Textor Construction, Inc. v. Forsyth R-III School District

60 S.W.3d 692, 2001 Mo. App. LEXIS 1840, 2001 WL 1195722
CourtMissouri Court of Appeals
DecidedOctober 11, 2001
Docket23744
StatusPublished
Cited by9 cases

This text of 60 S.W.3d 692 (Textor Construction, Inc. v. Forsyth R-III School District) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Textor Construction, Inc. v. Forsyth R-III School District, 60 S.W.3d 692, 2001 Mo. App. LEXIS 1840, 2001 WL 1195722 (Mo. Ct. App. 2001).

Opinion

JOHN E. PARRISH, Presiding Judge.

Forsyth R-III School District (the district) appeals a judgment awarding Tex-tor Construction, Inc., (Textor) damages, including interest awarded under Missouri’s public works prompt payment statute, § 34.057, 1 for the district’s breach of contract and denying the district’s counterclaim against Textor for liquidated damages for failure to timely perform the contract and for repayment of excess amounts the district contended it had paid Textor. This court affirms all parts of the judgment except the interest that was awarded based on § 34.057. That award is reversed.

A judgment in a court-tried case must be affirmed unless there is no substantial evidence to support it, it is against the weight of the evidence or the trial court erroneously declared or applied the law. Rule 84.13(d); Vikings, USA Bootheel v. Modern Day Veterans, 33 S.W.3d 709, 710 (Mo.App.2000). No request was made to the trial court for a statement of the grounds for its decision and the trial court made no such declaration. Thus, all fact issues are considered as having been found in accordance with the result reached. See Rule 73.01(c). “The judgment is to be affirmed on any reasonable theory the record on appeal supports.” In re Trust of Nitsche, 46 S.W.3d 682, 683 (Mo.App.2001).

The district and Textor contracted for construction of additions and alterations to existing school facilities. Textor subcontracted with Larry Snyder & Co. (Snyder) for excavation work on the project. The work included tiering ball fields labeled “Future Ball Field” and “Future Softball Field” on the “Site Plan” that was part of the contract.

William Edward Textor testified that he was vice president of Textor when it con *694 tracted with the district. Mr. Textor explained what was done in the area the site plan designated for ball fields. Dirt was stripped from the area and stored. Dirt that was removed from the ball field areas was used to construct a parking lot and adjacent areas south of the ball field areas. It was also used as fill near the classroom addition and adjacent lawn areas. Mr. Textor explained, “It was removed proportionately from both ballfields [sic] and then the ballfields [sic] were graded and leveled after that point, whenever the building construction was completed.”

Mr. Textor added:
Whenever we stripped off the site, all of the top soil [sic] that we stripped off was stockpiled off to the side. We were instructed to use the best of the top soil [sic] up around the building and the lawn areas because school wanted to get rapid growth, get grass going there as quick as possible.

All areas of the project, other than the ball field areas, were hand-raked in smooth condition. Grass plantings were placed on areas other than the ball field areas by using sod or hydro-mulch and seed. The ball field areas were graded and tiered. They were rock-raked, rolled, and made ready for topsoil.

Textor received a letter dated February 19, 1997, from the superintendent of the district, Dr. Tom Darnell. The letter was hand-delivered by Dr. Darnell to Michael Groom, Textor’s project manager. The letter referenced “Ballfield [sic]” and stated:

On inspection of the site work today of the ballfield [sic] area, it appears to be satisfactory to the best of my knowledge and belief and I will recommend approval of the site area to the school board and the architect. Please note this will have to be signed off through the architect for finalization.
If you have questions concerning this matter, please contact me at 417-546-6384.

The letter was signed “Tom Darnell” as “Superintendent.”

By letter dated February 21, 1997, the district’s architectural firm notified Textor:

It has been brought to my attention that no topsoil has been installed on the athletic fields. I refer you to the enclosed portion of the specifications for Section 221 — Site Grading. Unless other arrangements have been made with the Owner, 4" of topsoil needs to be installed as per specifications on all areas where earthwork has occurred.
Please advise as to why the 4" of topsoil has not been installed in these areas.

The letter was signed by Ken Hamilton on behalf of the architectural firm, Sam A. Winn & Associates Architects, P.C. Mr. Hamilton was identified as “Senior Technician.”

Textor replied by its letter dated February 24, 1997, directed to the attention of Mr. Hamilton. It referenced “Forsyth School Addition Topsoil at Ballpark Area.” The letter advised Mr. Hamilton:

In reference to your letter dated February 21, 1997, I would like to call your attention to Addendum No. # [sic] 3 which states[,] “The ballfields [sic] may be lowered as required to avoid bringing in any fill dirt.” I would also like to call your attention to note # 6 on the revised sheet A-l — Revised: September 8, 1995, which states[,] “Topsoil excavated during the initial grading shall be stockpiled for application during final grading of unpaved areas.”
On September 21, 1995, at 2:18 p.m., I received a bid from Larry Snyder & Company for the sitework on the above captioned project. His bid excluded the import of topsoil. I spoke to Mr. John *695 Montgomery at 2:20 p.m. in regard to his exclusions. He stated that he had spoken with Mr. Graham at Sam Winn and Associates’ office and confirmed that the intent was for the contractor to strip the topsoil from the site and stockpile, balance the site, and reuse existing topsoil. At that time I contacted Mr. David Graham personally to verify that we understood this correctly. He stated that the intent was to reuse the existing topsoil to me as well. We understood that this was changed in order to prevent the enormous cost that would have been encountered had the dirt been hauled in as shown on the original drawings.
We have done exactly as we were instructed. There was, however, very little ‘topsoil’ on the site. We removed all of the top layer of dirt and stockpiled it as we had been directed. We then used most of the good topsoil up around the building. All of the remaining top layer of dirt was spread over the ballfield [sic],
I understand that the school has contracted separately for additional topsoil to be hauled in by another contractor. Please review the information above and call me at your earliest convenience.
If you have any questions, please let me know.

The letter was signed on behalf of Textor by Bill Textor. The letter identified Mr. Textor as “Vice President.”

Textor requested final payment from the district for the balance due on its contract. Its request was dated March 7, 1997. It requested payment of $55,000. The architect issued a “Payment Certificate” dated April 21, 1997, for $16,950.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
60 S.W.3d 692, 2001 Mo. App. LEXIS 1840, 2001 WL 1195722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/textor-construction-inc-v-forsyth-r-iii-school-district-moctapp-2001.