Thomas v. A.G. Electrical, Inc.

304 S.W.3d 179, 2009 Mo. App. LEXIS 1693, 2009 WL 4279374
Missouri Court of Appeals·Decided November 24, 2009·No. ED 92109·Published·Cited by 9 cases

Opinion

LAWRENCE E. MOONEY, Judge.

Workers on a public-works project sued to recover unpaid prevailing wages from the bonding company that had issued two bonds on the project. The trial court dismissed the workers’ claims. Because we hold that the Performance Bond issued by the bonding company covers the workers’ claim, and because we conclude that the notice-of-claim provision in the Payment Bond issued by the bonding company does not negate the workers’ claim, we reverse and remand.

Factual and Procedural Background

Abdelmalek Construction, L.L.C., a general contractor in the building construction industry, contracted with the St. Charles School District to complete work on the Lewis and Clark Vocational Technical School Renovations and Additions Project. Prior to commencing work on the project, Abdelmalek Construction, as the general contractor, purchased two bonds from Contractors Bonding and Insurance Company, to insure the general contractor’s work on the project. These two bonds, entitled and referred to as the Perform- *182 anee Bond and the Payment Bond, are at the heart of the instant dispute.

After securing the contract with the school district, the general contractor entered into a contract with A.G. Electrical, Inc., an electrical contractor, to perform electrical work on the Lewis and Clark project. The plaintiff-workers in this action performed work on the Lewis and Clark project as employees of this electrical subcontractor. 1 The electrical contractor paid the workers, but failed to pay the workers the prevailing wage for their work on the project. 2 The difference between the wages and benefits received by the workers, and the wages and benefits they should have received under Missouri’s Prevailing Wage Law, amounted to $20,864.24.

The workers, by letter dated May 29, 2007, made alternative claims on the Performance Bond and the Payment Bond, to recover the prevailing wages that had not been paid to them for their work on the project. The bonding company denied the workers’ claims. Consequently, the workers filed suit against the bonding company, which was the surety on the two bonds, to recover their unpaid wages, as well as statutory damages and attorneys’ fees. 3

The bonding company filed a motion to dismiss the workers’ two claims for failure to state a cause of action. As to the Performance Bond, the company argued that the workers’ claim should be dismissed because the workers had not timely sued and because the bond did not cover the workers’ prevailing-wage claim. The company argued the Performance Bond only insured the completion of work on the Lewis and Clark project, not payment of labor or the prevailing wage because the Payment Bond had been issued for those purposes. As to the workers’ claim against the Payment Bond, the company argued that the workers’ claim was time-barred, and thus should be dismissed, because the workers did not comply with the ninety-day notice requirement set forth in that bond.

The trial court granted the bonding company’s motion and dismissed the workers’ claims. The court reasoned that the workers’ prevailing-wage claim was not covered by the Performance Bond, and that them claim on the Payment Bond was untimely pursuant to the ninety-day notice provision in that bond. The workers appeal, alleging the trial court erred in dismissing their two claims. We shall address the workers’ claim against each bond in turn.

Standard of Review

Appellate review of a trial court’s grant of a motion to dismiss is de novo. Lynch v. Lynch, 260 S.W.3d 834, 836 (Mo. banc 2008). “A motion to dismiss for failure to state a cause of action is solely a test of the adequacy of the plaintiffs petition.” Nazeri v. Missouri Valley College, 860 S.W.2d 303, 306 (Mo. banc 1993); Stein v. Novus Equities Co., 284 S.W.3d 597, 601 (Mo.App. E.D.2009). When this *183 Court reviews the dismissal of a petition for failure to state a claim, we treat the facts contained in the petition as true and construe them liberally in favor of the plaintiff. Lynch, 260 S.W.3d at 836; Stein, 284 S.W.3d at 601. We do not attempt to weigh whether the factual allegations are credible or persuasive. Nazeri, 860 S.W.2d at 306; Stein, 284 S.W.3d at 601. Nor do we address the merits of the case or consider evidence outside the pleadings. Ryann Spencer Group, Inc. v. Assurance Co. of America, 275 S.W.3d 284, 287 (Mo.App. E.D.2008). Rather, we review the petition “in an almost academic manner, to determine if the facts alleged meet the elements of a recognized cause of action, or of a cause that might be adopted in that case.” Nazeri, 860 S.W.2d at 306; Stein, 284 S.W.3d at 601. “If the petition sets forth any set of facts that, if proven, would entitle the plaintiff to relief, then the petition states a claim.” Lynch, 260 S.W.3d at 836; Stein, 284 S.W.3d at 602. A petition states a cause of action if “its averments invoke principles of substantive law that may entitle the plaintiff to relief.” Id. (internal quotation omitted). “A petition cannot be dismissed for failure to state a claim unless it appears that the plaintiff can prove no set of facts in support of the claim that would give a right to relief.” Thomas v. B.K.S. Development Corp., 77 S.W.3d 53, 58 (Mo.App. E.D.2002).

General Prevailing Wage Law

Free access — add to your briefcase to read the full text and ask questions with AI

Thomas v. A.G. Electrical, Inc., 304 S.W.3d 179, 2009 Mo. App. LEXIS 1693, 2009 WL 4279374 (Mo. Ct. App. 2009).

304 S.W.3d 179 (Thomas v. A.G. Electrical, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

DOUGLAS WHITE v. R.L. PERSONS CONSTRUCTION, INC., Defendant-Respondent.
503 S.W.3d 339 (Missouri Court of Appeals, 2016)
Carl and Janice Duffner v. City of St. Peters
482 S.W.3d 811 (Missouri Court of Appeals, 2016)
Nancy Gardner v. Bank of America, N.A.
466 S.W.3d 642 (Missouri Court of Appeals, 2015)
Gregory Grim v. Eastern Electric
West Virginia Supreme Court, 2014
Grim v. Eastern Electric, LLC
767 S.E.2d 267 (West Virginia Supreme Court, 2014)
Doe ex rel. Subia v. Kansas City, Missouri School District
372 S.W.3d 43 (Missouri Court of Appeals, 2012)
Jennings v. SSM Health Care St. Louis
355 S.W.3d 526 (Missouri Court of Appeals, 2011)