United States Ex Rel. Marmet Corp. v. Becon Services Corp.

794 F. Supp. 428, 38 Cont. Cas. Fed. 76,372, 1992 U.S. Dist. LEXIS 10482, 1992 WL 180724
CourtDistrict Court, District of Columbia
DecidedJuly 17, 1992
DocketCiv. A. 91-2502
StatusPublished
Cited by1 cases

This text of 794 F. Supp. 428 (United States Ex Rel. Marmet Corp. v. Becon Services Corp.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Marmet Corp. v. Becon Services Corp., 794 F. Supp. 428, 38 Cont. Cas. Fed. 76,372, 1992 U.S. Dist. LEXIS 10482, 1992 WL 180724 (D.D.C. 1992).

Opinion

MEMORANDUM AND OPINION

REVERCOMB, District Judge.

Plaintiff seeks recovery under the Miller Act (40 U.S.C. § 270b) for allegedly unpaid construction material bills. Both plaintiff and defendants now move for summary judgment. The Court heard full argument on the motions at a hearing conducted on July 15, 1992, based on the facts as set forth in the parties’ pleadings and affidavits. The parties agree that there are no material facts in dispute. For the reasons set forth below, the Court must order summary judgment in favor of the plaintiff. Facts

The essential facts are as follows. Defendant Becon Services Corporation was the prime contractor to the Department of the Army for a construction project in Washington, D.C. Defendant Aetna was Becon’s surety on the contract. Becon subcontracted Olympus Glass to furnish a portion of labor and materials for the job. Olympus, in turn, contracted with defendant Marmet Corporation, a materialman, to supply materials. Olympus arranged with Becon to pay Marmet’s billings with checks made payable jointly to Olympus and Marmet. Olympus also entered into a “retainage agreement” with Marmet under which Olympus would withhold for a period of months 10 percent of amounts owing to Marmet for materials it supplied. Becon was not privy to this retainage agreement, which Marmet characterizes without contradiction as “an adhesion contract” prepared by Olympus.

Marmet provided all the materials ordered and, between June and November 1990, sent Olympus eight separate invoices which Olympus forwarded to Becon. In response, between September and December 1990, Becon issued four joint checks payable to Olympus and Marmet in the exact amounts stated on the Marmet invoices. 1 The dispute in this case arises from *429 the circumstances surrounding these four joint checks.

Becon points to the amount of these joint checks as “[mjanifestly” indicating its espoused intent that the checks were to serve as full payment for Marmet’s materials invoices. However, upon receipt of the first of these checks, which was made out for the combined amount of Marmet’s first two invoices, Olympus’ administrative manager wrote to Marmet on October 1, 1990, stating

[w]e are in receipt of a check from Becon Services in the amount of $138,153.00 which represents a partial payment on our account with them. This check has been issued jointly to us and your company as we requested it to be.
We intend to endorse this check over to you under the following conditions.
We will pay 90% of your invoice a 34952 which amount [sic] to $83219 from this draw. A company check from Mar-met Corporation will be issued to Olympus Glass in the amount of $54,933.60 and sent via Federal Express to Olympus Glass....

The amount proffered by Olympus — $83,-219 — equals 90 percent of the amount of Marmet’s first invoice, indicating the administrative manager’s apparent belief that Becon was remitting payment for only one invoice. Marmet subsequently accepted the administrative manager’s proposal, received and deposited the Becon check, and then sent Olympus a check for $54,933.60— presumably to cover $9,246.60 in retainage, i.e., 10 percent of the first invoice, and $45,687 in supposed excess to Marmet— “believ[ing] that it was not entitled to keep more than $83,219.00 from [Beacon’s] ... check because of the information given to Marmet by the Olympus Glass letter of 10/1/90 and the terms of the supply contract regarding retainage.” Marmet Statement of Undisputed Material Facts, para. 23.

Regarding the second and third joint checks, Marmet states that Olympus did not request, and so Marmet did not pay, any retainage. However, Becon’s fourth joint check, dated December 11, 1990, was payable in the amount of $104,276.00; on this check, “Marmet negotiated for a reduced retainage, and the two parties [Olympus, and Marmet] agreed upon a re-tainage of $8,941.20.” Plaintiff’s Memorandum in Support of Summary Judgment at 4. As before, Olympus endorsed the Becon check and sent it to Marmet, and Marmet endorsed and deposited that check and sent Olympus its own check for $8,941.20.

It is thus clear that Marmet received full payment, at least physically, for all eight of its invoices but voluntarily returned a total of $63,847.80 to Olympus in compliance with Olympus’ directions pursuant to the retainage agreement. Ultimately, Olympus defaulted on its agreement to pay Mar-met the retainage Marmet remitted. Mar-met now seeks an award against Becon of $58,981.80 based on the following calculation:

$ 267,646.63 sum due Marmet under contract w/ Olympus $ 138,153.00 joint checks from Becon

10,818.00

3,477.00

104.276.00

$ 256.724.00

$ 15,000.00 other checks from Olympus

815.63

$ 15.815.63

$ 272,539.63 total checks to Marmet

*430 $ 54,933.60 amounts returned by Marmet 8.941.20

$ (63,874.80) total returned by Marmet

$(208,664.83) $ 208,664.83 amount retained by Marmet

$ 58,891.80

Discussion

The above facts present a close case, since there are considerable equities and inadequacies on both sides. Defendant Be-con argues in essence that, by making out its joint checks in the amounts of Marmet’s invoices, it effectively directed the application of its payment — as is its right to do— and that it should not be subject to the retainage agreement, under which Marmet returned money to Olympus, to which it was not privy and of which it had no knowledge. Becon points out that the Marmet invoices it paid were all prominently marked “no retainage allowed” and that, although Marmet may not have been party to Olympus’ joint check agreement with Becon, Marmet was placed on notice of this agreement by Olympus’ October 1, 1990, letter, which Marmet received before obtaining any payments on the contract. Be-con argues that it should not be required to pay twice for the supplies it received.

Marmet, for its part, points to the general rules relating to allocation of payments from a prime contractor in Miller Act cases, see Silver Hill Concrete Corp. v. Thomason Indus., 556 F.Supp. 291, 293-94 (D.D.C.1982), aff'd 704 F.2d 1294 (D.C.Cir.1983), which provide that an undesignated payment from a prime contractor is to be applied as the debtor (i.e., the subcontractor) intends and directs, and that the substantial burden of proving sufficient designation by the prime contractor and misapplication by the supplier lies with the prime contractor. In this regard, the Court notes the further admonition of Silver Hill, quoted but not discussed by plaintiff, that

If the debtor [the subcontractor] is under a duty to a third person [the prime contractor] to devote funds paid by him to discharge a particular debt, the payment must be so applied if the creditor [the supplier]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education ex rel. Bertolino v. Vince Kelly Construction Co.
963 S.W.2d 331 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
794 F. Supp. 428, 38 Cont. Cas. Fed. 76,372, 1992 U.S. Dist. LEXIS 10482, 1992 WL 180724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-marmet-corp-v-becon-services-corp-dcd-1992.