State Ex Rel. Laszewski v. R.L. Persons Construction, Inc.

136 S.W.3d 863, 2004 Mo. App. LEXIS 912, 2004 WL 1398566
CourtMissouri Court of Appeals
DecidedJune 23, 2004
Docket25592, 25594
StatusPublished
Cited by6 cases

This text of 136 S.W.3d 863 (State Ex Rel. Laszewski v. R.L. Persons Construction, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Laszewski v. R.L. Persons Construction, Inc., 136 S.W.3d 863, 2004 Mo. App. LEXIS 912, 2004 WL 1398566 (Mo. Ct. App. 2004).

Opinion

NANCY STEFFEN RAHMEYER, Chief Judge.

This case presents an action by a laborer for unpaid wages brought against a general contractor and a surety for work performed on two public works construction projects. Both Appellant, Brandon Laszewski (“Laszewski”), and Respondents, R.L. Persons Construction, Inc. (“RLP”) and United States Fidelity and Guarantee Company (“USF & G”), appeal from the trial court’s judgment awarding $40,282.73 to Laszewski. 1

In reviewing a court-tried case, we must affirm the trial court’s judgment unless the judgment is not supported by substantial evidence, is against the weight of the evidence, or erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). 2 Substantial evidence is competent evidence from which the trier of fact could reasonably decide the case. Wallace v. Van Pelt, 969 *866 S.W.2d 380, 382 (Mo.App. W.D.1998). We view the evidence in the light most favorable to the judgment. Searcy v. Seedorff, 8 S.W.3d 113, 116 (Mo. banc 1999). The credibility of witnesses and the weight to be given their testimony is a matter for the trial court, which is free to believe all, part, or none of the testimony of any witness. Harris v. Desisto, 932 S.W.2d 435, 443 (Mo.App. W.D.1996).

The record reveals that RLP, a general construction contractor, was awarded two public works contracts in 1998 and 1999. The first project was for the construction of the Blanchard Elementary School in Cape Girardeau, Missouri, (“the Cape project”), and the second project was for the construction of the New Madrid Juvenile Center in New Madrid, Missouri (the New Madrid project) (collectively, “the public works projects”). In 1999, RLP also accepted a non-public works contract with American Superstores to construct a commercial budding in Poplar Bluff, Missouri (“the Poplar Bluff project”). RLP enlisted USF & G as a surety and USF & G issued payment and performance bonds to cover RLP on the public works projects. 3 As both the Cape project and the New Madrid project met the definitions of Missouri’s Prevailing Wage Act (“the Act”) as “new construction by a public body,” RLP was required by Section 290.230 to pay “[n]ot less than the prevailing hourly rate of wages for work of a similar character in the locality.” 4

On June 29,1998, RLP and Griffin Electric (“Griffin”), a business owned by Gay-Ion Griffin, entered into a subcontract agreement wherein Griffin subcontracted to perform electrical work on the Cape project by providing labor and materials in exchange for a quoted contract price of $328,687.00. Later, Griffin also agreed to perform electrical work for RLP on both the New Madrid Project and the Poplar Bluff project.

Laszewski, who was not a licensed electrician, worked intermittently for Griffin between 1996 and 1999. Though on previous occasions, and on the Poplar Bluff project, Griffin had paid him $8.00 per hour, Laszewski was paid $12.70 per hour for his work on the public works projects. The prevailing wage for an electrician on the particular public works projects at issue was $36.55 per hour.

On July 12, 2001, the Division of Labor Standards notified Laszewski that, after investigating a complaint filed with their office, they believed that Laszewski had been underpaid for the work he did on the two public works projects for RLP and Griffin. 5 Laszewski brought suit under Section 290.300 against both RLP, the *867 prime contractor on the projects, and USF & G, as the surety, alleging that he had been underpaid and should have received $36.55 per hour, the prevailing wage for an electrician on those projects. 6 RLP then filed a third-party petition against the subcontractor, Griffin.

Following a bench-trial, the trial court found in favor of Laszewski. In its detailed “Findings of Fact and Conclusions of Law and Judgment,” the trial court stated that Laszewski’s work from July of 1999 through October of 1999 on the public works projects amounted to “electrical indoor work” under the Act; therefore, he was entitled to be paid the stated prevailing wage of $36.55 per hour, as opposed to the $12.70 or $12.75 per hour that he actually received. As Laszewski was paid a total of $7,513.45 for his services when he should have received $21,654.50, the total unpaid prevailing wages owed to Laszew-ski were $14,051.05. Further, he was entitled to double the unpaid wages under Section 290.300 or an amount of $28,102.10. The trial court also awarded Laszewski reasonable attorney fees in the amount of $3,750.00 for thirty hours of his counsel’s services.

Thereafter, the trial court entered judgment in favor of Laszewski and against RLP in the amount of $40,282.73. 7 Additionally, the trial court found that RLP was entitled to recover the full amount of the judgment from Griffin and entered an order against Griffin for $40,282.73. These appeals by RLP, 8 USF & G, and Laszewski followed.

Respondents bring three points on appeal. First, Respondents assert that the trial court’s finding that it was “unnecessary” to determine Laszewski’s “employment status” impermissibly broadens the plain language of the Prevailing Wage Act. Specifically, Respondents allege that prevailing wages are,required to be paid to workmen “employed” on a public works project, and not to independent contractors such as Laszewski. Respondents argue that Laszewski must be an employee to be subject to the prevailing wage act but the evidence supports an inference that Laszewski was an independent contractor and not an employee. Respondents argue that to hold otherwise violates the due process rights of the general contractors, as well as the subcontractors. Second, Respondents state that the trial court erred in awarding $28,102.10 in unpaid prevailing wages to Laszewski because there was no evidence of his actual dates of employment and the trial court used impermissible inferences to ascertain the dates of employment from cancelled *868 checks. Third, Respondents argue that Laszewski’s claim was governed by either the one-year statute of limitations applicable to penal laws in Section 516.380 or the two-year statute of limitations as set forth in Section 290.527, and therefore, was not timely filed.

Laszewski also alleges three points of trial court error. First, he asserts that the trial court erred in entering the judgment which included an award of attorney fees and in denying his motion to reopen the evidence. He asserts that he is entitled by statute to reasonable attorney fees and, even though his request for a hearing was not made until after the close of evidence, the trial court erred in not granting him a hearing on attorney fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mihlfeld & Associates, Inc. v. Bishop & Bishop, L.L.C.
295 S.W.3d 163 (Missouri Court of Appeals, 2009)
Bonney v. Environmental Engineering, Inc.
224 S.W.3d 109 (Missouri Court of Appeals, 2007)
State ex rel. Griffin v. R.L. Persons Construction, Inc.
193 S.W.3d 424 (Missouri Court of Appeals, 2006)
Trimble v. Pracna
167 S.W.3d 706 (Supreme Court of Missouri, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
136 S.W.3d 863, 2004 Mo. App. LEXIS 912, 2004 WL 1398566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-laszewski-v-rl-persons-construction-inc-moctapp-2004.