Lieber v. Bridges

650 S.W.2d 688, 1983 Mo. App. LEXIS 3211
CourtMissouri Court of Appeals
DecidedApril 19, 1983
Docket12577
StatusPublished
Cited by7 cases

This text of 650 S.W.2d 688 (Lieber v. Bridges) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lieber v. Bridges, 650 S.W.2d 688, 1983 Mo. App. LEXIS 3211 (Mo. Ct. App. 1983).

Opinion

TITUS, Judge.

In June 1974 plaintiffs contracted with defendant to erect a house on plaintiffs’ lakefront property in Camden County. The house design was very close to a house which defendant had already built and which had been inspected and approved by plaintiffs. Plaintiffs were to pay defendant $35,000 in exchange for defendant furnishing all material and labor for construction.

The house was fully completed and paid for in October 1974 with no visible problems. It was built on a thirty degree slope, consisting of two stories with an elevated deck and concrete patio fronting much of it. In order to prevent the structure from “settling” defendant sunk concrete “piers” under the foundation to insure that it was upon a firm footing.

In early 1975 plaintiffs noticed that the posts supporting the elevated deck were dangling above the piers upon which they had rested. The increased pressure on the deck caused it to pull away from the house until defendant returned and placed “caps” on the piers, allowing them to once again support the deck posts. Shortly afterwards, however, plaintiffs noticed that the concrete porch had begun to separate from the house, followed, once again, by the deck. In subsequent months, plaintiffs testified, the house grew worse as cracks appeared, the porch sunk deeper, the roof listed, and the floor began to drop out of the house, along with numerous other problems. All was reported to defendant, who never responded.

Plaintiffs obtained the help of another contractor who made substantial corrections to the piers which totally corrected the settlement problem. The contractor testified, inter alia, that the piers constructed by appellant were “inadequate” in that they were not placed upon solid rock, but upon loose dirt and stone, which was in turn upon rock. It was his opinion that the problems were caused by the inadequately constructed piers and that defendant was wrong in not sinking them to solid rock. This, he said, would have prevented any settling of the house.

Plaintiffs brought suit alleging that defendant had impliedly warranted the house to be suitable for its ordinary purpose, but that it was in fact built in an unskillful and unworkmanlike manner. They prayed for a $17,000 judgment, consisting of $5,000 for diminution in value and $12,000 for repairs. The jury found for the plaintiffs under an implied warranty theory, awarding $25,000 in damages. After the trial court granted remittitur to $17,000, this appeal was filed.

We first consider defendant’s second point relied on which states that the trial *690 court erred in refusing to accept defendant’s MAI 34.02 1 withdrawal instruction to instruct the jury that all evidence concerning unskilled or unworkmanlike conduct on the part of defendant is no longer to be considered since that evidence is irrelevant in a case involving breach of an implied warranty. The issue, he asserts, is the quality of the house, not the workmanship in building it. Plaintiffs, on the other hand, suggest that such evidence is properly admitted since the jury deserves a reasonable explanation as to why the house was rendered unfit for use as a residence.

The controversy is caused by the difference between contract and tort law as to the types of damages recoverable under each. The damages recoverable under contract law relate solely to the deterioration or loss of bargain of a house, whereas negligence law allows recovery not only for loss of bargain, but also for personal injury. Therefore, the evidence relevant to proof of damages under contract law is that which deals solely with the end result, i.e. quality of the house; whereas that relevant in negligence law is both conduct of the builder and resultant quality of the house. In other words, “[fjault is irrelevant in an action in implied warranty.” Crowder v. Vandendeale, 564 S.W.2d 879, 882 (Mo. banc 1978). See also Smith v. Old Warson Dev. Co., 479 S.W.2d 795, 798 (Mo. banc 1972).

The case before us admittedly involves only the deterioration of a house, and not any threat of personal injury; it thus falls under the contract oriented implied warranty theory. However, in reviewing the evidence we note that there was extensive testimony regarding how defendant built the house, what he could have done and what he should have done. Such evidence was elicited by plaintiffs’ attorney from defendant, plaintiffs and the other witnesses introduced by both sides. And such evidence went beyond merely showing what caused the house to sink—it, in fact, attempted to place blame on the builder by alleging negligent conduct. Since in a case of implied warranty such testimony is irrelevant and possibly prejudicial, we hold that the lower court abused its discretion in failing to submit defendant’s withdrawal instruction. Helming v. Adams, 509 S.W.2d 159, 169[14] (Mo.App.1974).

Defendant’s first point relied on alleges that the trial court erred in its submission of a verdict director that contains neither the correct law of the case nor a “tail” referring to defendant’s affirmative defense instruction. The verdict director that was used was MAI 25.08, which is patterned on the law of implied warranty of merchantability. To recover under such a warranty, the plaintiffs were required to show that the house is not fit for the ordinary purpose for which it is used. Similar submissions have been upheld under implied warranties of fitness for a particular purpose, which yield a broader scope of liability, yet involve the more difficult showing of whether the builder had knowledge of the particular purpose for which the building was to be used and whether the building in fact lived up to such a purpose. Cf. O’Dell v. Custom Builders Corp., 560 S.W.2d 862 (Mo. banc 1978).

Defendant’s criticism of the use of MAI 25.08 is that the issue litigated in this lawsuit involved not merchantability, but quality of workmanship. Therefore, he asserts, the case should have been submitted under a verdict director dealing with workmanship, instead of merchantability. In support of this claim defendant merely concludes that the issue of good workmanship was litigated “in great detail” and thus was tried but never submitted. But as discussed earlier, this case deals with damages in the form of mere deterioration of a house, not with the threat of personal injury to anyone. And as such, the present case is one involving an implied warranty that the house would meet a certain standard of quality. The matter was thus correctly submitted under the theory of implied warranty.

*691 Defendant also contends that the trial court erred in failing to include in plaintiffs’ verdict director the phrase: “unless you believe plaintiff is not entitled to recover by reason of Instruction Number -” This phrase, more commonly referred to as a “tail,” is intended to refer the jury’s attention to the defendant’s affirmative defense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Redman v. State
860 S.W.2d 491 (Court of Appeals of Texas, 1993)
Lane v. Amsted Industries, Inc.
779 S.W.2d 754 (Missouri Court of Appeals, 1989)
Christensen v. R.D. Sell Construction Co.
774 S.W.2d 535 (Missouri Court of Appeals, 1989)
Kennedy v. State
735 S.W.2d 176 (Missouri Court of Appeals, 1987)
J. Stiles, Inc. v. Evans
683 S.W.2d 481 (Court of Appeals of Texas, 1984)
Ferguson v. Alfred Schroeder Development Co.
658 S.W.2d 62 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
650 S.W.2d 688, 1983 Mo. App. LEXIS 3211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lieber-v-bridges-moctapp-1983.