Banner Iron Works, Inc. v. Amax Zinc Company, Inc., Banner Iron Works, Inc. v. Amax Zinc Company, Inc.

621 F.2d 883, 28 U.C.C. Rep. Serv. (West) 1046, 1980 U.S. App. LEXIS 18782
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 10, 1980
Docket79-1302, 79-1343
StatusPublished
Cited by8 cases

This text of 621 F.2d 883 (Banner Iron Works, Inc. v. Amax Zinc Company, Inc., Banner Iron Works, Inc. v. Amax Zinc Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Banner Iron Works, Inc. v. Amax Zinc Company, Inc., Banner Iron Works, Inc. v. Amax Zinc Company, Inc., 621 F.2d 883, 28 U.C.C. Rep. Serv. (West) 1046, 1980 U.S. App. LEXIS 18782 (8th Cir. 1980).

Opinion

HEANEY, Circuit Judge.

Banner Iron Works, Inc., contracted to fabricate steelwork to be used in building certain highly specialized equipment for Amax Zinc Company, Inc. Numerous difficulties arose during the performance of the contract, however, and Amax called in other contractors to complete the job. Amax withheld payment to Banner and suit and countersuit were filed.

The circumstances surrounding the formation of the contract were as follows: After meeting with Amax representatives and studying the project plans and specifications, Banner submitted to Amax a written quotation for the steelwork on March 15, 1977. This bid was supplemented by letter of March 16, and a revised bid was submitted on March 22. On March 23, an Amax representative telephoned the Banner engineer assigned to the project, informing him that Amax would sent Banner a purchase order for the steelwork. That order was sent to Banner on March 24 and was signed and returned to Amax on April 1.

On June 13, 1977, Banner wrote a letter to Amax stating that, due to delays in steel delivery from its supplier, Banner “projected” a delivery date for the final steelwork that was two weeks later than the delivery date called for in the purchase order. Amax responded in writing about two days later, granting the two-week extension requested by Banner. On August 9, Banner requested an additional one to two-week extension for delivery of the steelwork. Amax denied the request and notified Banner that it was terminating part of the contract and assigning the work to other contractors. Amax contracted with various other companies to complete the contract work at substantially higher cost.

Amax paid Banner a total of $221,829, withholding $114,000 of the total contract price of $335,829. Banner maintained that it had supplied all of the materials and approximately eighty-five percent of the labor called for in the contract. It estimated the value of the remaining fifteen percent of the labor to be $27,687 and, there *886 fore, claimed that $86,313 was due under the contract.

Banner brought suit to recover the contract price or, in the alternative, to recover in quantum meruit for the labor and materials supplied. Amax counterclaimed for breach of contract, claiming it had paid $206,547 to other contractors to complete the work that Banner was obligated to perform. The jury returned a verdict in favor of Banner in the amount of $75,000 on its quantum meruit claim and in favor of Amax in the amount of $150,000 on its counterclaim, leaving Amax with a net recovery of $75,000. Both parties appealed.

I

Banner’s first contention on appeal is that the district court erred in refusing to allow closing argument or jury instructions informing the jury that it could find the delivery dates to be conditioned on the securing of steel from April mill rollings. Banner relies on two provisions of its written quotation of March 22,1977. The typewritten portion of the quotation included the following:

Based on a prompt award of a contract and the securing of April mill rollings on items where accumulated tonnages are required, we would begin sequenced deliveries starting August 1, 1977 and complete August 15, 1977.

In addition, a printed notation near the top of the quotation’s first page declared:

All contracts and agreements are contingent upon strikes, differences with workmen, fires, accidents, delays of carriers, rolling mills, and all other delays unavoidable or beyond our control.

Banner’s position is that these terms in the quotation were part of the contract agreed upon by the parties. At least, Banner argues, the jury should have been permitted to find the April mill rolling contingency to be part of the contract.

We disagree. This Court has consistently held that the determination of whether a given set of writings constitutes a valid contract is a question of law to be determined by the Court. See Neff v. World Publishing Co., 349 F.2d 235, 253 (8th Cir. 1965); Canton Cotton Mills v. Southwest Overall Co., 8 F.2d 807, 810 (8th Cir. 1925). Hence, the district court did not err in refusing to submit the mill rolling contingency issue to the jury.

We are also convinced that the district court correctly ruled on the merits of the contingency issue. Banner’s quotation of March 22 was just that — a quotation. Although in some circumstances such a quotation may be construed to be an “offer,” the acceptance of which forms a contract, no evidence of acceptance was presented in this case. In the March 23 telephone call, the Amax representative stated that Amax would send a purchase order to Banner. That purchase order, sent on March 24, was the true “offer” in this case. When Banner officials signed the purchase order and returned it to Amax on April 1, the offer was accepted and the contract formed. Since the terms of that purchase order agreed to by Banner included no mill rolling contingency, neither did the contract.

Moreover, the purchase order contained express terms that clearly show that the delivery dates were not conditional. The order stated:

Award of this contract was contingent upon scheduled deliveries of all purchased items under this order between Aug. 1, 1977 [and Aug. 15,1977 1 ]. Time is of the essence to AMAX due to the critical nature of the ordered parts to AMAX Mfg process. The delivery schedule must be met.

The purchase order also contained the following printed statements:

1. Terms of this purchase order prevail and only a signed consent by us will be binding if your terms are in conflict with the terms stated on the reverse side of this order.
* * * * * *
2. a. The purchase Order and these General Terms and Conditions from [sic] the entire contract between the parties, *887 and no variation thereof, irrespective of the wording or terms of the Seller’s proposal or acceptance of the order, will be effective unless specifically agreed to in writing by the Purchaser.
# # # * # *
7. If any of the provisions of Seller’s proposal or Seller’s other writing are in conflict with the terms of this purchase order, the terms of this purchase order shall govern.

These terms leave no doubt that the purchase order was intended to embody the final agreement between the parties and that the agreement required prompt delivery without providing a mill rolling contingency.

Furthermore, there is an alternative but equally compelling reason for refusing to hold that the delivery dates were subject to a mill rolling contingency: new terms relating to delivery dates were later agreed to by both parties. Banner’s June 13 letter “projected” the need for a two-week extension due to problems with the steel supply. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
621 F.2d 883, 28 U.C.C. Rep. Serv. (West) 1046, 1980 U.S. App. LEXIS 18782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/banner-iron-works-inc-v-amax-zinc-company-inc-banner-iron-works-inc-ca8-1980.