27185
StatusPublished
Cited by20 cases

This text of 540 S.W.2d 918 (Artcraft Cabinet, Inc. v. Watajo, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Artcraft Cabinet, Inc. v. Watajo, Inc., 540 S.W.2d 918 (Mo. Ct. App. 1976).

Opinion

SHANGLER, Presiding Judge.

The plaintiff ArtCraft, Inc. sued Summit Homes [a commonalty of eight domestic corporations doing business as a general partnership] for a mechanic’s lien and contract damages. Summit counterclaimed for breach of contract. The causes were tried to the court and a judgment was returned for ArtCraft for $33,050.56 and against Summit on the counterclaim. The court also found that ArtCraft had abandoned its pleading for a lien on the premises.

The defendant Summit, as general contractor, planned the construction of the Glendale Gardens apartment complex in Independence, Missouri. ArtCraft, a manufacturer of prefabricated cabinets, bid on the project, and on October 29, 1970, was awarded the subcontract to provide and install kitchen and bath vanities for 280 apartment units and a clubhouse. Shop drawings prepared by ArtCraft had been submitted to Summit with the bid. The total contract price was $89,595.

The contract provided in paragraph III for ArtCraft “[t]o begin the work herewith contracted for as soon as the project upon which the work required is ready for such or within 10 calendar days after the contractor has given notice of work or material requirements and to complete the several portions of the whole thereof within the time or times following namely: . . . ”. The blank space which ensued was not completed.

In January of 1971, the various subcontractors [including the plaintiff ArtCraft] met with the Summit representative to establish the production schedule. According to this schedule, ArtCraft was to start installation in building 12 of the complex on March 18,1971, and was to follow the painters and trim carpenters who were to have finished by that date. ArtCraft was to be allowed ten working days to complete the job. Instead, the first delivery of cabinets by ArtCraft did not take place until May 11.

*921 The project had not started on schedule and Jones, the Summit general manager, testified that the apartment units in building 12 were probably not ready for cabinets on March 18. ArtCraft had made field measurements in March and found that there was no sheetrock on the walls and that the building was definitely not ready for the installation of cabinets. According to Jones, building 12 was finally ready for cabinets in early April and so informed ArtCraft by telephone. Jones wrote to Allison, the ArtCraft sales representative, on April 6 that plaintiff was to begin installation on April 14, 1971. ArtCraft, however, could not properly proceed with fabrication of the cabinets until the shop drawings were approved. They had been submitted with the bid and remained with Summit until April; they had not been returned either approved or disapproved, by the architect. In another letter to ArtCraft, this one dated April 22, 1971, Jones informed ArtCraft that their drawings had not been approved and would have to be resubmitted. Jones added that time was of the essence, since time for installation was nearly at hand.

ArtCraft sales representatives Allison and Cotton, who did cost analysis and field measurements for the plaintiff, met with the Summit architect and drawings were devised to the satisfaction of the architect. They were ultimately approved by Richardson, the Summit job superintendent. As of May 4, 1971, however, ArtCraft had yet to receive approval of the shop drawings and on that date Cotton wrote Summit that until such was forthcoming, ArtCraft could not manufacture any cabinets. That same day [in a letter which crossed], Jones wrote ArtCraft that Summit would treat the contract as breached unless the plaintiff was on site for installation work on May 5.

It was the testimony of Ms. McGauvran, ArtCraft president, that Jones telephoned her on May 5 or 6 and intimated that Art-Craft was unable to furnish the cabinets for the project as agreed. She, in turn, insisted the work would be done but that approved drawings were needed first. It was her testimony [not recalled by Jones] that he agreed to guarantee the drawings would be sent if ArtCraft delivered the cabinets. Ms. McGauvran acceded to a May 11 delivery date and confirmed this commitment by telegram that day. Thus, although the approval of the architect was not received, the cabinets were manufactured and delivered on May 11 as agreed.

The vexations, however, did not abate. The first site for installation, building 12, did not conform to the original plans and specifications, nor were the floors level. These presented difficulties for the Art-Craft installers. Also, the painters and trim carpenters were still working in the units. ArtCraft service manager, Gill testified that when the cabinets were delivered to the individual units in building 12, the carpenters had some “moulding and stuff laid on the floor, and they were mad because we were in their way”. This confusion created hard feelings so that the other artisans moved the cabinets into other apartments out of the way.

The production schedule allowed Art-Craft 10 working days to install the cabinets. Ms. McGauvran sent Allison to the project to resolve the problems. Allison found that Summit superintendent, Richardson, had employed carpenters to hang the cabinets. Apparently, the ArtCraft cabinet installers had been fired. Gill testified that two ArtCraft installers were present on May 11, the delivery date, and two additional installers appeared the next day. When Gill returned to the site three days later, these men had been replaced by two men hired by Jones, the Summit general manager. Jones testified the ArtCraft installers did not know what they were doing. According to Jones, he had been granted authority from Ms. McGauvran to terminate the men and hire the other two. Ms. McGauvran testified she had never instructed Jones to fire any installer working for ArtCraft.

*922 The two installers employed by Jones worked for a short time and then quit, disaffected because the cabinet components were in disarray, scattered throughout the apartments where they had been moved by the other artisans. Allison placed an advertisement in the Kansas City Star for installers; several men responded and three were eventually hired and worked on the project until Summit terminated the ArtCraft contract. [There was testimony from Summit that none of the ArtCraft installers lasted long on the job and no crew worked continuously.]

The most formidable obstacle facing the ArtCraft installers resulted from a drafting error involving a number of the kitchens: the architectural plans did not allow sufficient room for the gas ranges. The result was that the dishwasher door in these kitchens would not fully open and ArtCraft had to redesign 10 cabinets. The cabinets from these kitchens were returned to the Art-Craft plant and reworked while others were replaced by new cabinets. This additional expense was calculated to be $2000.

Jones informed McGauvran by letter of June 10,1971, that ArtCraft was in default and that if qualified installers were not on the job on June 11, Summit would consider the contract breached. [According to the terms of this letter, Summit had put its own carpenters on the installation of cabinets on June 10.] In response, the ArtCraft attorney wrote Jones on June 17 in which he charged that the use by Summit of their carpenters without a prior 48-hour notice to ArtCraft violated paragraph XVI of the subcontract:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matt Miller Co. v. Taylor-Martin Holdings, LLC
393 S.W.3d 68 (Missouri Court of Appeals, 2012)
Inauen Packaging Equipment Corp. v. Integrated Industrial Services, Inc.
970 S.W.2d 360 (Missouri Court of Appeals, 1998)
Hawkins v. Foster
897 S.W.2d 80 (Missouri Court of Appeals, 1995)
Hastings & Chivetta Architects v. Burch
794 S.W.2d 294 (Missouri Court of Appeals, 1990)
Standard Improvement Co. v. DiGiovanni
768 S.W.2d 190 (Missouri Court of Appeals, 1989)
Tony Thornton Auction Service, Inc. v. Quintis
760 S.W.2d 202 (Missouri Court of Appeals, 1988)
Jetco Heating & Air Conditioning, Inc. v. Spizman
735 S.W.2d 54 (Missouri Court of Appeals, 1987)
Oates v. Centerre Trust Co. of St. Louis
729 S.W.2d 566 (Missouri Court of Appeals, 1987)
Dudley v. St. Regis Corp.
635 F. Supp. 1468 (E.D. Missouri, 1986)
Hart and Son Hauling, Inc. v. MacHaffie
706 S.W.2d 586 (Missouri Court of Appeals, 1986)
Liberty Financial Management Corp. v. Beneficial Data Processing Corp.
670 S.W.2d 40 (Missouri Court of Appeals, 1984)
Alaska Children's Services, Inc. v. Smart
677 P.2d 899 (Alaska Supreme Court, 1984)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
Smith v. Morgan Drive Away, Inc.
613 S.W.2d 469 (Missouri Court of Appeals, 1981)
Wilson v. Farrow
583 S.W.2d 545 (Missouri Court of Appeals, 1979)
S. G. Adams Printing & Stationery Co. v. Central Hardware Co.
572 S.W.2d 625 (Missouri Court of Appeals, 1978)
Ark Construction Co. v. City of Florissant
558 S.W.2d 418 (Missouri Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
540 S.W.2d 918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/artcraft-cabinet-inc-v-watajo-inc-moctapp-1976.