Penzel Construction Company, Inc. v. Jackson R-2 School District

CourtMissouri Court of Appeals
DecidedNovember 8, 2022
DocketED110487
StatusPublished

This text of Penzel Construction Company, Inc. v. Jackson R-2 School District (Penzel Construction Company, Inc. v. Jackson R-2 School District) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penzel Construction Company, Inc. v. Jackson R-2 School District, (Mo. Ct. App. 2022).

Opinion

In the Missouri Court of Appeals Eastern District DIVISION FOUR

PENZEL CONSTRUCTION COMPANY, ) No. ED110487 INC., ) ) Respondent, ) Appeal from the Circuit Court of ) Cape Girardeau County vs. ) ) Honorable Benjamin F. Lewis JACKSON R-2 SCHOOL DISTRICT, ) ) Appellant. ) Filed: November 8, 2022

Introduction

Jackson R-2 School District (“the District”) appeals the judgment of the 32nd Judicial

Circuit Court denying its motion for an order showing satisfaction of the original judgment

obtained by Penzel Construction Company, Inc. (“Respondent”). The District raises three points

on appeal. In Point I, the District argues the trial court erred in denying its motion for an order

showing satisfaction of the judgment because the money they tendered to Respondent satisfied

the plain and unambiguous meaning of the judgment. In Point II, the District argues the trial

court erred in denying its motion for an order showing satisfaction of the judgment because the

trial court impermissibly altered the judgment by effectively changing the rate of interest due. In

Point III, the District argues the trial court erred in denying its motion for an order showing

satisfaction of the judgment because neither the judgment nor the Prompt Pay Act provide for

compound interest. Because the trial court erroneously applied the law in interpreting the Prompt Pay Act to

provide for compound penalty interest, we grant Point III. Because we grant Point III we grant

Point I. Because Points III and I are dispositive, we decline to address Point II.

We reverse and remand.

Factual and Procedural History

This case comes to us for the third time. The District sought to build an addition to

Jackson High School. As part of the bidding process, the District provided plans to Respondent,

which in turn provided the plans to its subcontractor Total Electric, Inc. Neither Respondent nor

Total Electric recognized errors in the plans. Total Electric submitted a $1,040,444.00 bid to

Respondent for electrical work. On September 15, 2006, the District contracted with Respondent

and Respondent subcontracted with Total Electric. The District notified Respondent it expected

substantial completion within 550 days. Total Electric substantially completed its work

significantly late and claimed the delay resulted from defects in the plans. The District refused to

pay Respondent. Penzel Constr. Co., Inc. v. Jackson R-2 Sch. Dist. (Penzel II), 635 S.W.3d 109,

139 (Mo. App. E.D. 2021), reh'g and/or transfer denied (Aug. 23, 2021), transfer denied (Dec.

21, 2021).

Respondent sued the District for breach of contract and raised a claim under section

34.057 (the “Prompt Pay Act”),1 arguing the District made an implied warranty the plans were

adequate and complete and the defective plans harmed Total Electric. In July 2010, Total

Electric authorized Respondent to pursue Total Electric’s claims. Respondent filed an amended

petition seeking damages for Total Electric and for Respondent’s markup for overhead and profit

caused by the defective plans provided by the District.

1 All statutory citations are to RSMo (2000), unless otherwise indicated.

2 The trial court entered summary judgment for the District. On appeal, this court reversed

and remanded in Penzel Constr. Co., Inc. v. Jackson R-2 Sch. Dist. (Penzel I), 544 S.W.3d 214

(Mo. App. E.D. 2017). On remand, a jury awarded Respondent $800,000.00 in damages. The

trial court’s judgment (“Judgment”), issued November 14, 2019, awarded Respondent: (1) the

$800,000.00 principal; (2) nine percent annual pre-judgment interest beginning May 10, 2020;

(3) Prompt Pay penalty interest “at the rate of one and one half percent (1½%) per month

commencing May 10, 2010”; and (4) $630,884.00 in attorney’s fees. The trial court assessed

costs against the District. The trial court denied the District’s post-trial motions for judgment

notwithstanding the verdict and for a new trial. On appeal, this Court affirmed in Penzel II, 635

S.W.3d 109.

The District paid Respondent and Total Electric $4,585,762.94. The District asserts this

amount includes the judgment principal, pre-judgment and post-judgment interest, attorneys’

fees, costs, and Prompt Pay penalty interest calculated at one and a half percent per month in

simple interest. On February 28, 2022, the District moved under Rule 74.11(c) for an order

showing satisfaction of the Judgment.2 On April 5, 2022, the trial court entered an order and

judgment denying the District’s motion. The trial court found the District had not satisfied the

Judgment because the District calculated the Prompt Pay Act penalty in simple interest. The trial

court reasoned the Prompt Pay Act provides for compounding penalty interest through its use of

a monthly rather than an annual interest provision so the District’s payment did not satisfy the

Judgment.

This appeal follows.

2 All Rule citations are to the Missouri Supreme Court Rules (2022), unless otherwise indicated.

3 Standard of Review

We review a trial court’s ruling on a Rule 74.11(c) motion under the standard in Murphy

v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). McLean v. First Horizon Home Loan, Corp.,

369 S.W.3d 794, 799 (Mo. App. W.D. 2012) (citing Rhodus v. McKinley, 71 S.W.3d 191, 195

(Mo. App. W.D. 2002)). We will affirm the trial court’s judgment unless there is no substantial

evidence to support it, it is against the weight of the evidence, or it erroneously declares or

applies the law. Id. We review questions of statutory interpretation de novo. Truman Med. Ctr.,

Inc. v. Am. Standard Ins. Co., 508 S.W.3d 122, 124 (Mo. App. W.D. 2017) (citing Ivie v. Smith,

439 S.W.3d 189, 202 (Mo. banc 2014)).

Discussion

Point III: Penalty Interest Under the Prompt Pay Act

We take Appellant’s points out of order to ease our analysis. The District argues, in

denying its motion for an order showing satisfaction of the Judgment, the trial court erred by

adding an unexpressed provision of compound interest to the Judgment and to the Prompt Pay

Act. The District argues the Judgment and the Prompt Pay Act provide only for simple interest,

which the District paid in full.

The District argues the trial court erred in finding it granted compound interest not

expressly stated in its Judgment. Medlin v. RLC, Inc., 467 S.W.3d 865, 869 (Mo. App. S.D.

2015). The District argues the Prompt Pay Act, under which the Judgment awarded penalty

interest, is silent on compound interest and therefore provides only for simple interest. The

District contends no case holds the Prompt Pay Act provides for compound interest and cites

cases which reject attempts to read language into statutes or contracts. Stoner v. Evans, 38 Mo.

461 (Mo. 1866); Wallemann v. Wallemann, 817 S.W.2d 548, 549 (Mo. App. E.D. 1991). The

4 District argues it satisfied the Judgment because it paid Respondent “$1,691,346.54 for ‘Prompt

Pay penalty interest at the rate of one and one half percent (1½%) per month commencing May

10, 2010’ for 140.945545 months from May 10, 2010, to February 7, 2022, on the principal sum

of $800,000.00.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richardson v. QuikTrip Corp.
81 S.W.3d 54 (Missouri Court of Appeals, 2002)
Fru-Con/Fluor Daniel Joint Venture v. Corrigan Bros., Inc.
154 S.W.3d 330 (Missouri Court of Appeals, 2004)
SD Investments, Inc. v. Michael-Paul, L.L.C.
157 S.W.3d 782 (Missouri Court of Appeals, 2005)
Garza v. Valley Crest Landscape Maintenance, Inc.
224 S.W.3d 61 (Missouri Court of Appeals, 2007)
Daniels v. Board of Curators
51 S.W.3d 1 (Missouri Court of Appeals, 2001)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Murphy v. Carron
536 S.W.2d 30 (Supreme Court of Missouri, 1976)
Missouri Hospital Ass'n v. Air Conservation Commission of the State
900 S.W.2d 263 (Missouri Court of Appeals, 1995)
Missouri Public Service Co. v. Platte-Clay Electric Cooperative, Inc.
407 S.W.2d 883 (Supreme Court of Missouri, 1966)
McPherson v. U.S. Physicians Mutual Risk Retention Group
99 S.W.3d 462 (Missouri Court of Appeals, 2003)
Nelson v. Crane
187 S.W.3d 868 (Supreme Court of Missouri, 2006)
Husch & Eppenberger, LLC v. Eisenberg
213 S.W.3d 124 (Missouri Court of Appeals, 2006)
State v. Sledd
949 S.W.2d 643 (Missouri Court of Appeals, 1997)
Metro Auto Auction v. Director of Revenue
707 S.W.2d 397 (Supreme Court of Missouri, 1986)
City of Independence v. Kerr Construction Paving Co.
957 S.W.2d 315 (Missouri Court of Appeals, 1997)
Lucas v. Central Missouri Trust Co.
162 S.W.2d 569 (Supreme Court of Missouri, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
Penzel Construction Company, Inc. v. Jackson R-2 School District, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penzel-construction-company-inc-v-jackson-r-2-school-district-moctapp-2022.