Eugene L. Lane D/B/A Commercial Construction Co. v. Geiger-Berger Associates, P.C.

608 F.2d 1148, 1979 U.S. App. LEXIS 10578
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 9, 1979
Docket79-1216
StatusPublished
Cited by11 cases

This text of 608 F.2d 1148 (Eugene L. Lane D/B/A Commercial Construction Co. v. Geiger-Berger Associates, P.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eugene L. Lane D/B/A Commercial Construction Co. v. Geiger-Berger Associates, P.C., 608 F.2d 1148, 1979 U.S. App. LEXIS 10578 (8th Cir. 1979).

Opinion

REGAN, District Judge.

In this diversity action a jury found Geiger-Berger Associates, Inc., P.C. liable on plaintiff’s third party claim for indemnity. By this appeal from the resultant judgment, reversal is sought on the basis of asserted trial errors.

The controversy stems from the construction of the Hammond Center (the multipurpose recreation building) at the Southwest Missouri State University in Springfield, Missouri, for which B. B. Andersen Company, Inc. was general contractor. The structural plans and drawings for the building had been prepared by Geiger-Berger, a structural engineering firm. Eugene L. Lane entered into a subcontract with Andersen for the performance of certain fill and excavation and related work called for by Geiger-Berger’s plans and specifications. Lane’s contract, although dated January 27, 1975, was actually executed by him after February 5, 1975.

After Lane had completed a substantial amount of work, a dispute arose between Lane and Andersen concerning the extent of soil excavation and the kind of fill material required to bring the project site up to finish grade. Lane contended that the entire site had to be excavated to a minimum depth of seven feet and that the fill material was to be “crushed rock sub-base material” which had been excluded from his contract. On the other hand, it was Andersen’s position that only the excavation to insert the footings was required and (more importantly) that on-site clay material was suitable for use as fill. The use of the clay fill material would have greatly increased Lane’s costs. This contractual dispute was submitted by Andersen to the project architect for his interpretation of the pertinent drawings and specifications. The contract contained a provision to the effect that the decision of the architect “as to the true construction and meaning of the drawings and specifications shall be final.”

On July 1, 1975, the project architect issued his interpretation sustaining Andersen’s contentions, following which Andersen demanded that Lane complete the contract by utilizing the clay material as fill. Upon Lane’s refusal to do so, insisting that his contract made no such requirement, Andersen terminated the subcontract and expended a large sum (allegedly approximately $240,000) to complete the job. Lane subsequently filed suit against Andersen seeking to recover amounts allegedly owing under his subcontract and for damages. Andersen counterclaimed for his expenditures in completing Lane’s subcontract. Lane then filed a third party claim against Geiger-Berger for indemnity. Prior to trial, Lane settled the Andersen claim. Before finalizing the settlement, Lane submitted it to Geiger-Berger for approval, tendering it the defense of the claim in the event the settlement was disapproved. However, Geiger-Berger refused either to approve or disapprove the settlement or to assume Lane’s defense. Lane then settled the claim for $73,500.

During the trial of this action, the parties stipulated that Lane had a potential liability to Andersen with a maximum exposure of $240,000 and that the settlement of that potential liability for $73,500 was reasonable as between Lane and Andersen. It was further stipulated that Lane’s expenditure for attorneys’ fees and expenses in the Andersen litigation was fair, just and reasonable. Hence, the issue of Geiger-Berger’s liability having been found for Lane, the jury awarded him (by direction of the Court, not excepted to) the sum of $99,-146.97.

The thrust of Lane’s claim for indemnity is that the obligation under his subcontract to pay the increased cost resulting from the use of clay material as fill was proximately caused by the negligence of Geiger-Berger *1151 in preparing the structural plans and drawings or by its February 5, 1975 affirmative oral misrepresentations (on which Lane relied in entering into the contract) that crushed rock fill (which he had excluded from the subcontract) was required. Verdict-directing instructions were given on both theories.

I

This appeal does not bring into question Lane’s right under Missouri law to indemnity from Geiger-Berger. The principal assignment of error relates to the damage instruction which directed the jury to award Lane $99,146.97 if the jury found for him on the issue of liability. This claim of error, raised for the first time on appeal, is premised on the contention that under “current” Missouri law governing allegedly comparable situations (Missouri Pacific Railroad Co. v. Whitehead & Kales Co., 566 S.W.2d 466 (Mo. en banc 1978) an “all or nothing” damage instruction is improper, and that in lieu thereof the jury should have been instructed to apportion the damages between Lane and Geiger-Berger on the basis of their relative responsibility for such damages.

Rule 51 Federal Rules of Civil Procedure explicitly provides that “(n)o party may assign as error the giving or the failure to give an instruction unless he objects thereto before the jury retires to consider the verdict.” Admittedly, Geiger-Berger made no objection at all in the district court to the giving of the “all or nothing” damage instruction, nor did it proffer or request any instruction on apportionment of damages. In this situation, to avoid the reach of Rule 51, Geiger-Berger invokes the “plain error” doctrine, arguing that this alleged “error” unjustly affected its substantial rights, in that by precluding the jury from apportioning the damages, the instruction “forced the jury to place the entire burden of Andersen’s expenses on one of two parties.”

We find no error, much less “plain error,” in the damage instruction. Whitehead & Kales has no application to the facts of this case. What Whitehead & Kales held was merely that where two concurrent or joint tortfeasors are liable to a third party for the damages sustained by said party, a jury should, as between the tortfeasors, determine their relative fault as a predicate to apportioning their liability for such damages, and this is so without regard to labels such as “active-passive” negligence.

It is simply not true that Lane and Geiger-Berger were joint tortfeasors. Andersen had no tort claim against Lane. It sued him for breach of contract, for which Lane alone could be held liable to it. Andersen had no claim at all against Geiger-Berger, and certainly none based on Lane’s breach of contract. And since Lane and Geiger-Berger were not joint tortfeasors, nothing in Whitehead & Kales either authorizes or mandates an apportionment between them of the damages sustained by Andersen on the basis of their relative fault. We add that nothing in the pleadings or in the pre-trial order raises any issue as to apportionment of damages.

II

The only instruction which was objected to in the district court is to the effect that the decision of the architect was final and binding on Lane under the facts. As we have noted, the contract between Lane and Andersen specifically provided that the “[architect’s] decision as to the true construction and meaning of the drawings and specifications shall be final.” The instruction is a correct statement of the applicable law. See 17A C.J.S. Contracts § 326, page 253; Benjamin Foster Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Gruttemeyer v. Transit Authority
31 F.4th 638 (Eighth Circuit, 2022)
Duane L. Hartman v. Bob Workman
476 F.3d 633 (Eighth Circuit, 2007)
Hartman v. Workman
476 F.3d 633 (Eighth Circuit, 2007)
IRS v. Petersen (In Re Petersen)
312 B.R. 385 (N.D. Iowa, 2004)
INGRASSIA CONST. CO. v. Vernon Tp. Bd. of Educ.
784 A.2d 73 (New Jersey Superior Court App Division, 2001)
Baker Electric Cooperative, Inc. v. Chaske
28 F.3d 1466 (Eighth Circuit, 1994)
SWAN CONST. CO., INC. v. Bituminous Cas. Corp.
588 F. Supp. 65 (E.D. Missouri, 1984)
Stephenson v. McClure
606 S.W.2d 208 (Missouri Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
608 F.2d 1148, 1979 U.S. App. LEXIS 10578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eugene-l-lane-dba-commercial-construction-co-v-geiger-berger-ca8-1979.