Board v. Eurostyle, Inc.

998 S.W.2d 810, 1999 Mo. App. LEXIS 943, 1999 WL 460924
CourtMissouri Court of Appeals
DecidedJuly 8, 1999
Docket22472
StatusPublished
Cited by14 cases

This text of 998 S.W.2d 810 (Board v. Eurostyle, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board v. Eurostyle, Inc., 998 S.W.2d 810, 1999 Mo. App. LEXIS 943, 1999 WL 460924 (Mo. Ct. App. 1999).

Opinion

*812 JOHN E. PARRISH, Judge.

Four employees of Rick Foster d/b/a Preferred Roofing and Construction (Foster) brought this action against Eurostyle, Inc., (Eurostyle) and Safeco, Inc., (Safeco) for double their unpaid wages plus attorney fees relative to work performed on a public works construction project for the State of Missouri. See §§ 107.170 and 290.300. 1 Eurostyle was the contractor for the project. Foster was a subcontractor. Safeco was the surety on a performance bond purchased by Eurostyle.

The trial court held the employees were entitled to receive double the amount of unpaid wages and attorney fees from Foster, as permitted by § 290.300, but could recover only the amount of unpaid wages from Eurostyle or Safeco. Judgment was entered for Jack Board, Leonard Pack and Donald Evans against Eurostyle and Safe-co for unpaid wages in the amounts of $4,006.67, $1,630.51 and $2,750.00, respectively. They appeal. 2 This court reverses as to the amount of damages and remands with directions. In all other respects the judgment is affirmed.

Appellants present one point on appeal. They contend the trial court erred in not permitting them to collect double their unpaid wages and their attorney fees from Eurostyle and Safeco. They argue that § 290.300 permits them to recover those amounts.

Section 290.300 provides:

Any workman employed by the contractor or by any subcontractor under the contractor who shall be paid for his services in a sum less than the stipulated rates for work done under the contract, shall have a right of action for double whatever difference there may be between the amount so paid and the rates provided by the contract together with a reasonable attorney’s fee to be determined by the court, and an action brought to recover same shall be deemed to be a suit for wages, and any and all judgments entered therein shall have the same force and effect as other judgments for wages.

Section 290.300 relates to provisions in § 290.250. Section 290.250 requires public bodies undertaking public works construction projects to require contractors doing the work to pay not less than the prevailing rates of pay for the area where the work is performed. 3 The statute requires contracts pursuant to which work is performed to include “a stipulation to the effect that not less than the prevailing hourly rate of wages shall be paid to all workmen performing work under the contract.” It requires all contractors’ bonds to “include such provisions as will guarantee the faithful performance of the prevailing hourly wage clause as provided by contract.” The statute imposes penalties on contractors that do not comply. The penalties imposed on contractors are for violations both with respect to underpayment of wages to the contractor’s employees and violations with respect to underpayment of wages to subcontractors’ employees.

Section 107.170.2 requires public agencies that contract for public works, “the cost of which is estimated to exceed twenty-five thousand dollars,” to require contractors to provide performance bonds that include conditions for payment for “labor performed in such work whether by subcontractor or otherwise.” Section 107.170.3 provides, “All bonds executed and furnished under the provisions of this *813 section shall be deemed to contain the requirements and conditions as herein set out, regardless of whether the same be set forth in said bond, or of any terms or provisions of said bond to the contrary notwithstanding.”

Workers on public works construction projects have the right to sue on any bond executed pursuant to § 107.170 that covers the project on which they worked. See § 522.300. Safeco’s bond was executed pursuant to § 107.170.

Article 5 of Eurostyle’s contract with the state provides, consistent with § 290.250:

It is understood and agreed by and between the parties that not less than the prevailing hourly rate of wages for work of a similar character in the locality in which the work is performed and not less than the prevailing hourly rate of wages for legal holiday and overtime work in the locality in which the work is performed, both as determined by the Department of Labor and Industrial Relations or determined by the court on appeal, shall be paid to all workmen employed by or on behalf of the Contractor or any subcontractor, exclusive of maintenance work. Only such workmen as are directly employed by the Contractor or his subcontractors, in actual construction work on the site shall be deemed to be employed. [Emphasis added.]

Section 290.250 requires state agencies “to take cognizance of all complaints of all violations of the provisions of sections 290.210 to 290.340 committed in the course of the execution of the contract, and, when making payments to the contractor becoming due under said contract, to withhold and retain therefrom all sums and amounts due and owing as a result of any violation of sections 290.210 to 290.340.” The statute permits contractors to withhold from payments to subcontractors amounts withheld from the contractor “on account of said subcontractor’s failure to comply with the terms of sections 290.210 to 290.340.” If payment has been made to a subcontractor, § 290.250 permits the contractor to maintain a lawsuit to recover appropriate amounts.

Missouri statutes clearly place the onus for compliance with prevailing wage laws applicable to public works construction projects on the contractor. They provide the contractor with remedies against a subcontractor for whose violations the contractor is liable. They require contractors to obtain performance bonds that assure payment of wages earned by their workers and workers employed by subcontractors.

A contractor that performs public works construction projects must cause wages to be paid of an amount “not less than the prevailing hourly rate.” § 290.250. The duty imposed on the contractor extends to both the contractor’s workers and subcontractors’ workers. To not permit a subcontractor’s underpaid employees to recover double the amount of unpaid wages and attorney fees, to which § 290.300 entitles them, from the contractor and its surety would be inconsistent with the contractor’s statutory duties. To enable contractors to escape mandated contractual responsibilities by exempting them from liability imposed by § 290.300 for their subcontractors’ non-payment of wages would encourage less than diligent oversight by contractors.

Eurostyle and Safeco argue, nevertheless, that § 290.300 is a penal statute. They contend it must be strictly construed as being intended to punish only a particular contractor or subcontractor who failed to pay employees the applicable prevailing hourly rate of pay. This court does not find that argument persuasive.

As Eurostyle and Safeco assert, penal statutes must be strictly construed. State ex rel. Danforth v. European Health Spa, Inc., 611 S.W.2d 259, 262 (Mo.App.1980), quoting City of Charleston v. McCutcheon,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lapponese v. Carts of Colorado, Inc.
422 S.W.3d 396 (Missouri Court of Appeals, 2013)
Snyder v. Consolidated Library District No. 3
306 S.W.3d 133 (Missouri Court of Appeals, 2010)
Thomas v. A.G. Electrical, Inc.
304 S.W.3d 179 (Missouri Court of Appeals, 2009)
Collins & Hermann, Inc. v. TM2 Construction Co.
263 S.W.3d 793 (Missouri Court of Appeals, 2008)
Bonney v. Environmental Engineering, Inc.
224 S.W.3d 109 (Missouri Court of Appeals, 2007)
State ex rel. Griffin v. R.L. Persons Construction, Inc.
193 S.W.3d 424 (Missouri Court of Appeals, 2006)
Cement Masons Pension Fund v. William A. Randolph, Inc.
832 N.E.2d 228 (Appellate Court of Illinois, 2005)
State Ex Rel. Laszewski v. R.L. Persons Construction, Inc.
136 S.W.3d 863 (Missouri Court of Appeals, 2004)
Rolfe v. New Britain General Hospital
790 A.2d 1194 (Connecticut Superior Court, 2001)
Rolfe v. New Britain General Hospital, No. Cv 99 496563 (Oct. 11, 2001)
2001 Conn. Super. Ct. 14071 (Connecticut Superior Court, 2001)
Preston v. State
33 S.W.3d 574 (Missouri Court of Appeals, 2000)
Williams v. Kemp (In Re Kemp)
242 B.R. 178 (Eighth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
998 S.W.2d 810, 1999 Mo. App. LEXIS 943, 1999 WL 460924, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-v-eurostyle-inc-moctapp-1999.