Sunny Baer Co., Inc. v. Slaten

623 S.W.2d 595, 1981 Mo. App. LEXIS 3067
CourtMissouri Court of Appeals
DecidedOctober 20, 1981
Docket41767
StatusPublished
Cited by12 cases

This text of 623 S.W.2d 595 (Sunny Baer Co., Inc. v. Slaten) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunny Baer Co., Inc. v. Slaten, 623 S.W.2d 595, 1981 Mo. App. LEXIS 3067 (Mo. Ct. App. 1981).

Opinion

SATZ, Presiding Judge.

In this cause, Sunny Baer Co., Inc., sued defendants, William and Ossie Slaten, for breach of contract. Under the terms of the contract, plaintiff was to repair defendants’ fire-damaged building for $4,800. Defendants paid plaintiff only $2,500. In its suit, plaintiff alleged complete performance of the contract and sought the $2,300 balance due on the contract price. 1 Defendants counterclaimed. Defendants alleged that plaintiff failed to perform up to contract standards and sought damages resulting from plaintiff’s breach. The jury returned a verdict against plaintiff on its claim and returned a verdict in favor of defendants on their counterclaim in the amount of $2,500.

Plaintiff raises several points on appeal. Only one of these points has merit. That point goes to the issue of damages only. All of plaintiff’s other points would require a reversal and remand for an entire new trial. Those points, however, are without merit. Accordingly, for the reasons which follow, we reverse and remand for a new trial on the issue of damages only.

We first address plaintiff’s asserted grounds which would require an entire new trial. Plaintiff argues the jury verdicts were against the weight of the evidence. This ground is not cognizable on appeal. “Whether a jury’s verdict is against the weight of the evidence is a question for the trial court alone.” Wilcox v. Coons, 362 Mo. 381, 241 S.W.2d 907, 917 (1951); Neavill v. Klemp, 427 S.W.2d 446, 450 (Mo.1968).

Plaintiff next contends MAI 2.02, the “facts not assumed” instruction, 2 was not given in proper order. At the time of trial, this instruction was required to be given as the next to last instruction, “immediately before the Form of Verdict Instruction.” MAI 2.02, Notes on Use (1980 Supp.). In the present case, the instruction was given fifth among twelve instructions. Plaintiff claims the failure to follow MAI was prejudicial error and cites Crystal Tire Co. v. Home Service Oil Co., 525 S.W.2d 317 (Mo. banc 1975) as controlling. Contrary to plaintiff’s contention, however, subsequent decisions narrowly limited the meaning of Crystal Tire and the recent revision of MAI rendered Crystal Tire meaningless.

Crystal Tire involved multiple defendants with numerous cross claims. In that case, MAI 2.02 was given as the second instruction among twenty-two other instructions. The complexity of the issues and the number of instructions in Crystal Tire may well have required a rigid adherence to the sequence in which MAI 2.02 had to be given. Subsequent decisions, however, have demonstrated this sequence may be varied without prejudice in less complex cases. E. g., Morse v. Johnson, 594 S.W.2d 610, 616 (Mo. banc 1980); Doyle v. St. Louis — S.F. Ry. Co., 571 S.W.2d 717, 724-725 (Mo.App.1978). In the present case, there were only two claims and MAI 2.02 was given fifth among twelve instructions. This sequence could not have misled the jury. Salsberry v. Archibald Plumbing and Heating Co., 587 S.W.2d 907, 916 (Mo.App.1979). Furthermore, MAI now recognizes that the sequential order of this instruction is best left to the good sense and sound discretion of the trial judge. MAI 2.02, Notes on Use (1980 Revision). Plaintiff was not prejudiced by the sequence of instructions here.

*597 Plaintiff also attacks several other instructions. Plaintiff complains that defendants were allowed two converse instructions against plaintiff’s single verdict director. Plaintiff fails to designate the offending instructions. We assume plaintiff refers to Instructions 7 and 8 which were similarly worded. 3 These are not, however, two converse instructions. Instruction 7 is a proper converse to plaintiff’s verdict director and Instruction 8 is plainly the defendants’ verdict director on their counterclaim. Thus, there was no error in giving these two instructions.

Plaintiff also argues the court used an instruction submitted by defendants as plaintiff’s verdict director. No assertion is made that the instruction was erroneous. In any event, the record clearly shows plaintiff’s verdict director, Instruction 6, was submitted by the court. 4

Plaintiff next complains because the names of the parties were used in the instructions. The use of the name of a party in an instruction instead of the term “plaintiff” or “defendant” is expressly authorized. MAI, How to Use This Book, Use Of Terms Plaintiff and Defendant (1981). Thus, the use of the parties’ names in the present instructions was not error. Price v. Bangert Brothers Road Builders, Inc., 490 S.W.2d 53, 57 (Mo.1973).

Plaintiff’s final complaint does have merit. Plaintiff complains there was no substantial evidence to support the measure of damages submitted by defendants. We agree.

Defendants’ theory of recovery was breach of contract. In breach of contract cases, the goal of compensation is to award “a sum which is the equivalent of performance of the bargain — [it is] the attempt to place the [injured party] in the position he would be in if the contract had been fulfilled.” McCormick, Damages, § 137, p. 561 (1935). To achieve this goal when a building repair contractor has breached his contract, two measures of damages are commonly used. “The first measure, called the ‘cost’ rule, is the cost of completing the work promised by the contractor or the cost of repairing it where the work is defective.” Dobbs, Remedies, § 12.21, pp. 897-898 (1973). See, e. g., Burger v. Wood, 446 S.W.2d 436, 442 (Mo.App.1969). The second *598 measure, called the “value” rule, is the difference between the value of the building as promised and its value as actually constructed. See, e. g., Kahn v. Prahl, 414 S.W.2d 269, 282-283 (Mo.1967); Dobbs, supra at p. 897. Apparently, defendants’ instruction on damages was an attempt to submit the cost of repairs as the measure of damages here. 5 Obviously, to compute this damage, the cost of repairing plaintiff’s defective work must first be shown. Defendants did attempt to prove the cost of repairing the defective work through a properly qualified witness, a general contractor, but, for reasons not relevant here, they were unable to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ex Parte Sergio Rodriguez Cuellar
Court of Appeals of Texas, 2015
Dominguez v. PRICE OKAMOTO HIMENO & LUM
205 P.3d 649 (Hawaii Intermediate Court of Appeals, 2009)
Gee v. Payne
939 S.W.2d 383 (Missouri Court of Appeals, 1997)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
Kincaid Enterprises Inc. v. Porter
758 S.W.2d 503 (Missouri Court of Appeals, 1988)
Fly v. Royal Auto Repair
747 S.W.2d 237 (Missouri Court of Appeals, 1988)
Kozeny-Wagner, Inc. v. Shark
709 S.W.2d 149 (Missouri Court of Appeals, 1986)
Missouri Farmers Ass'n v. Killion
708 S.W.2d 801 (Missouri Court of Appeals, 1986)
Rust & Martin, Inc. v. Ashby
671 S.W.2d 4 (Missouri Court of Appeals, 1984)
Liberty Financial Management Corp. v. Beneficial Data Processing Corp.
670 S.W.2d 40 (Missouri Court of Appeals, 1984)
Brion v. Vigilant Insurance Co.
651 S.W.2d 183 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
623 S.W.2d 595, 1981 Mo. App. LEXIS 3067, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunny-baer-co-inc-v-slaten-moctapp-1981.