School District of Springfield R-12 Ex Rel. Midland Paving Co. v. Transamerica Insurance Co.

633 S.W.2d 238, 34 U.C.C. Rep. Serv. (West) 433, 1982 Mo. App. LEXIS 2887
CourtMissouri Court of Appeals
DecidedApril 19, 1982
Docket11566, 11571 and 11572
StatusPublished
Cited by32 cases

This text of 633 S.W.2d 238 (School District of Springfield R-12 Ex Rel. Midland Paving Co. v. Transamerica Insurance Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District of Springfield R-12 Ex Rel. Midland Paving Co. v. Transamerica Insurance Co., 633 S.W.2d 238, 34 U.C.C. Rep. Serv. (West) 433, 1982 Mo. App. LEXIS 2887 (Mo. Ct. App. 1982).

Opinions

HOGAN, Judge.

This is a materialman’s action brought upon a public contractor’s bond. Because the performance and payment bond was executed by DeWitt-Newton (the prime contractor) pursuant to the requirement of § 107.170, RSMo 1978,1 this litigation was instituted by the obligee as provided by § 522.020, but Midland Paving Company is the real party in interest and we shall refer to Midland as the plaintiff.

Plaintiff sued the surety, defendant Transamerica. Under the provisions of Rule 52.11(a), the surety impleaded the prime contractor and a group of indemni-tors; these parties defendant in turn im-pleaded Everett Jackson, the subcontractor to whom the materials were furnished. Sundry conflicting claims, crossclaims and counterclaims were interposed by the parties and by December 18, 1978, the cause stood at issue. After a 4-day bench trial, the court found, in essence: 1) that the plaintiff should have and recover judgment against the surety in the amount of $5,879.23, with interest at the rate of 6 percent per annum; that the surety should stand indemnified and should recover over [241]*241against defendants DeWitt-Newton and the individual third-parties defendant in the amount of the judgment rendered against the surety, together with the sum of $12,-000.00 stipulated as fair and reasonable attorney’s fees incurred by the surety,2 and 2) that DeWitt-Newton and the other third-parties defendant recover over against Jackson, the subcontractor.

All the parties except Jackson, who defaulted, have appealed. The appeals were consolidated for purposes of argument, but will be considered separately to the extent that the contentions presented differ. We must note, in candor, that the case was presented — perhaps of necessity — in confounding detail. At plaintiff’s request, the trial court made extensive findings of fact and conclusions of law. We readily acknowledge the utility and clarity of those findings although we shall not set them forth in detail. We confine ourselves to a recitation of those facts and a consideration of those issues essential and necessary to a proper resolution of the appeals. See Bloomfield Reorganized School Dist. No. R-14 v. Stites, 336 S.W.2d 95, 97 (Mo.1960); Southwest Engineer. Co. v. Reorganized Sch. Dist. R-9, Lawrence County, 434 S.W.2d 743, 746 (Mo.App.1968).

The appeals are focused upon the performance of and payment for a single subcontract awarded by the prime contractor during the construction of a high school building. At some time prior to May 27, 1970, the Springfield School District R-12 determined that a fifth high school was necessary. The prime contract was let to DeWitt-Newton for $1,828,400.00 and the bond required by § 107.170 was executed. The high school building was built on or near the old Kickapoo prairie south of Springfield, was later named Kickapoo High School and during the trial, the witnesses referred to the building as “Kickapoo.”

On September 29, 1970, DeWitt-Newton let a subcontract for asphalt paving to defendant Jackson, who did business in his own name and as D. 0. Allen Asphalt Paving. The subcontract calls for asphalt paving and installing the materials for a “Red Dog” track; as explained upon trial, it included paving the parking lots, driveway and tennis courts and the installation of the track at Kickapoo. The contract price for the paving was $47,300.00; the “red dog” installation cost was $1,900.00. It is readily inferable that the work Jackson had to do was substantially complete by the end of October 1971, although he was required to repair and resurface the tennis courts during the summer of 1972.

On October 25, 1971, Jackson submitted an invoice requesting a progress payment in the amount of $44,935.00. DeWitt-Newton remitted the sum of $40,441.50, the amount due less 10 percent retainage. On November 18,1971, Jackson paid plaintiff the sum of $20,000.00 which was credited to Jackson’s open account. Jackson submitted another request for a progress payment on November 26, 1971, which was refused because the tennis court surfaces were not satisfactory to the prime contractor. Jackson was given an extension of time and the tennis courts were resurfaced. In September 1972, Jackson requested his retent payment. By check dated September 8, 1976, DeWitt-Newton remitted Jackson’s retain-age in the amount of $7,048.50, plus $30.00 in payment of a charge simply noted on the check as “# 1305.” On September 11, Jackson paid plaintiff $10,000.00 by check. The check bears the legend: “FOR On Account.” This check was also credited to Jackson’s open account. The trial court held that the payment of $20,000.00 should have been credited to that part of Jackson’s account incurred in the performance of the Kickapoo subcontract, but the retainage payment was properly credited to Jackson’s [242]*242open account. Several ancillary questions have been briefed but the trial court’s allocation of these two payments is the principal matter in dispute.

Appeal number 11566 is the plaintiff’s appeal. Although the defendants have not specifically briefed the point, a plaintiff’s appeal ordinarily puts the sub-missibility of the case in issue. Usually our courts have applied this principle to cases tried to a jury, holding that trial errors are immaterial if the plaintiff made no submis-sible case. Osborn v. McBride, 400 S.W.2d 185, 188[1] (Mo.1966); O’Dell v. Dean, 356 Mo. 861, 863, 204 S.W.2d 248, 249[1] (1947). A similar rule applies in court-tried eases; if a plaintiff has failed to prove his right to recover any sum, he cannot have been prejudiced by the trial court’s rulings limiting the amount of recovery. Laclede Land & Improvement Co. v. Schneider, 177 S.W. 388, 390[6] (Mo.1915); State ex rel. Brown v. Hamilton, 202 Mo. 377, 386, 100 S.W. 609, 611 (1907). So, we consider first the contention of both defendants that the trial court erred in applying Jackson’s payments so as to avoid payment for the materials on the Kickapoo project because it was impossible to separate Jackson’s purchases into separate job accounts and there was no basis for making an application of payments other than to apply the payments first to the oldest purchases. As developed, particularly in defendant DeWitt-Newton’s brief, this point amounts to an argument that the items shown on Jackson’s account with plaintiff were so commingled that it could not be determined what materials went into the Kickapoo project or the manner in which Jackson’s payments should be credited. Defendants Transamerica and DeWitt-Newton have cited Herrman v. Daffin, 302 S.W.2d 313 (Mo.App.1957), which the trial court cited in its memorandum opinion.

The point is not without merit. Defendants’ argument that there is no identifiable debt allocable to the Kickapoo paving project because plaintiff’s invoices for materials do not identify the project in which they were used or consumed is not as impressive as it may appear to be at first glance. It cannot be said that the items of Jackson’s account were capable of easy separation, which is the language of some of the precedents, e.g., C. A. Burton Machinery Co. v. National Surety Co., 182 S.W. 801, 804 (Mo.App.1916); the invoices do not show precisely what materials went into the Kickapoo project, as was the case in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. A.G. Electrical, Inc.
304 S.W.3d 179 (Missouri Court of Appeals, 2009)
Board of Education ex rel. Bertolino v. Vince Kelly Construction Co.
963 S.W.2d 331 (Missouri Court of Appeals, 1997)
Sokol v. Labor & Industrial Relations Commission of Missouri
946 S.W.2d 20 (Missouri Court of Appeals, 1997)
Zolman v. SEMO Produce, Inc.
875 S.W.2d 605 (Missouri Court of Appeals, 1994)
Wilson v. Brewster
809 S.W.2d 183 (Missouri Court of Appeals, 1991)
In re the Marriage of Hughes
773 S.W.2d 897 (Missouri Court of Appeals, 1989)
In the Interest of W.J.D.
756 S.W.2d 191 (Missouri Court of Appeals, 1988)
UHL Construction v. Fidelity & Deposit Co. of Maryland
538 A.2d 562 (Superior Court of Pennsylvania, 1988)
Uhl Const. v. FID. & DEP. CO. OF MD.
538 A.2d 562 (Supreme Court of Pennsylvania, 1988)
Sab Harmon Industries, Inc. v. All State Building Systems, Inc.
733 S.W.2d 476 (Missouri Court of Appeals, 1987)
Rigby Corp. v. Boatmen's Bank and Trust Co.
713 S.W.2d 517 (Missouri Court of Appeals, 1986)
City of Union v. Julius
706 S.W.2d 513 (Missouri Court of Appeals, 1986)
Thornbrugh v. Poulin
679 S.W.2d 416 (Missouri Court of Appeals, 1984)
Patterson v. Foster Forbes Glass Co.
674 S.W.2d 599 (Missouri Court of Appeals, 1984)
Brotherton v. Burlington Northern Railroad
672 S.W.2d 133 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
633 S.W.2d 238, 34 U.C.C. Rep. Serv. (West) 433, 1982 Mo. App. LEXIS 2887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-of-springfield-r-12-ex-rel-midland-paving-co-v-moctapp-1982.