Public Water Supply District No. 8 of Jefferson County v. Maryland Casualty Co.

478 S.W.2d 293
CourtSupreme Court of Missouri
DecidedApril 10, 1972
Docket55593
StatusPublished
Cited by11 cases

This text of 478 S.W.2d 293 (Public Water Supply District No. 8 of Jefferson County v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Water Supply District No. 8 of Jefferson County v. Maryland Casualty Co., 478 S.W.2d 293 (Mo. 1972).

Opinion

SEILER, Judge.

Contractor breached a contract with water district to install a water distribution system. Water district sued surety for the contractor for $122,949.51, the full amount of the performance bond. The surety filed a cross-claim against contractor for indemnification. A supplier sued the contractor and its surety for $17,656.79 worth of materials furnished. The claims were consolidated for trial, and the judgment awarded $17,656.79 to the supplier, and $22,041.71 to the water district. The surety and water district appeal.

On December 21, 1967, Public Water Supply District No. 8 of Jefferson County entered into a contract with L.C.R. Excavating Contractors, Inc. for the construction of a water distribution system. The contract price for the work to be performed was $122,949.51 based upon unit prices and estimated quantities of work to be done and supplies and materials to be used and installed. A performance payment bond was furnished, in the penal sum of $122,949.51, with the Maryland Casualty Company as surety.

The contractor commenced to install the pipe for this subterranean water system in March, 1968. By November, 1968, the contractor had installed about 7,000 feet of cast iron pipe and 60,000 to 65,000 feet of plastic pipe. The contractor began to test the water lines under pressure to determine if they met the contract, specifications. The testing revealed that there were numerous leaks in the system. The contractor repaired a number of leaks but in spite of his efforts only a 300 foot section of cast iron pipe passed the required pressure test. In March, 1969, the contractor terminated the testing of the pipe and walked off the project.

Subsequently, the water district and Phillips Products Company, manufacturer and supplier of the plastic pipe, tested and made repairs on the lines. At the time of the trial, about 20,200 feet of water pipe had been tested. Repairs were still being made. Only the 300 feet of cast iron, and about 1,450 feet of plastic pipe passed the pressure test. The water district also completed installation of pipe in five widely scattered areas where the contractor failed to do so.

The court, as the trier of fact in this jury-waived case, found that the water district spent $14,241.78 for a contractor to test and repair some of the worst leaks, $5,800.00 for additional engineer expense to locate leaks, and $7,800.00 to complete the installation of the lines required by the contract. However, the court concluded that the additional engineer expense was not chargeable against the contractor because the engineer representing the water district agreed to waive certain preinstallation tests on the pipe. The court refused *295 to grant damages in the amount needed to replace the system completely with the new pipe because these damages would be remote and speculative since only 20,200 feet of pipe had been tested. The court also indicated that such damages could not be chargeable against contractor because the engineer on behalf of water district relied upon a written guarantee from the manufacturer of the plastic pipe in lieu of the required tests and the water district had filed suit elsewhere to recover damages from the manufacturer of the pipe.

In accordance with the Civil Rule 73.01, V.A.M.R., we review de novo the facts as well as the law, as in an equity case. We recognize and reiterate that “. . . the court’s finding is not binding on us; that the question is not merely whether the court’s findings are supported by substantial evidence; and that we are to make our independent investigation and reach our own conclusions as to the weight of the evidence . . .” Schmitt v. Pierce, (Mo.Sup. banc), 344 S.W.2d 120, 122; Cleary v. Cleary, (Mo.Sup.) 273 S.W.2d 340, 346. We need not give deference to the opportunity of the lower court to ascertain the credibility of witnesses because their testimony was not in conflict and much of the evidence was documentary, not testimonial.

J. C. Stevens & Associates, Inc., a civil engineering firm, was the engineer employed by the water district for the project. Danny Gardner, an employee of this firm, was the resident engineer responsible for seeing that the work was on schedule, measuring the work performed, observing the testing, and confirming that specifications were being carried out. The water district contends that since the engineer determined that the water distribution system was totally unacceptable, and cheaper to rebuild than repair, the surety is liable for the full amount of the bond. The surety maintains that the evidence showed the water distribution system to be operative, and thus the engineer’s opinion must be rejected as speculation and conjecture. The surety also argues that the engineer acting on behalf of the water district waived certain pressure tests required by the contract specifications and that the damages of water district resulted from this waiver.

This contract entrusted many decisions to the engineer. The following provisions were specifications incorporated into the contract:

2.3.01 Engineer’s Responsibility and Authority :
All work shall be done under the general supervision of the Engineer. The Engineer shall decide any and all questions which may arise as to quality and acceptability of materials furnished, work performed, rate of progress of work, interpretation of Drawings and Specifications and all questions as to the acceptable fulfillment of the Contract on the part of the Contractor. (italics added).
2.3.02 Engineers Decisions:
All claims of the Owner or the Contractor shall be presented to the Engineer for decision which shall be made in writing within a reasonable time. All decisions of the Engineer shall be final except in cases where time and/or financial considerations are involved, which shall be subject to arbitration.
2.7.17 Acceptance and Final Payment:
When the Contractor shall have completed the work in accordance with the terms of the Contract Documents, the Engineer shall certify his acceptance to the Owner .

Under the clear language of these specifications, the engineer had the authority to determine when the work had been *296 performed in accordance with the contract, and the responsibility to certify this determination to the water district. “A stipulation in the contract that payment shall be made upon the certificate of the engineer is equivalent to providing that the decisions of the engineer are conclusive”. Massman Const. Co. v. Lake Lotawana Ass’n, Inc., 240 Mo.App. 469, 210 S.W.2d 398, 402. There is no contention here that the engineer certified his final acceptance of the work of the contractor, or that the contractor did not breach the contract. However, the surety points out that the determination by the engineer would not be binding upon the parties if a result of “. . . fraud, or such gross mistake as would imply bad faith on the part of such engineer . . .” Massman Const. Co. v. Lake Lotawana Ass’n, Inc. supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Meco Systems, Inc. v. Dancing Bear Entertainment, Inc.
948 S.W.2d 185 (Missouri Court of Appeals, 1997)
Hart and Son Hauling, Inc. v. MacHaffie
706 S.W.2d 586 (Missouri Court of Appeals, 1986)
Bernard McMenamy Contractors, Inc. v. Missouri State Highway Commission
582 S.W.2d 305 (Missouri Court of Appeals, 1979)
Sides Construction Co. v. Arcadia Valley R-II School District
565 S.W.2d 761 (Missouri Court of Appeals, 1978)
Public Water Supply District No. 8 v. Maryland Casualty Co.
513 S.W.2d 311 (Supreme Court of Missouri, 1974)
Modine Manufacturing Company v. Carlock
510 S.W.2d 462 (Supreme Court of Missouri, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
478 S.W.2d 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-water-supply-district-no-8-of-jefferson-county-v-maryland-casualty-mo-1972.