Rust & Martin, Inc. v. Ashby

671 S.W.2d 4, 1984 Mo. App. LEXIS 3707
CourtMissouri Court of Appeals
DecidedApril 26, 1984
Docket13216
StatusPublished
Cited by15 cases

This text of 671 S.W.2d 4 (Rust & Martin, Inc. v. Ashby) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rust & Martin, Inc. v. Ashby, 671 S.W.2d 4, 1984 Mo. App. LEXIS 3707 (Mo. Ct. App. 1984).

Opinion

*6 PREWITT, Judge.

The principal issue tried was whether plaintiff, who sought recovery of the balance of a contract price from defendants, breached that contract by improperly installing a herringbone pattern Permagrain floor. A jury verdict denied plaintiff any recovery and awarded defendants $3,500 on their counterclaim for breach of contract due to defective performance. Judgment was entered in accordance with the verdict. Plaintiff appeals.

Defendants entered into an agreement with plaintiff for the floor’s installation as a part of the remodeling they were doing to their home. The floor was installed in the kitchen, sunroom, bath and adjacent hallways. The subfloor was installed when plaintiffs installer commenced working. The floor was installed by putting glue on the subfloor and then placing the boards which comprised the floor on the subfloor, with the tongues of the boards inserted into the groove of the boards next to them. Defendants presented evidence that the floor was not properly installed and that to install it properly it would be necessary to tear out the floor and subfloor and reconstruct them. No evidence was offered on the value of the house following the installation of the floor and its value had the floor been properly installed.

In plaintiffs first point, it contends that evidence of the costs of tearing out the existing floor and subfloor and replacing it should not have been allowed as defendants’ proper measure of damages is the difference in value of defendants’ home as the floor was completed and the value of the home as it would have been if the flooring had been properly installed. Plaintiffs second point asserts that the trial court erred in submitting the damage instructions and verdict form to the jury on the counterclaim because there was no evidence to support the proper measure of damages. 1 As presented these points stand or fall together depending upon whether the defendants’ evidence on damages was proper and sufficient to support the verdict. Therefore, we discuss them together.

Relying primarily on Forsythe v. Starnes, 554 S.W.2d 100, 109-110 (Mo.App.1977), plaintiff contends the owner of a building is not allowed to recover from a contractor for the cost of reconstruction and completion in accordance with the contract if this would involve unreasonable economic waste. It contends that tearing up the floor would be unreasonable economic waste.

Forsythe states that in the case of substantial but defective performance the owner is entitled to have the contractor’s recovery reduced by the amount that would reasonably be required to remedy the defects, and make the structure conform to the plans and specifications, unless unreasonable economic waste, that is, “destruction of usable property”, would occur in bringing the structure into conformity with the contract. If such waste would occur, then the owner’s damage must be calculated by the difference between the value of the structure as completed and the value of the structure if it had been constructed according to the contract. For further discussion of these principles, see 5 Corbin, Contracts, § 1089-1091, (1964); Dobbs, Remedies, § 12.21 (1973).

13 Am.Jur.2d, Building and Construction Contracts, § 79, p. 79, states: “The fundamental principle which underlies the decisions regarding the measure of damages for defects or omissions in the performance of a building or construction contract is that a party is entitled to have what he contracts for or its equivalent.” It states that as a general rule the measure of damages is the cost of correcting the defects or completing the omissions, rather than the difference in value between what ought to have been done and what was done, where the correction or completion would not involve unreasonable destruction of the work *7 and the cost of doing so would not be grossly disproportionate to the results to be obtained.

That section, on pages 80 and 81, states that there is authority that the damages for breach of contract in constructing a dwelling, not built in accordance with the plans and specifications, are the costs required to reconstruct it to make it conform to such plans, since, unlike a commercial structure, a dwelling has esthetic value and must be constructed as the owner wants it, even though the finished dwelling may be just as good. As noted in Forsythe, the cases referred to do not include any from Missouri. 13 Am.Jur.2d also states at page 82 that “decorating work”, to which at least the design of this floor was similar, which is worthless, entitles the owner to the expense of redecorating. 2

If we follow Forsythe’s indication that the rule in Missouri is not different as to dwellings, we must determine if tearing out the existing floor and installing a new one would be unreasonable economic waste. Of course, unless hazardous, it is seldom that anything is constructed in such a faulty manner that it could not be used, and we believe the question here must be further narrowed to whether it would be reasonable to use the floor in its condition. What is reasonable to be used in a commercial building may not be reasonable for an owner to tolerate in a residence.

The evidence established that this was an expensive floor that had been rarely installed, if at all, in Southeast Missouri. Plaintiff, whose principal office is in Cape Girar-deau, and its installers had not previously installed this type of floor. There is no claim that the breach was wilful. If there were defects in the installation, they appear to have been caused by plaintiff’s inexperience with this type of floor.

Defendants presented evidence that there were cracks in the floor wide enough that a silver dollar could be inserted in them, apparently with the silver dollar on its edge; that there were uneven places and loose boards in three or four locations; and that the floor “squeaks” when walked upon.

There was testimony that the floor is warped, the middle of the boards are sagging, the ends of some boards are curled up, that there are chips in the floor, and “little square holes where you can see sub-floor.” Defendant Mrs. Ashby said there was a one-sixteenth of an inch difference in the height of some boards and there were gaps between the boards of a sixteenth of an inch “everywhere”. Defendant Mr. Ashby said they were going to replace the floor as soon as they could afford to do so.

By stating that the owner can have the contractor’s recovery reduced by the amount that it would be required to remedy the defects, Forsythe and the other authorities are assuming that other work must have been performed by the contractor that he is entitled to recover for. Here that did not occur, as the contractor’s work, if defendants’ evidence is to be believed, not only did not accomplish its intended purpose, but actually caused additional damage to the house. Apparently the subflooring had been installed when plaintiff’s installer commenced work. Defendants presented evidence that because the boards installed were glued to the sub-floor, the subfloor would have to be torn out and replaced in order to properly reinstall the floor defendants requested.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelley v. Widener Concrete Construction, LLC
401 S.W.3d 531 (Missouri Court of Appeals, 2013)
Henson ex rel. Lincoln v. Board of Education
948 S.W.2d 202 (Missouri Court of Appeals, 1997)
Bray v. Bi-State Development Corp.
949 S.W.2d 93 (Missouri Court of Appeals, 1997)
Riley v. Union Pacific Railroad
904 S.W.2d 437 (Missouri Court of Appeals, 1995)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
White River Development Co. v. Meco Systems, Inc.
806 S.W.2d 735 (Missouri Court of Appeals, 1991)
Kopp v. Franks
792 S.W.2d 413 (Missouri Court of Appeals, 1990)
McPherson Redevelopment Corp. v. Watkins
782 S.W.2d 690 (Missouri Court of Appeals, 1989)
Robinson v. Estate of Robinson
768 S.W.2d 676 (Missouri Court of Appeals, 1989)
McDaniel v. Grady Bros., Inc.
764 S.W.2d 177 (Missouri Court of Appeals, 1989)
Boyer v. Empiregas, Inc. of Chillicothe
734 S.W.2d 828 (Missouri Court of Appeals, 1987)
Mathis v. Glover
714 S.W.2d 222 (Missouri Court of Appeals, 1986)
Hritz ex rel. Hritz v. Slawin
706 S.W.2d 296 (Missouri Court of Appeals, 1986)
Pfeffer v. Kerr
693 S.W.2d 296 (Missouri Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
671 S.W.2d 4, 1984 Mo. App. LEXIS 3707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rust-martin-inc-v-ashby-moctapp-1984.