Turn Key Gaming, Inc. v. Oglala Sioux Tribe

313 F.3d 1087, 2002 WL 31875288
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 10, 2003
Docket01-2957
StatusPublished
Cited by8 cases

This text of 313 F.3d 1087 (Turn Key Gaming, Inc. v. Oglala Sioux Tribe) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turn Key Gaming, Inc. v. Oglala Sioux Tribe, 313 F.3d 1087, 2002 WL 31875288 (8th Cir. 2003).

Opinion

RICHARD S. ARNOLD, Circuit Judge.

Turn Key Gaming promised to build a casino for the Oglala Sioux Tribe but could not keep the project within its budget. Turn Key stopped construction when the Tribe refused to modify their contract. Turn Key filed suit against the Tribe to resolve the parties’ dispute over the costs of a temporary casino and the incomplete permanent casino. The District Court 1 found in favor of the Tribe and awarded it a net amount of $336,843.73 in damages. Turn Key appealed. We hold that the District Court was correct in using the cost of completion of the permanent casino as the measure of damages for the breach of contract and awarding interest on the judgment. The District Court did not clearly err in giving more credence to some pieces of evidence than it did to others. Further, the Court properly held that the Tribe’s sovereign immunity prevents Turn Key from bringing claims in a federal court regarding the temporary ca *1089 sino. We affirm the decision of the District Court in all respects.

I.

Turn Key Gaming and the Oglala Sioux Tribe negotiated a contract for Turn Key to build and operate a casino for the Tribe. Turn Key was to manage the casino for five years in return for a share of the casino’s profits after deducting the cost of building the casino. The contract was submitted to the National Indian Gaming Commission in late November of 1994 for approval. The Management Agreement was approved by the Commission a year later. Pending approval of the Management Agreement, the -Tribe and Turn Key operated a temporary casino on tribal land under a Rental Agreement in which Turn Key provided temporary facilities, equipment, and support in exchange for dividing casino profits with the Tribe.

After approval of the Management Agreement, Turn Key, using Mid-West Construction Managément Services, began to build the permanent casino. Under the Agreement, the Tribe was liable only for the first $4,000,000 in construction costs. Turn Key realized that the project was going to cost $1,300,000 more than that, and tried to get the Tribe voluntarily to increase its liability. The Tribe refused to alter the Management Agreement. Turn Key refused to continue construction, and the Tribe announced that it was treating the contract as broken. It seized the temporary casino to operate on its own. Turn Key sued the Tribe to recover its construction costs, and the Tribe counterclaimed for the damages it suffered because of Turn Key’s breach.

The District Court granted summary judgment for the Tribe. Turn Key appealed to this Court. On appeal, we affirmed for the most part. We held that Turn Key had committed a breach of the Management Agreement by refusing to complete the permanent casino for the agreed-upon price of $4,000,000. In our view, however, the District Court had failed to address certain of Turn Key’s claims, specifically that it was entitled to reimbursement of certain costs either under the Management Agreement or on an unjust-enrichment theory. The Tribe’s counterclaim also remained to be decided. We remanded the case for the District Court to consider these remaining issues. Turn Key Gaming, Inc. v. Oglala Sioux Tribe, 164 F.3d 1092, 1096 (8th Cir.1999).

After a three-day bench trial on remand, the District Court awarded breach-of-contract damages to both parties. The Tribe was awarded $1,973,002.32, and Turn Key was awarded $1,745,658.87. The District Court declined to award any damages arising out of opening or operating the temporary casino, on the ground that those expenses were incurred under a separate contract, as to which the Tribe had not waived ■ sovereign immunity. Ultimately, the Tribe netted $336,000 in damages and prejudgment interest. Turn Key appealed to this Court.

II.

The principal legal issue presented, and the one we discuss first, is the measure of damages properly applied on the Tribe’s counterclaim. It will be recalled that the counterclaim sought damages for Turn Key’s breach of the Management Agreement. The breach occurred before construction was completed. Under the approach taken by the District Court, Turn Key’s damages would be the amount of money required to complete the construction according to the specifications in the Management Agreement, less an adjustment for the $4,000,000 ceiling contained in that agreement. The District Court computed that amount at $1,973,002.32. Turn *1090 Key argues that a significant fact was omitted in the District Court’s analysis. If no breach had occurred, the permanent facility would have been completed at Turn Key’s expense, but Turn Key would also have been entitled to manage the facility for a period of time, and to receive for its services a fee amounting to 30 per cent, of net revenues. But because of the breach, the Tribe took over the casino (actually the temporary facility) and operated it for its own account. It did not have to pay Turn Key’s management fee. This benefit to the Tribe, in the form of a reduced expense, should have been allowed for in the computation of the Tribe’s damages. On this view, the damages would have been $1,973,002.32, less the amount of the manager’s fee that the Tribe did not have to pay.

The purpose of contract damages is to put the injured party in the same position it would have occupied if there had been no breach. Clayton Center Associates v. Schindler Houghton Elevator Corp., 731 F.2d 536, 540 (8th Cir.1984). The District Court believed that its computation did exactly that. The Court said:

23. Because of the breach of the Management Agreement, plaintiff is not entitled to a credit relating to the 30% manager’s fee. In addition, even if plaintiff was entitled to this credit, the Court finds its calculation to be speculative. Furthermore, the credit would not account for the costs incurred by defendant in assuming the duties of the manager.

Turn Key Gaming, Inc. v. Oglala Sioux Tribe, CIV. 96-5084 (D.S.D., opinion filed July 13, 2001), p. 6.

We have no fault to find with this approach. It contains no error of law, and no clearly erroneous finding of fact. It was Turn Key’s breach in the first place that prevented performance of the contract, including Turn Key’s management of the permanent facility, from going forward. In addition, Turn Key does not dispute the District Court’s finding that calculation of the amount that might be saved by the Tribe is “speculative.” Instead, Turn Key takes the position that the burden of proof was on the Tribe to show all elements of damage, including the amount of any credit or offset that Turn Key might be entitled to in consequence of losing its manager’s fee. We cannot agree with this contention. Whether or not the manager’s fee is properly characterized, in technical pleading terms, as a set-off or affirmative defense, we hold it was not unfair, under the circumstances of this case, for the District Court to rely, in part, upon the speculative nature of this item when deciding not to reduce the recovery that the Tribe was otherwise entitled to for breach of the construction contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
313 F.3d 1087, 2002 WL 31875288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turn-key-gaming-inc-v-oglala-sioux-tribe-ca8-2003.