Kozeny-Wagner, Inc. v. Shark

709 S.W.2d 149, 1986 Mo. App. LEXIS 4088
CourtMissouri Court of Appeals
DecidedMay 6, 1986
DocketNos. 49506, 50093
StatusPublished
Cited by10 cases

This text of 709 S.W.2d 149 (Kozeny-Wagner, Inc. v. Shark) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kozeny-Wagner, Inc. v. Shark, 709 S.W.2d 149, 1986 Mo. App. LEXIS 4088 (Mo. Ct. App. 1986).

Opinion

SIMON, Judge.

In this consolidation of the appeals from the Circuit Court of St. Louis County, Koz-eny-Wagner, Inc. (plaintiff) and Joseph Shark (defendant) appeal the rulings of the trial court setting aside the stay of plaintiff’s claim and the sustainment of plaintiff’s motion for directed verdict on defendant’s counterclaim.

Plaintiff’s claim arises out of a contract executed by the parties in 1972 whereby plaintiff was to construct a two story pharmacy and office building on defendant’s land in Florissant, Missouri. Specific plans were made to accommodate the building’s structure to a flooding creek located near defendant’s land. Plans for the structure provided that the building be set at an elevation of 512.75 feet based upon the 50 and 100 year high water flood levels of the creek. Construction of the building began in 1973 and continued through the spring of 1974. The building was actually constructed at an elevation 21½ inches below the level provided for by contract. Both parties were unaware of the mistake in elevation until a surveying crew in the area of the jobsite surveyed defendant’s land, at defendant’s request, and informed him of the mistake in elevation. Subsequently, plaintiff confirmed the mistake.

In May of 1974, plaintiff offered to construct an earthen terrace around the building to remedy water problems caused by the improper construction of the building. Defendant rejected this remedy as an unacceptable solution.

The contract provided that plaintiff be paid on a monthly basis for 90% of the cost of labor and materials at the jobsite. Plaintiff discontinued construction in July of 1974. Plaintiff subsequently sued for breach of contract for defendant’s refusal to pay the alleged balance due. Defendant counterclaimed alleging plaintiff’s failure to perform the contract in a workmanlike manner in accordance with the plans and specifications.

On November 14, 1984, plaintiff obtained a jury verdict in its favor on its claim for breach of contract. Plaintiff’s motion for a directed verdict on defendant’s counterclaim was sustained and judgment entered in plaintiff’s favor. On December 7, 1984, defendant’s motion for a new trial on plaintiff’s claim was granted. Defendant’s motion for a new trial on its counterclaim was denied, and on December 17, 1984 defendant filed his notice of appeal of the denial of his counterclaim.

On February 4, 1985, the trial court granted defendant’s motion for a stay of the new trial of plaintiff’s claim, pending appeal of the denial of its counterclaim. Over the objections of both parties and upon its own motion, the trial court set aside the stay of the new trial on March 6, 1985. The court ordered the parties to proceed on the retrial of plaintiff’s claim, stating that the appeal of the directed ver-[151]*151diet on defendant’s counterclaim was premature. On March 20, 1985, the jury returned a verdict on plaintiff’s claim in favor of defendant and judgment was entered accordingly. Subsequently, plaintiff appealed.

On appeal, plaintiff contends that the trial court erred in setting aside the stay of the new trial of plaintiff’s claim on March 6, 1985. Plaintiff asserts that defendant’s notice of appeal was timely filed and the appeal is taken from a final judgment. Therefore, the trial court did not have jurisdiction to set aside the stay of the trial order previously entered.

In his first point on appeal, defendant contends the trial court erred in sustaining plaintiff’s motion for a directed verdict on defendant’s counterclaim. Defendant maintains he made a submissible case of breach of contract for failure to construct the building in a workmanlike manner in accordance with the plans and specifications. Defendant also contends the trial court erred in striking the testimony of defendant’s expert, Harold Helmkampf. Defendant alleges the testimony offered on the cost of raising the building was based upon personal experience and observation, and provided competent and relevant evidence on the issue of damages.

We will first address plaintiff’s points on appeal. Supreme Court Rule 75.01 provides that a trial court retains jurisdiction over judgments for a limited period of thirty days after entry of judgment in the case. The term “entry of judgment” used in the rule, has been interpreted to refer to a final, appealable judgment that disposes of all parties and all issues in a case. Bell v. Garcia, 639 S.W.2d 185, 189 (Mo.App.1982). However, the time limits of Rule 75.01 are not applicable if the judgment is not final and the trial court retains jurisdiction. Ray Nolting Oldsmobile Co. v. 66 Watson Development Co., 518 S.W.2d 167, 169 (Mo.App.1974).

Generally, a final and appealable judgment is one that disposes of all parties and all issues in the case and leaves nothing for future determination, unless the trial court has specifically designated the particular judgment as a final judgment for purposes of appeal. See Rule 81.06. State ex rel. Thompson v. Terte, 357 Mo. 229, 207 S.W.2d 487, 489 (1947); Laclede Gas Co. v. Solon Gershman, Inc., 539 S.W.2d 574, 578 (Mo.App.1976).

A review of the sequence of procedural events in the present case leads to the conclusion that the court properly removed the stay of the new trial and ordered the parties to proceed. First, plaintiff’s motion for a directed verdict was granted on defendant’s counterclaim. Then, defendant’s motion for a new trial on plaintiff’s claim was granted. Defendant subsequently filed notice of appeal of the motion for directed verdict in plaintiff’s favor on defendant’s counterclaim. A stay of the new trial on plaintiff’s claim was entered pending this appeal. The court sua sponte voided this stay and ordered the parties to proceed with a new trial on plaintiff’s claim.

The court properly characterized the appeal of the directed verdict as premature. The plaintiff’s claim and defendant’s counterclaim arose out of the same transaction, the contract to construct defendant’s building. According to Rule 81.06 and the holding in Laclede Gas, the directed verdict ruling on the counterclaim was not final unless the judgment on plaintiff’s claim was final, or the court designated the directed verdict as a final judgment. The record reveals that the court did not designate its ruling on the motion for directed verdict as final. Plaintiff’s separate claim arising out of the same transaction was set for a new trial and was not a final and appealable judgment at that time. Therefore, as judgment on one of the separate claims was not final and appealable, the appeal of the other claim was premature. See also McIntyre v. Seabaugh, 655 S.W.2d 712 (Mo.App.1983); Shores v. Melson, 676 S.W.2d 921 (Mo.App.1984).

The court’s setting aside of the stay of the new trial originally granted was proper. The court retained jurisdiction to [152]*152hear the new trial on plaintiffs claim as the time limits of Rule 75.01 were inapplicable due to the presence of a judgment not yet final and appealable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. St. John's Regional Medical Center
88 S.W.3d 1 (Missouri Court of Appeals, 2002)
Jones v. Grant
75 S.W.3d 858 (Missouri Court of Appeals, 2002)
Crangle v. Crangle
809 S.W.2d 474 (Missouri Court of Appeals, 1991)
Young v. St. Louis University
773 S.W.2d 143 (Missouri Court of Appeals, 1989)
Fairfield Square Development Co. v. Rogalski
767 S.W.2d 626 (Missouri Court of Appeals, 1989)
Baker v. Gordon
759 S.W.2d 87 (Missouri Court of Appeals, 1988)
Kozeny-Wagner, Inc. v. Shark
752 S.W.2d 889 (Missouri Court of Appeals, 1988)
Maxwell v. Maxwell
748 S.W.2d 78 (Missouri Court of Appeals, 1988)
Lick Creek Sewer Systems, Inc. v. Bank of Bourbon
747 S.W.2d 317 (Missouri Court of Appeals, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
709 S.W.2d 149, 1986 Mo. App. LEXIS 4088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kozeny-wagner-inc-v-shark-moctapp-1986.