Mays-Maune & Associates., Inc. v. Werner Bros., Inc.

139 S.W.3d 201, 2004 Mo. App. LEXIS 1033, 2004 WL 1554480
CourtMissouri Court of Appeals
DecidedJuly 13, 2004
DocketED 83400
StatusPublished
Cited by10 cases

This text of 139 S.W.3d 201 (Mays-Maune & Associates., Inc. v. Werner Bros., Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mays-Maune & Associates., Inc. v. Werner Bros., Inc., 139 S.W.3d 201, 2004 Mo. App. LEXIS 1033, 2004 WL 1554480 (Mo. Ct. App. 2004).

Opinion

LAWRENCE E. MOONEY, Judge.

Mays-Maune and Assoc., Inc., filed a civil action for money damages against Werner Bros. Inc. (the subcontractor), Bridwell Construction and Design (the general contractor), and Grandview R-II School District (the school district) for failure to pay for building materials supplied by the plaintiff. In its petition, the plaintiff asserted against all three defendants claims of unjust enrichment and violation of the Public Works Prompt Payment Act, 1 and against the subcontractor an additional claim of breach of contract. The plaintiff obtained a default judgment against the subcontractor on its breach-of-contract claim. The trial court granted the remaining defendants’ respective motions to dismiss plaintiffs claims of unjust enrichment and violation of the Prompt Payment Act. The trial court also denied the plaintiffs motion for reconsideration of its order of dismissal of the unjust-enrichment claim filed against the general contractor. The plaintiff appeals from these rulings, presenting four points on appeal. We reverse the judgment dismissing the plaintiffs claim of unjust enrichment against the general contractor and remand the cause. The judgment is otherwise affirmed.

In its first point, the plaintiff alleges that the trial court erred in sustaining the general contractor’s motion to dismiss the plaintiffs claim of unjust enrichment, because the plaintiff sufficiently pleaded a claim of unjust enrichment against the general contractor, in that: (1) the plaintiffs allegation that the school district has not paid the general contractor for the panels does not preclude the plaintiff from pleading in the alternative that the general contractor benefited from the supply of the panels, and (2) even if the school district did not pay the general contractor, the plaintiff sufficiently pleaded a benefit to the general contractor by the plaintiffs supply of the panels, which enabled the general contractor to construct the school and created in the general contractor a right to be paid for the panels.

In its petition, the plaintiff pleaded certain allegations that were common to all counts. As pertinent to this point, the *204 plaintiff pleaded “upon information and belief’ that the school district had contracted with the general contractor for construction of a school and that the general contractor had thereafter contracted with the subcontractor for the supply of certain materials, including the metal wall panels that are the subject of this dispute. The plaintiff further averred that the subcontractor had in turn contracted with the plaintiff for the delivery of the wall panels for a sum certain. The plaintiff also pleaded that it had, in accordance with the terns of the agreement, delivered the panels, which thereafter the subcontractor accepted and incorporated into the construction of the school. The plaintiff pleaded that the sum certain had not been fully paid.

Later in the petition, the plaintiff pleaded certain other allegations as to its claims of unjust enrichment lodged against all three defendants in a single count. After incorporating the prior factual allegations common to all counts and pleading the constituent elements of an unjust-enrichment claim, the plaintiff further pleaded that the school district had not paid the general contractor or anyone else for the metal panels. The plaintiff also alleged that the general contractor had not paid the subcontractor or anyone else for the panels. The plaintiff thereafter pleaded his damages and prayed judgment be entered against all three defendants due to their unjust enrichment.

The general contractor moved to dismiss the unjust-enrichment claim lodged against it due to a single circumstance. In its motion, the general contractor asserted that since the plaintiff had affirmatively alleged that the school district had not paid the general contractor for the wall panels, the general contractor received no benefit and could therefore not have been unjustly enriched. The trial court dismissed the unjust-enrichment claim against the general contractor.

In its first point on appeal, the plaintiff challenges this dismissal in two regards. First, the plaintiff claims that its allegation that the school district had not paid the general contractor was but an alternative factual allegation necessary to plead its claim of unjust enrichment against the school district, which should not serve as the basis for a dismissal of its cause against the general contractor. Second, the plaintiff asserts that even if the school district did not pay the general contractor, the general contractor nonetheless received a benefit by virtue of the plaintiffs supply of the wall panels in that the general contractor was thereby able to construct the school, which created a right in the general contractor to be paid by the school district. We need only consider the plaintiff’s first challenge in this point on appeal to the trial court’s dismissal, since it is dispositive of the plaintiff’s claim of error.

On a motion to dismiss for failure to state a claim, we are required to construe the petition favorably and to give the pleader the benefit of every reasonable and fair intendment in view of the facts alleged and if the pleader’s allegations invoke principles of substantive law that may entitle it to relief, the petition is not to be dismissed. Laclede Gas Co. v. Hampton Speedway Co., 520 S.W.2d 625, 629-630 (Mo.App.1975). If the facts pleaded and the reasonable inferences to be drawn therefrom looked at most favorably from the plaintiffs standpoint show any ground upon which relief may be granted, the plaintiff has the right to proceed. Id. at 630. If the pleader’s allegations invoke substantive principles of law that if proved may entitle it to relief, the petition is not to be dismissed. Id. Under modern pleading principles, a petition is not to be dismissed for failure to state a claim unless *205 it appears that the plaintiff can prove no set of facts in support of his claim which would entitle it to relief. Id. Because the trial court did not state a basis for its dismissal, we presume that dismissal was based on the grounds stated in each motion to dismiss and will affirm if dismissal was appropriate on any ground supported by the motions. Duvall v. Lawrence, 86 S.W.3d 74, 78 (Mo.App. E.D.2002).

The elements of a claim of unjust enrichment are: (1) a benefit conferred upon the defendant by the plaintiff; (2) appreciation by the defendant of the fact of such benefit; and (8) acceptance and retention by the defendant of that benefit under circumstances in which retention without payment would be inequitable. Associate Engineering Co. v. Webbe, 795 S.W.2d 606, 608 (Mo.App. E.D.1990). In the context of a construction case, the plaintiff must plead non-payment by the defendant to anyone else for the benefit in order to state a claim for unjust enrichment. Archway Kitchen & Bath, Inc. v. Lands Development Corp., 888 S.W.2d 13, 14 (Mo.App. E.D.1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
139 S.W.3d 201, 2004 Mo. App. LEXIS 1033, 2004 WL 1554480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mays-maune-associates-inc-v-werner-bros-inc-moctapp-2004.