Steffens v. Paramount Properties, Inc.

667 S.W.2d 725, 1984 Mo. App. LEXIS 3612
CourtMissouri Court of Appeals
DecidedMarch 20, 1984
Docket46308
StatusPublished
Cited by14 cases

This text of 667 S.W.2d 725 (Steffens v. Paramount Properties, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steffens v. Paramount Properties, Inc., 667 S.W.2d 725, 1984 Mo. App. LEXIS 3612 (Mo. Ct. App. 1984).

Opinion

GAERTNER, Presiding Judge.

On November 4, 1977, plaintiffs, Michael and Darlene Steffens, and defendant, Paramount Properties, Inc., executed a contract whereby plaintiffs agreed to purchase a lot and house in a subdivision being developed by defendant. Plaintiffs moved into the house on July 1, 1978, and began to discover numerous construction defects. Subsequently, they instituted this action against defendant alleging, among other charges voluntarily dismissed before trial, that the house was defectively constructed *727 and that defendant had breached the contract. A jury found in favor of plaintiffs and assessed their damages in the sum of $5,278 and judgment in that amount was duly entered against defendant.

Defendant does not challenge the sufficiency of the evidence. It asserts, as grounds for reversal, that plaintiffs’ verdict directing instruction and the measure of damages instruction were erroneous.

Plaintiffs submitted their case to the jury under Instruction No. 6 which reads:

Your verdict must be for plaintiffs if you believe:
First, defendant Paramount Properties, Inc., did not construct plaintiffs’ residence in a workmanlike manner, and Second, because of such failure, defendant’s Paramount Properties, Inc., contract obligations were not performed, and
Third, plaintiffs were thereby damaged.

This instruction is based on MAI 26.02 (1980 Rev.) entitled “Verdict Directing— Breach of Bilateral Contract—Breach Sole Issue.” Defendant argues this instruction improperly submits breach of implied warranty under the guise of breach of contract and that the phrase “workmanlike manner” should have been defined.

In Buder v. Martin, 657 S.W.2d 667 (Mo.App.1983) this court approved an instruction virtually identical to Instruction No. 6. Buder involved a breach of contract submission for failure to construct a lake and pond in a workmanlike manner. Citing Hotchner v. Liebowits, 341 S.W.2d 319, 326 (Mo.App.1960), we noted that the requirement of performance of a construction contract in a workmanlike manner “was an express specification of the contract and one that would have been implied had it not been expressly stated.” Buder, 657 S.W.2d at 669. Such a requirement is referred to as “implied condition” of a construction contract in Pitzer v. Hercher, 318 S.W.2d 397, 399 (Mo.App.1958) and is described in Ribando v. Sullivan, 588 S.W.2d 120, 123 (Mo.App.1979) as both a condition of the contract and as an implied warranty of the contractor. In Ribando the appellant argued that the submission of the case on a breach of contract theory was a departure from the pleaded allegations of breach of the implied warranty of habitability. The court rejected this argument and approved the submission of breach of contract based upon a breach of “an implied warranty or condition of good workmanship.” Id. at 123[2], As in Ribando, plaintiffs here presented detailed expert testimony regarding each of the defective conditions including qualified opinion testimony that the defects were a result of poor workmanship. This evidence is sufficient to authorize submitting the case to the jury under either a breach of contract theory or under the theory of breach of the implied warranty of habitability, a tort concept. See Smith v. Old Warson Development Co., 479 S.W.2d 795, 800 (Mo. banc 1972).

Defendant’s contention that the court erred in failing to define “workmanlike manner” is neither supported by citation of authority nor is the point developed in the argument portion of defendant’s brief. Accordingly, the point is deemed abandoned and nothing is preserved for appellate review. Berry v. Federal Kemper Insurance Co., 621 S.W.2d 948, 952 (Mo.App.1981). Moreover, two cases cited above, Buder and Pitzer, are but examples of the frequent instructional use of the phrase “workmanlike manner” without definition. Words in instructions which have common usage and which are generally understood need not be defined. Huff v. Union Electric Co., 598 S.W.2d 503, 510 (Mo.App.1980). We note the absence from the record before us of any request to the trial court by defendant for an instruction defining “workmanlike manner.” The point is without merit.

Defendant’s second point challenges the propriety of plaintiff’s damage instruction taken from MAI 4.01 (1980 Rev.) Having chosen to submit their case on the breach of contract theory, plaintiffs are entitled to recover as damages only a sum which is tbe equivalent of performance of the bargain—to be placed in the position *728 they would be in if the contract had been fulfilled in a workmanlike manner. Hensic v. Afshari Enterprises, Inc., 599 S.W.2d 522, 524 (Mo.App.1980) states as follows:

When a building contractor breaches his contract by defective performance, ... two methods are commonly used to measure the resulting damages. One method, called ‘cost of repair’ is, as its name implies, the cost of repairing the defective work. 5 Corbin, Contracts, § 1089 (1964); Restatement of Contracts, § 346(1)(a) (1932). The second method, called ‘diminution in value,’ is the difference between the value of the building as promised and its value as actually constructed. See Kahn v. Prahl, 414 S.W.2d 269, 282-283 (Mo.1967); Hotchner v. Liebowits, 341 S.W.2d 319, 332 (Mo.App.1960). The particular facts of each case determine which measure of damages is to be used.

The basic rule is that plaintiffs are entitled to recover whichever is lower as between the cost of repair and the diminution of value. Rilando v. Sullivan, 588 S.W.2d at 124. The proper jury instruction for the submission of the question of damages is MAI 4.02, whether the evidence shows cost of repairs, diminution of value or both. Id. at 126; Sands v. R. G. McKelvey Building Co., 571 S.W.2d 726, 732 (Mo.App.1978). As stated in Sands, “[b]y instructing the jury to ‘fairly and justly compensate’ plaintiffs should it find in their favor (MAI 4.01) rather than to award [the cost of repair] (MAI 4.02) the trial court provided an unfocused instruction which could permit the jury to gloss over that question altogether.” Id. at 731.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lowdermilk v. Vescovo Building & Realty Co.
91 S.W.3d 617 (Missouri Court of Appeals, 2003)
State Farm Mutual Automobile Insurance Co. v. DeCaigney
927 S.W.2d 907 (Missouri Court of Appeals, 1996)
Metro Waste Systems, Inc. v. A.L.D. Services, Inc.
924 S.W.2d 335 (Missouri Court of Appeals, 1996)
National Bank of Commerce v. Quirk
922 S.W.2d 717 (Supreme Court of Arkansas, 1996)
In Re Marriage of Swanson
904 S.W.2d 88 (Missouri Court of Appeals, 1995)
White River Development Co. v. Meco Systems, Inc.
806 S.W.2d 735 (Missouri Court of Appeals, 1991)
Crawford v. Whittaker Construction, Inc.
772 S.W.2d 819 (Missouri Court of Appeals, 1989)
Schulze v. C & H BUILDERS
761 S.W.2d 219 (Missouri Court of Appeals, 1988)
Am. Family Mut. Ins. Co. v. AUTO. CLUB INTER-INS. EXCHANGE
757 S.W.2d 304 (Missouri Court of Appeals, 1988)
Riberglass, Inc. v. Giesler
720 S.W.2d 37 (Missouri Court of Appeals, 1986)
Marshall v. Edlin
690 S.W.2d 477 (Missouri Court of Appeals, 1985)
J. Stiles, Inc. v. Evans
683 S.W.2d 481 (Court of Appeals of Texas, 1984)
Rust & Martin, Inc. v. Ashby
671 S.W.2d 4 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
667 S.W.2d 725, 1984 Mo. App. LEXIS 3612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steffens-v-paramount-properties-inc-moctapp-1984.