Global Construction, Inc. v. Missouri Highway & Transportation Commission

963 S.W.2d 340, 1997 Mo. App. LEXIS 2120, 1997 WL 796800
CourtMissouri Court of Appeals
DecidedDecember 16, 1997
DocketNo. WD 53160
StatusPublished
Cited by4 cases

This text of 963 S.W.2d 340 (Global Construction, Inc. v. Missouri Highway & Transportation Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global Construction, Inc. v. Missouri Highway & Transportation Commission, 963 S.W.2d 340, 1997 Mo. App. LEXIS 2120, 1997 WL 796800 (Mo. Ct. App. 1997).

Opinion

HOWARD, Judge.

Global Construction, Inc. (“Global”) sued the Missouri Highway and Transportation Commission (“the Commission”) for breach of a contract to repaint a bridge, alleging that the Commission wrongfully required Global to upgrade its method of containing airborne sandblasting residue. The trial court entered a summary judgment on behalf of the Commission, and Global now appeals, claiming that there is a genuine issue of material fact concerning the contract’s containment standards.

Affirmed.

In the summer of 1992, the Commission solicited bids for a project which involved the sandblasting and repainting of a bridge on Southwest Traffieway in Kansas City, Missouri. Global submitted the lowest bid and, on July 10,1992, entered into a contract with the Commission to make the proposed improvements. According to the express terms of the contract, Global agreed to “comply [342]*342with all federal and state laws and regulations and local ordinances.” In addition, the contract provided that the work would be done in accordance with the Commission’s 1990 Standard Specifications for Highway Construction, which were expressly made “part and parcel of this contract.”

Section 107.1 of the Standard Specifications stated:

Laws to be Observed. The contractor shall at all times observe and comply with all Federal and State laws, local laws, ordinances, orders, decrees, and regulations existing at the time of or enacted subsequent to the execution of the contract which in any manner affect the prosecution of the work.

At the times that the contract was bid, executed, and performed, the following state regulation was in effect:

10 CSR 10-6.170 Restriction of Particulate Matter to the Ambient Air Beyond the Premises of Origin
(1) Restrictions to Limit Fugitive Particulate Matter Emissions.
(A) No person may cause or allow to occur any ... construction or use of a road, driveway or open area ... without applying reasonable measures as may be required to prevent, or in a manner which allows or may allow, fugitive particulate matter to go beyond the premises of origin in quantities that the particulate matter—
1. Remains visible in the ambient air beyond the property line of origin; or
2. May be found on surfaces beyond the property line of origin.

And, at the times that the contract was bid, executed, and performed, § 18.86(e)(2) of the Kansas City, Missouri, Code of General Ordinances was in effect:

(E) Preventing Fugitive Particulate Matter From Becoming Airborne:
(2) Construction, use, repair, demolition: No person may cause or permit ... a road, a driveway, or an open area to be constructed, used, repaired or demolished without applying all such reasonable measures as may be required to prevent fugitive particulate matter from becoming airborne so that it remains visible beyond the premises where it originates or that its presence may be found beyond the premises where it originates.

Global began work under the contract in October of 1992. The contract did not specify the method to be used to contain the particles emitted by the sandblasting, and Global used tarps as a containment device — a method which contained 85% of the emitted particles. In March of 1993, the City of Kansas City, Missouri, notified Global that dust emission from the sandblasting violated the City’s air quality ordinance. On May 7, 1993, a Commission engineer ordered Global to stop work on the project because of the excessive dust emission. At a May 10,1993, meeting attended by representatives from Global, the City, and the Commission, Global was instructed to change to a negative air pressure containment system — a method which contained 100% of the emitted particles. There is no evidence in the record that Global was ever found guilty of, or that Global ever pleaded guilty to, violating the ordinance.

The contract provided that, if Global felt that additional compensation was due for work not clearly covered in the contract, Global could file a claim for adjustment with the Commission. Global made such a claim, seeking additional compensation for the costs associated with the change of containment methods. The Commission denied Global’s cost adjustment claim, and Global subsequently sued the Commission for breach of contract.

Global’s petition for damages alleged that the contract did not contain any specifications for Global’s debris containment operations, and that the Commission wrongfully required Global to upgrade its debris containment operations because the change constituted additional work which was not required by the contract. The petition sought $781,932.53 in damages for the cost of the increased debris containment operations, and $1,016,063.00 in damages from the delay to Global’s other projects caused by the additional time and labor which needed to be applied to the debris containment operations.

[343]*343The Commission filed a motion for summary judgment, claiming that Global could not, as a matter of law, recover under the theory of liability asserted in its petition. The Commission stated that “it is very difficult to ascertain plaintiffs liability theory from the petition,” but concluded that Global’s suit was predicated, upon the proposition that the contract should have specified a method of containment, and that the Commission’s failure to include such a provision rendered them liable for breach of contract. The Commission argued that Global could recover under a defective contract theory only if the missing provision was a design specification, and that any provision specifying a method of containment would have been a performance specification.

The trial court granted the Commission’s motion for summary judgment, stating that

To find a submissible theory of liability, this Court would have to determine, in accordance with Global’s theory of recovery, that [the Commission] should have had a detail design specification in the contract for dust containment and because it did not the contract was ambiguous.
The Court finds, however, that the contract was an unambiguous performance specification placing on Global the duty and cost to comply with the applicable Kansas City Ordinance and State Regulation which clearly informed Global the result it was to obtain regarding fugitive particulate matter generated by its sandblasting. (Emphasis in the original.)

Therefore, the trial court concluded, “Global cannot recover on its defective containment specification theory of liability.”

The trial court’s decision was correct in its analysis of the defective specification theory of liability; however, this was not the only theory of liability contained in Global’s petition. While not a model of clarity (as the Commission observed in its motion for summary judgment), Global’s petition does contain another theory of liability, which can best be explained by the following summary of public contract law principles.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Textor Construction, Inc. v. Forsyth R-III School District
60 S.W.3d 692 (Missouri Court of Appeals, 2001)
Lawson v. State
999 S.W.2d 912 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
963 S.W.2d 340, 1997 Mo. App. LEXIS 2120, 1997 WL 796800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-construction-inc-v-missouri-highway-transportation-commission-moctapp-1997.