Childress Painting & Associates, Inc. v. John Q. Hammons Hotels Two, L.P.

106 S.W.3d 558, 2003 Mo. App. LEXIS 825, 2003 WL 21312687
CourtMissouri Court of Appeals
DecidedJune 10, 2003
DocketWD 61062, WD 61069
StatusPublished
Cited by11 cases

This text of 106 S.W.3d 558 (Childress Painting & Associates, Inc. v. John Q. Hammons Hotels Two, L.P.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Childress Painting & Associates, Inc. v. John Q. Hammons Hotels Two, L.P., 106 S.W.3d 558, 2003 Mo. App. LEXIS 825, 2003 WL 21312687 (Mo. Ct. App. 2003).

Opinion

EDWIN H. SMITH, Judge.

Childress Painting and Associates, Inc. (Childress), appeals from the summary judgment of the Circuit Court of Platte County for the respondent, KCC Contractor, Inc. (KCC), on Childress’ claim for payment of $20,948.75, which it claims was due it for subcontracting work done for KCC, the general contractor, on a hotel construction project in Platte County, Missouri. KCC had contracted with John Q. Hammons Hotels Two, L.P., to construct a Homewood Suites hotel. KCC cross-appeals from the trial court’s denial of its request for attorney’s fees.

Of the $20,948.75 Childress claims is owed it by KCC on the project, $8,670 is claimed for work done under the original subcontract, executed on June 14, 1996, for *560 $176,500, while $12,278.75 is for additional work done on a time and materials basis. In Counts II and III of its three-count first amended petition, filed on May 10, 1999, Childress alleged alternative theories of recovery, Count II for unjust enrichment and Count III for breach of contract. In Count I, Childress sought enforcement of a mechanic’s hen, filed on December 17, 1997, for $20,948.75. In addition to payment of the $20,948.75, Childress sought in its lawsuit its attorney’s fees and costs.

In answering Childress’ amended petition, KCC filed what amounted to a general denial. However, in what it denominated as a “counterclaim” for indemnification, but what would appear more accurately to be an affirmative defense to Childress’ claim, KCC essentially admitted that it owed the $8,670 under the parties’ subcontract. As to Childress’ claim for $12,278.75 for additional work on the project, KCC sought to be “indemnified” by Childress, under SECTION 3 of the subcontract, for “damages in an amount equal to the sum of any additional monies which [it might] be obligated to pay [Childress],” over and above the final billing amount of $8,670 that Childress verified to KCC was due it. SECTION 3 reads, in pertinent part:

Within thirty (30) days after the Subcontractor’s last work hereunder, or within thirty (30) days after receipt from the Contractor of a request for a final bill hereunder, the Subcontractor shall send to the Contractor its final bill for all labor and material. Failure to send a final bill within the said thirty (30) days shall be a complete defense to any action of the Subcontractor to collect any such unbilled amount from the Contractor or the Owner. In consideration of the award of this subcontract agreement, the Subcontractor further agrees to indemnify, defend, and hold harmless the Contractor from any losses to the Contractor which arise from any failure on the part of the Subcontractor to comply with the above stated provisions.

KCC also sought payment of attorney’s fees, expenses and costs “necessarily incurred by [it] in defense of [Childress’] action, prosecution of [its] counterclaim and in providing for and arranging the defense of John Q. Hammons Hotels Two, L.P.”

On May 17, 2000, KCC filed a motion for summary judgment on Childress’ claim alleging that in accordance with SECTION 3 of the parties’ subcontract, Childress, in response to KCC’s written request for a final bill, had verified on July 31,1997, that it was owed $8,670 by KCC, entitling KCC to judgment as a matter of law, indemnifying it for any amount Childress was found to be due from KCC over and above the $8,670. No motion was filed as to KCC’s “counterclaim.” On August 21, 2000, the trial court entered a judgment which, although not included in the record on appeal, is described in the trial court’s docket sheet, which is a part of the record, as a summary judgment awarding KCC $15,278 from Childress and interest at 9% from the date of judgment.

On February 2, 2002, the trial court entered an “amended judgment” granting KCC’s motion for summary judgment as to “Counts 1 and 3 of Plaintiffs Amended Petition.” In granting the motion, the trial court: (1) entered judgment for Chil-dress in the amount of $8,760; (2) awarded no attorney’s fees to either party; (3) ordered its prior judgment of August 21, 2000, set aside; and (4) designated its amended judgment for early appeal, pursuant to Rule 74.01(b). 1 Inasmuch as KCC *561 never filed a motion for summary judgment on its counterclaim, the trial court’s summary judgment ruling only addressed KCC’s motion -with respect to Childress’ claim. However, given the trial court’s ruling on KCC’s motion for summary judgment, the counterclaim was rendered moot in that the court’s summary judgment effectively disposed of all the issues raised in KCC’s indemnification “counterclaim.”

We dismiss for lack of jurisdiction.

Appellate Jurisdiction

Childress raises two points on appeal, and KCC raises one point on cross-appeal. However, before addressing those claims on the merits, as in every case, we must first address our jurisdiction, sua sponte. Lumbermens Mut. Cas. v. Thornton, 36 S.W.3d 398, 401 (Mo.App.2000). For the reasons discussed, infra, we find that the summary judgment record was not sufficient to dispose of Childress’ claim on all theories pled such that the trial court’s summary judgment for KCC on Childress’ claim was a partial summary judgment, which is not subject to review as a final judgment.

To be entitled to summary judgment under Rule 74.04, the movant must show that: (1) there is no genuine dispute as to the material facts on which the mov-ant is relying for summary judgment; and (2) based on those undisputed facts, the movant is entitled to judgment as a matter of law. Rule 74.04; ITT Commercial Fin. Corp. v. Mid-Am. Marine Supply Corp., 854 S.W.2d 371, 380 (Mo. banc 1993). If the movant is a defending party, as in our case, a prima facie case for summary judgment can be established by employing one or more of three means: (1) showing undisputed facts that negate any one of the plaintiffs required proof elements; (2) showing that the plaintiff, after an adequate period of discovery, has not produced and will not be able to produce evidence sufficient to allow the trier of fact to find the existence of one or more of the plaintiffs' proof elements; or (3) showing that there is no genuine dispute as to the existence of the facts necessary to prove the movant’s properly pleaded affirmative defense. ITT Commercial Fin. Corp., 854 S.W.2d at 381. “Regardless of which of these three means is employed by the ‘defending party,’ each establishes a right to judgment as a matter of law.” Id.

To be entitled to full summary judgment, a defending party, such as KCC, employing one of the three means for obtaining summary judgment, must allege undisputed facts demonstrating that the plaintiff cannot recover on any theory pled. Ashworth v. City of Moberly, 53 S.W.3d 564, 571 (Mo.App.2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Taney Cnty.
552 S.W.3d 745 (Missouri Court of Appeals, 2018)
Tennille v. Western Union Company
751 F. Supp. 2d 1168 (D. Colorado, 2010)
Cln Properties, Inc. v. Republic Services, Inc.
688 F. Supp. 2d 892 (D. Arizona, 2010)
State Ex Rel. Nixon v. Hughes
281 S.W.3d 902 (Missouri Court of Appeals, 2009)
Hampton v. Carter Enterprises, Inc.
238 S.W.3d 170 (Missouri Court of Appeals, 2007)
Allen v. Midwest Institute of Body Work & Somatic Therapy, L.L.C.
197 S.W.3d 615 (Missouri Court of Appeals, 2006)
Cridlebaugh v. Putnam County State Bank of Milan
192 S.W.3d 540 (Missouri Court of Appeals, 2006)
Firestone v. VanHolt
186 S.W.3d 319 (Missouri Court of Appeals, 2005)
Mays-Maune & Associates., Inc. v. Werner Bros., Inc.
139 S.W.3d 201 (Missouri Court of Appeals, 2004)
Precision Investments, L.L.C. v. Cornerstone Propane, L.P.
119 S.W.3d 611 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
106 S.W.3d 558, 2003 Mo. App. LEXIS 825, 2003 WL 21312687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/childress-painting-associates-inc-v-john-q-hammons-hotels-two-lp-moctapp-2003.