Dudley v. St. Regis Corp.

635 F. Supp. 1468, 1986 U.S. Dist. LEXIS 24078
CourtDistrict Court, E.D. Missouri
DecidedJune 17, 1986
Docket85-1584C(1)
StatusPublished
Cited by2 cases

This text of 635 F. Supp. 1468 (Dudley v. St. Regis Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dudley v. St. Regis Corp., 635 F. Supp. 1468, 1986 U.S. Dist. LEXIS 24078 (E.D. Mo. 1986).

Opinion

635 F.Supp. 1468 (1986)

Thomas DUDLEY, et al., Plaintiffs,
v.
ST. REGIS CORPORATION, Defendant.

No. 85-1584C(1).

United States District Court, E.D. Missouri, E.D.

June 17, 1986.

*1469 Keith C. Zagar, Dubail, Judge Kilker O'Leary & Smith, St. Louis, Mo., for plaintiffs.

Kenneth R. Heineman, Dale R. Joerling, Coburn Croft & Putzell, St. Louis, Mo., for defendant.

MEMORANDUM

NANGLE, Chief Judge.

In this action, plaintiffs seek to recover lost profits due to a breach of a written contract to refurbish a portion of the roof on defendant's factory. The case was tried to the Court sitting without a jury. The Court having considered the pleadings, the testimony of the witnesses, the documents in evidence, and the stipulations of the parties, and being fully advised in the premises, hereby makes the following findings of fact and conclusions of law, as required by Rule 52 of the Federal Rules of Civil Procedure. Fed.R.Civ.P. 52.

FINDINGS OF FACT

1. St. Regis Corporation was, at the time relevant to this lawsuit, a New York corporation. On January 31, 1985, St. Regis was merged into Champion International Corporation, a New York corporation with its principal place of business in Connecticut. Champion is the successor in interest to St. Regis.

2. The Dudleys, d/b/a Basic Roofing Systems, are Missouri residents, with a business office in St. Louis County, Missouri. Basic Roofing has been in existence since May, 1983. For several years prior to that time, Thomas Dudley owned and operated Dudley Roofing.

3. On February 20, 1984, the parties entered into a written contract for the repair/replacement of the southwest quadrant of the roof on St. Regis' envelope plant, located in O'Fallon, Missouri. The contract provided that the work was to be completed between March 1, 1984 and June 1, 1984.

4. The specifications for the roof repair were prepared by St. Regis. The plans called for the installation of a Firestone EPDM single-ply roofing system. St. Regis' major concern was that the Firestone system would be installed according to the manufacturer's specifications. This was to insure that the roof would be covered under Firestone's warranty program.

5. On or about April 29, 1984, a wind and thunderstorm caused substantial damage to the southeast quadrant of the roof. There was no damage to the southwest quadrant. At some time prior to this storm, the southeast section had been refurbished and a Firestone EPDM single-ply system had been installed on that quadrant.[1]

*1470 6. Immediately following the storm, St. Regis informed the Dudleys of the damage to the southeast quadrant of the roof. St. Regis also directed the Dudleys to stop work on the southwest quadrant until defendant's engineering department could evaluate the roofing system.

7. At the time of the work stoppage, plaintiffs did not incur any costs or obligations for labor and materials for the southwest quadrant except for approximately 40 hours expended in preparing the estimate and negotiating the terms of the contract.

8. On August 27, 1984, after evaluating the roofing specifications, St. Regis informed plaintiffs by letter that it was cancelling the contract.

9. The parties stipulated that to perform the work under the contract, the plaintiffs would have expended $55,293.00 for materials, labor, patchwork and other charges. Plaintiffs would have realized $27,707.00 in overhead and profit from the project. The parties further stipulated that said amount of overhead and profit was reasonable for this type of work.

CONCLUSIONS OF LAW

This Court has jurisdiction in this matter under 28 U.S.C. § 1332. Venue is proper within this District.

The parties have stipulated to the written agreement at issue in this case. The terms and conditions section provides, in pertinent part:

11. CANCELLATION: In the event the Owner decides not to proceed with the work, though the Contractor is not at fault and subject to provisions of Section 10. above, the Owner may terminate this agreement at any time upon written notice to the Contractor, thereupon the Owner's only liability shall be to pay to the Contractor all costs for labor and materials incorporated in the work prior to termination and all costs incurred in discharging outstanding obligations of the Contractor at the request of the Owner, and a reasonable overhead and profit, less any previous payments made hereunder or amount of claims of Owner against Contractor.

It is plaintiffs' position that, upon termination of the contract by the defendant, the cancellation provision provides for recovery of the reasonable overhead and profit that would have been earned had the contract been completed.[2] The Court agrees. Under Missouri law, the general rule for damages as a result of a breach of contract is that the non-breaching party is entitled to that which places him in the position he would have been but for the breach. United Industrial Syndicate, Inc. v. Western Auto Supply Co., 686 F.2d 1312, 1316 (8th Cir.1982); Boten v. Brecklein, 452 S.W.2d 86, 93 (Mo.1970); Artcraft Cabinet, Inc. v. Watajo, Inc., 540 S.W.2d 918, 924 (Mo.App. 1976). The amount of damages would include any outlays as well as the anticipated profits the party would have reasonably made from the contract. 686 F.2d at 1316. The cancellation provision in the contract states the general damage rule and provides for recovery of $27,707.00 as a reasonable profit, see Findings of Fact No. 9.

Defendant attempts to argue that the clause "and a reasonable overhead and profit" applies only to the cost of labor and materials already expended at the time of cancellation. The Court finds defendant's position unsupported by the plain language *1471 of the agreement. There is nothing to indicate that the overhead and profit clause is restricted only to costs already incurred at the time of the cancellation. Moreover, such an interpretation would be a significant departure from the general rule on damages. The Court finds nothing to support such a reading of the contract. Accordingly, the Court rejects defendant's restrictive reading of the agreement.

Defendant raises, as an affirmative defense, the argument that its obligations under the written contract were excused under the doctrine of commercial frustration. In Howard v. Nicholson, 556 S.W.2d 477, 481-82 (Mo.App.1977), the court explained the doctrine as follows:

Under the doctrine, if the happening of an event not foreseen by the parties and not caused by or under the control of either party has destroyed or nearly destroyed either the value of the performance or the object or purpose of the contract, then the parties are excused from further performance. The doctrine of commercial frustration is close to but distinct from the doctrine of impossibility of performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Felt v. McCarthy
922 P.2d 90 (Washington Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
635 F. Supp. 1468, 1986 U.S. Dist. LEXIS 24078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dudley-v-st-regis-corp-moed-1986.