Board of Education ex rel. Bertolino v. Vince Kelly Construction Co.

963 S.W.2d 331, 1997 Mo. App. LEXIS 2141
CourtMissouri Court of Appeals
DecidedDecember 16, 1997
DocketNo. 71695
StatusPublished
Cited by1 cases

This text of 963 S.W.2d 331 (Board of Education ex rel. Bertolino v. Vince Kelly Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education ex rel. Bertolino v. Vince Kelly Construction Co., 963 S.W.2d 331, 1997 Mo. App. LEXIS 2141 (Mo. Ct. App. 1997).

Opinion

RHODES RUSSELL, Judge.

Defendant, Reliance Insurance Company (“surety”) appeals from the judgment entered upon a jury verdict entered in favor of plaintiff, John Bertolino, d/b/a Bertolino Sheet Metal Company (“materialman”). At issue in this case is whether the joint check rule applies to a public contract and, if so, whether a surety was entitled to a directed verdict on a materialman’s claim for payment on a Labor and Material Payment Bond where the materialman endorsed a joint check but did not receive all of the proceeds thereof from the co-payee. We find the joint check rule applies to a public contract and to the facts of this case. We accordingly reverse the trial court’s judgment.1

Vince Kelly Construction Company, Inc. (Kelly) entered into a contract with the City of St. Louis to renovate the Farragut and Woerner Schools. Kelly then sub-contracted with Hart Mechanical (Hart) to perform certain mechanical work at the two schools. Hart in turn engaged materialman to perform ventilation work on the projects. Pursuant to section 107.170, RSMo 1994,2 Kelly obtained a Contract Labor and Material Payment Bond from surety.

Materialman commenced work on the projects in the fall of 1990. Soon thereafter, he became concerned about Hart’s financial security. As a result of this concern, he submitted an invoice dated February 8, 1991 which showed $12,600.00 due on the December 1990 billing and $9,000.00 due on the January 1991 billing.

On February 14,1991, Kelly issued a check payable jointly to Hart and materialman in the amount of $21,600. Both parties endorsed the check and Hart then wrote mate-rialman a check for $8080.22, promising to pay the balance the following month. However, Hart never paid materialman. Hart subsequently walked off the job due to financial difficulty.

On May 9,1991, materialman sent a statement to Kelly showing a past due amount for work billed in December 1990 and January 1991 of $13,519.78. Kelly issued a check in [333]*333this amount on May 16, 1991. In March 1992, materialman sent Kelly a final bill in the amount of $10,507.00. Kelly refused to pay.

On July 20, 1992, materialman sent a demand letter to Kelly and surety at a local address claiming it was owed $10,507.00 on the school projects.3 The bond claims attorney from surety advised that surety had not received the correspondence until September 29 and asked materialman to fill in a claim form and submit information to surety. Surety advised materialman of Kelly’s position that materialman had been overpaid $3,515.78 by means of a joint check.

Materialman filed a petition on the contractor’s bond to establish its claim against Kelly and surety under section 522.300. At trial surety moved for a directed verdict at the close of all evidence, which the trial court denied. Materialman dismissed Kelly before the case was submitted to the jury. The jury returned a verdict in materialman’s favor and it awarded materialman payment on the bond, and it also awarded interest, penalties for vexatious refusal to pay, and attorney’s fees. Surety subsequently filed a motion for judgment notwithstanding the verdict (JNOV) and for a new trial, which the trial court denied. This appeal follows.

Surety raises four points on appeal. Surety first argues that the trial court erred in denying its motion to dismiss materialman’s second amended petition for failing to state a claim upon which relief could be granted in that materialman failed to plead surety’s legal capacity to be sued as a corporation. In its second point, surety contends the trial court erred in denying its motion for a directed verdict and its motion for JNOV in that materialman was deemed to have received the money due to him by endorsing the joint cheek made payable both to materi-alman and Hart. In its third point, surety maintains the trial court erred in denying its motion for directed verdict and JNOV because there was insufficient evidence adduced at trial to avoid the application of the joint cheek rule, and that there was insufficient evidence presented that its refusal to pay materialman’s claim was willful and without reasonable cause or excuse. Finally, surety contends that the trial court erred in refusing three jury instructions based upon the affirmative defense of the joint check rule. Because we find points two and three to be dispositive, we do not address points one and four.

In reviewing the denial of a motion for a directed verdict, we view the evidence in the light most favorable to the plaintiff. Seidel v. Gordon Gundaker Real Estate Co., 904 S.W.2d 357, 361 (Mo.App.1995). A directed verdict is a drastic action and should only be granted where reasonable persons could not differ on a correct disposition of the case. Id.

Surety argues that the trial court erred in denying its motions for directed verdict and for JNOV because under the joint check rule and section 400-3-310(b) governing the discharge of obligations, materialman has not only been paid in full, but has been overpaid. In response, materialman argues that the joint check rule is foreign to Missouri law and alternatively, that even if accepted, the joint check rule would not apply to this ease.

The joint check rule provides that, in the absence of an agreement to the contrary, if a material supplier receives and endorses a joint check without collecting the amount then due from the maker, the supplier is not entitled to assert a mechanic’s lien or payment bond claim. Post Bros. Constr. Co. v. Yoder, 20 Cal.3d 1, 141 Cal.Rptr. 28, 569 P.2d 133 (1977); See also Sidney R. Barrett, Jr., Joint Check Arrangements: Release for the General Contractor and Its Surety, 8 CONSTR. LAW. 7 (1988).

The Missouri Court of Appeals adopted the joint check rule in Southwest Hardware & Lumber Co. v. Borgerson, 77 S.W.2d 195 (Mo.App.1934). There, the owners of a house appealed from a judgment ordering them to pay a supplier $1,041.52 for materials furnished in the construction of [334]*334their house. The owners argued that they had already paid the supplier in full through cheeks payable jointly to the supplier and the contractor and that supplier had, by endorsing the checks, waived his right to further payment from them. Id. at 196. The court of appeals reversed the trial court, holding that the supplier had received the money due him as a matter of law. Id. at 197. The court reasoned that because the supplier had turned its portion of the joint checks over to the contractor by choice, it could only look to the contractor for repayment. Id. The joint check rule has been widely adopted by other state courts.4 The dual purpose of the rule, as explained by the adopting courts, is to protect suppliers and laborers by ensuring payment and also to protect owners and general contractors by eliminating potential lien claims.

The next question is whether the joint check rule applies to public construction projects. Under Missouri law, public and private construction projects are treated differently due to the fact that mechanic’s liens are unavailable on public land. Redbird Eng’g Sales, Inc. v. Bi-State Development Agency etc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board v. Eurostyle, Inc.
998 S.W.2d 810 (Missouri Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
963 S.W.2d 331, 1997 Mo. App. LEXIS 2141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-ex-rel-bertolino-v-vince-kelly-construction-co-moctapp-1997.