Environmental Protection, Inspection, & Consulting, Inc. v. City of Kansas City

37 S.W.3d 360, 2000 Mo. App. LEXIS 1914
CourtMissouri Court of Appeals
DecidedDecember 26, 2000
DocketWD 56182, WD 56183
StatusPublished
Cited by18 cases

This text of 37 S.W.3d 360 (Environmental Protection, Inspection, & Consulting, Inc. v. City of Kansas City) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Protection, Inspection, & Consulting, Inc. v. City of Kansas City, 37 S.W.3d 360, 2000 Mo. App. LEXIS 1914 (Mo. Ct. App. 2000).

Opinion

NEWTON, Judge.

The litigation and the eventual appeals between Environmental Protection, Inspection, and Consulting, Inc. (EPIC) and the City of Kansas City, Missouri (KCMo) arose from a construction contract for building a replacement spillway at the Kansas City Zoo. Although the contract provided for an initial completion date of four months, construction of the zoo spillway took fourteen months. The contract specified payment of $400,000.00 for the spillway project. Yet, in the ensuing litigation, EPIC sought the additional sum of $625,000.00 for breach of contract, late payment interest under the Prompt Payment Statute, and $100,000.00 for negligent maintenance of property.

Procedural Background

The litigation over the zoo spillway began in 1994 in the United States District Court. Included in that lawsuit was EPIC’s civil rights action in which KCMo prevailed on summary judgment. The remaining actions were dismissed without prejudice in 1996 and were refiled in the Jackson County Circuit Court the same year.

In the circuit court petition, EPIC reinstituted the actions against KCMo that are the subject of this appeal: Count I, negligent maintenance of property that caused flooding on the work site; Count X, breach of contract for failure to pay amounts due and for late payment interest. Counts II through IX in the petition sought damages for negligence, interference with contract, negligent misrepresentation, fraudulent misrepresentation, and civil conspiracy. The corporate defendants involved were the management, consultant, and engineering firms hired by KCMo for work on the new zoo project. The individual defendants included construction managers, engineers, the KCMo deputy director of Parks and Recreation, the KCMo contract administrator, and a KCMo assistant attorney.

The jury trial began in February 1998 and lasted six weeks. At the end of evidence, the trial court granted directed verdicts for the defendants on Counts II *364 through IX. After argument and submission of Counts I and X, the jury returned unanimous verdicts with money damages for EPIC and against KCMo. On the negligence action, the jury awarded EPIC $40,000.00 after reduction for 20% fault. For breach of contract, the jury set damages at $561,200.00. In addition, the jury imposed interest of $454,572.00 under the Prompt Payment Statute. The total damages awarded to EPIC equaled $1,015,772.00.

In post trial rulings, the trial court granted judgment notwithstanding the verdict (JNOV) for KCMo and set aside EPIC’s $454,572.00 award of late payment interest. The court conditionally granted a new trial for KCMo if the JNOV on Prompt Payment interest were reversed on appeal. In further post-trial rulings, the trial court denied (1) KCMo’s motion for JNOV/new trial on the negligence and breach of contract claims, and (2) EPIC’s motion for attorney fees under the Prompt Payment Statute. In its amended judgment, the trial court upheld EPIC’s damage awards of $40,000.00 for negligent maintenance of property and $561,200.00 for breach of contract for a total judgment of $601,200.00.

Both EPIC and KCMo appeal. Epic’s appeal centers on the Prompt Payment Statute and concerns the JNOV setting aside its $454,572.00 late payment interest award, the ordering of a conditional new trial, and the denial of attorney fees. In its cross appeal, KCMo challenges the denials of its motions for directed verdict and JNOV/new trial on the breach of contract claim.

Factual Background

In May 1992, KCMo awarded EPIC the construction contract on the replacement spillway for the new zoo project. EPIC had submitted the lowest bid. The contract amount for the spillway was $400,000.00, while the projected costs for the entire zoo renovation was $50,000,000.00. EPIC was to receive its compensation in progress payments. The contract set the time for completing the spillway at 120 days or four months. The contract provided procedures for requesting additional time for weather delays and additional compensation for unforeseen conditions requiring extra work.

The work site for the new spillway was on the seven-acre Lake of the Woods in Swope Park in Kansas City, Missouri. Gregory Boulevard ran across the top of the existing dam. While the then-existing spillway had channeled water to the Swope Park Lagoon, the new spillway was to divert water to the Blue River. The new spillway was designed with three components: a concrete box culvert or conduit connecting an inlet structure west of Gregory and an outlet structure east of Gregory. The specifications called for building the spillway without draining the lake. To accomplish this, EPIC was required to build a cofferdam, a temporary structure, to dam up the water to allow excavations for the spillway.

EPIC began its work on the spillway June 20, 1992, but did not complete the project until fourteen months later. The summer months of 1992 brought heavy rainfalls of over fifteen inches. In spite of the adverse weather, EPIC began constructing the cofferdam from the clay under the existing dam. Toward late summer, the cofferdam was complete. By July 1992, EPIC began excavations for the spillway. As work progressed during the fall months, EPIC installed the sheet pill-ing; placed and poured the concrete forms for the box culvert as well as the inlet and outlet structures.

Although the walls of the cofferdam held the water back, water seeped from beneath the cofferdam. The seepage required pumping. In October 1992, the water backup from the seepage caused unsafe conditions and required the inlet structure excavation to be shut down. EPIC consulted with KCMo’s engineers about the seepage problem, which re *365 mained unresolved. To combat the seepage, EPIC received permission from KCMo to inject urethane grout at the base of the cofferdam and to lower the water level of the entire lake. Through its own investigation, EPIC determined that the water flowed from a discrete layer of porous shot rock under the cofferdam. KCMo’s representatives directed EPIC to proceed with removal of the rock.

During the discovery phase of the litigation, EPIC found out about a rock haul road submerged in the lake near the cofferdam. Although KCMo and its engineers knew of the submerged road’s existence, the bidding materials and the contract for the spillway project contained no reference to it. The road had been constructed in 1990 as a part of KCMo’s chlordane remediation project. The materials composing the road were contaminated and consisted of packed rock that was porous and allowed water seepage.

In November 1992, the spillway project suffered another setback. A KCMo work crew entered EPIC’s work site and filled a ditch near the existing spillway with dirt. On November 19, the Kansas City area again experienced heavy rainfall. Because of the blockage by the work crew, the waters rose over the top of the cofferdam and flooded the new spillway work site. The resulting flood created an emergency situation: the police were called; ambulances were placed on standby; Gregory Boulevard had to be closed. Although the cofferdam sustained damage, its walls remained intact. EPIC lost equipment and materials at the work site. The flooding necessitated extensive repairs, replacement, pumping, and cleanup.

In meetings and correspondence, KCMo urged EPIC to timely complete the spillway project. To do so, EPIC provided extra work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PHILIP H. BERGER v. COPELAND CORPORATION, LLC
505 S.W.3d 337 (Missouri Court of Appeals, 2016)
Hutchens v. Burrell, Inc.
342 S.W.3d 399 (Missouri Court of Appeals, 2011)
Newell Rubbermaid, Inc. v. Efficient Solutions, Inc.
252 S.W.3d 164 (Missouri Court of Appeals, 2007)
Finova Capital Corp. v. Ream
230 S.W.3d 35 (Missouri Court of Appeals, 2007)
Pickel v. Gaskin
202 S.W.3d 630 (Missouri Court of Appeals, 2006)
Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc.
171 S.W.3d 81 (Missouri Court of Appeals, 2005)
Mays-Maune & Associates., Inc. v. Werner Bros., Inc.
139 S.W.3d 201 (Missouri Court of Appeals, 2004)
Brockman v. Regency Financial Corp.
124 S.W.3d 43 (Missouri Court of Appeals, 2004)
Schell v. LifeMark Hospitals of Missouri
92 S.W.3d 222 (Missouri Court of Appeals, 2002)
Long v. Interstate Ready-Mix, L.L.C.
83 S.W.3d 571 (Missouri Court of Appeals, 2002)
Missouri Consolidated Health Care Plan v. Community Health Plan
81 S.W.3d 34 (Missouri Court of Appeals, 2002)
Housley v. Mericle
57 S.W.3d 360 (Missouri Court of Appeals, 2001)
Textor Construction, Inc. v. Forsyth R-III School District
60 S.W.3d 692 (Missouri Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
37 S.W.3d 360, 2000 Mo. App. LEXIS 1914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-protection-inspection-consulting-inc-v-city-of-kansas-moctapp-2000.