State ex rel. Griffin v. R.L. Persons Construction, Inc.

193 S.W.3d 424, 2006 Mo. App. LEXIS 803, 2006 WL 1587453
CourtMissouri Court of Appeals
DecidedJune 12, 2006
DocketNo. 26562
StatusPublished
Cited by2 cases

This text of 193 S.W.3d 424 (State ex rel. Griffin v. R.L. Persons Construction, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Griffin v. R.L. Persons Construction, Inc., 193 S.W.3d 424, 2006 Mo. App. LEXIS 803, 2006 WL 1587453 (Mo. Ct. App. 2006).

Opinion

ROBERT S. BARNEY, Judge.

On November 21, 2005, this Court issued an opinion in this cause. On March 1, 2006, the Supreme Court of Missouri sustained an application for transfer to that court. On May 31, 2006, the Supreme Court entered an order re-transferring the cause to this Court. The original opinion of this court, which follows, is now readopted and reissued.

James Griffin (“Appellant”) appeals the trial court’s entry of judgment against him and in favor of Respondents R.L. Persons Construction, Inc. (“RLP”) and United States Fidelity and Guarantee Company (“USF & G”) (collectively “Respondents”).1 The trial court’s judgment in favor of Respondents was based on Respondents’ affirmative defense that Appellant’s cause of action for unpaid wages under the Prevail-[426]*426mg Wage Act (“the Act”), sections 290.210 — 290.340, was untimely due to the three-year statute of limitations set out in section 516.400.2 He raises one point in his appeal, discussed below. We affirm the judgment of the trial court.

In reviewing a court-tried case, we must affirm the trial court’s judgment unless the judgment is not supported by substantial evidence, is against the weight of the evidence, or erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). In the present matter, the record reveals that in 1998 RLP, a general construction contractor, received a public works construction contract to build Blanchard Elementary School (“the project”) in Cape Girardeau, Missouri. RLP took out a payment and performance bond with USF & G to cover the project. See § 107.170.2.3 RLP then entered into a subcontract agreement with Gaylon Griffin of Griffin Electric.4 Appellant, who began working for Griffin Electric in August of 1999, was paid $12.70 per hour for his work on the project and also received “time and a half’ for the overtime hours he worked. Appellant worked on the project until December of 1999.

On March 26, 2003, Appellant filed a petition against RLP and USF & G alleging he was underpaid because he was not paid the prevailing wage for the work he performed on the project. See § 522.300.5 He sought the relief provided by section 290.300 of the Act.

In its judgment, the trial court found Appellant began working on the project in September 1999; that he ceased working [427]*427on the project in December 1999; and that he filed his cause of action on March 26, 2003. The trial court also opined that because this Court held in Missouri ex rel. Laszewski v. R.L. Persons Constr., Inc., 136 S.W.3d 863 (Mo.App.2004), “that the statute of limitations for prevailing wage cases is three years from the date the work commenced, pursuant to [section] 516.400,” Appellant’s “action [was] barred by the statute of limitations on the face of his pleadings.” Accordingly, the trial court entered judgment in favor of Respondents and this appeal followed.

We observe that a statute of limitations allows a cause of action to accrue and then cuts off the claim if suit is not filed within a certain period of time. Lomax v. Sewell, 1 S.W.3d 548, 552 (Mo.App.1999). “Generally, a statute of limitations commences running when the right to bring a suit accrues.” Beavers v. Rec. Ass’n of Lake Shore Estates, Inc., 130 S.W.3d 702, 715 (Mo.App.2004). As a general rule, the right to bring suit accrues and the statute of limitations is set into motion “[w]hen the fact of damage becomes capable of ascertainment ...” even if the actual amount of damage is unascer-tainable. M & D Enters., Inc. v. Wolff, 923 S.W.2d 389, 394 (Mo.App.1996). “Normally, the running of the statute [of limitations] is a question of law for the trial court to decide.” Straub v. Tull, 128 S.W.3d 157, 159 (Mo.App.2004). “Such questions of law are granted de novo appellate review with no deference being paid to the trial court’s determination of law.” Id.

In his sole point on appeal, Appellant maintains the ten-year statute of limitations set out in section 516.1106 is the applicable statute of limitations relating to his claim, because it “applies to the cause of action as [Appellant] has pled it, an action on a bond....”7 Appellant asserts that the trial court’s application of the three-year statute of limitations set out in section 516.400 is inapplicable to suits for double wages brought under the Act. Appellant opines that section 516.400 is only applicable “to penalties or forfeitures and, while [section] 290.300 [of the Act] does allow underpaid workmen to recover double their unpaid wages, this is not a ‘penalty or forfeiture[,]’ in that the increased damages are linked to the extent of the harm [and] ... serve[ ] the purpose of compensating workmen ...” for expenses associated with bringing such a suit.

In Laszewski, a laborer (“Laszewski”) sought “unpaid wages” under the Act against the same Respondents as in the instant case. Laszewski, 136 S.W.3d at 865. Among their arguments in Laszew-ski, Respondents contended that Laszew-ski’s claim was governed by either the one-year statute of limitations applicable to penal laws in section 516.380 or the two-year statute of limitations for unpaid wages, set forth in section 290.527. In its judgment, the Laszewski trial court set out that:

[428]*428The court will assume that the prevailing wage statute is a penal statute covered by [sections] 516.380 — 516.420. The present action was commenced within three years of when [Laszewski] began work and pursuant to [section] 516.400 is timely. The penalty portion of the prevailing wage act appears in [section] 290.300 and vests any underpaid workmen with a cause of action for double his underpaid wages. These double damages are not recoverable by anyone who should choose to prosecute, therefore this cause of action does not fall within the parameters of [section] 516.380 and its one-year statute of limitations. The penalty for back due wages is not collectable by the State, which removes this case from the two-year statute of limitations specified in [section] 516.390. The penalty provided by [section] 290.300 is only collectable by underpaid workmen and the cause of action is governed by the statute of limitations set forth in 516.400 and is a three-year statute of limitations.... This came of action having been commenced within three years is therefore timely.

Id. at 872-73 (emphasis added) (internal citations omitted). In affirming the trial court’s determination as to this issue, this Court found there was “no fault with the trial court’s reasoning concerning the law....” Id. at 873.

While acknowledging Laszewski, Appellant attempts to differentiate it from the present matter by asserting that the holding in Laszewski

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sherrita Harris v. Hartford Fire Insurance Co.
781 F.3d 946 (Eighth Circuit, 2015)
Bonney v. Environmental Engineering, Inc.
224 S.W.3d 109 (Missouri Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
193 S.W.3d 424, 2006 Mo. App. LEXIS 803, 2006 WL 1587453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-griffin-v-rl-persons-construction-inc-moctapp-2006.