Housing Authority of Clinton Ex Rel. Evans Electrical Construction Co. v. Baumann

512 S.W.2d 436, 1974 Mo. App. LEXIS 1496
CourtMissouri Court of Appeals
DecidedJuly 1, 1974
DocketKCD 26-285
StatusPublished
Cited by20 cases

This text of 512 S.W.2d 436 (Housing Authority of Clinton Ex Rel. Evans Electrical Construction Co. v. Baumann) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Housing Authority of Clinton Ex Rel. Evans Electrical Construction Co. v. Baumann, 512 S.W.2d 436, 1974 Mo. App. LEXIS 1496 (Mo. Ct. App. 1974).

Opinion

SWOFFORD , Judge.

This is an appeal from a money judgment entered in a court-tried case which arose out of a construction project in the City of Clinton, Missouri. On June 28, 1967 the appellant, George E. Baumann d/b/a George E. Baumann Construction Co. (hereinafter referred to as “Bau-mann”), as general contractor entered into a contract with the Housing Authority of the City of Clinton, Missouri (hereinafter referred to as “Authority”) for the construction of 150 low cost housing units together with related facilities. Under Section 107.170 RSMo 1969, V.A.M.S., Bau-mann furnished a performance bond in the penal sum of $1,573,432.63 wherein Bau-mann was principal, and appellant, United Pacific Insurance Company, a corporation (hereinafter referred to as “United”), was surety, under the terms of which bond Baumann and United were jointly and severally liable for the payment of all materials and labor (including those furnished by Baumann’s subcontractors) which were supplied, used or consumed in the construction involved.

On September 1, 1967, Baumann entered into a subcontract with respondent Evans Electrical Company, a corporation (hereinafter referred to as “Evans”) under the terms of which Evans was to furnish all material and perform all work and labor necessary to complete the electrical work on the project for the contract price of $85,400.00. On January 2, 1968, Baumann increased the Evans subcontract by the amount of $4,020.00 for extra work involving the installation of certain air conditioner receptacles, thus, bringing the contract price to $89,420.00. In addition to the above, there was an extra item due Evans in the amount of $173.94 for rewiring work done by Evans because of a construction error by Baumann.

Under the terms of the general construction contract, Baumann was to submit to Authority each month a document styled “Periodical Estimate for Partial Payment” *438 to cover the work performed on the project for the preceding 30-day period. These estimates were to set forth in detail the work completed on the project (including that of subcontractors such as Evans) and the cost and value thereof and the value of the unused materials stored on the job site. These estimates required the approval of the Authority or its architect and upon payment thereof to Baumann, he, in turn, would remit to his subcontractors their proportionate share of such estimates.

Baumann was paid by Authority for the first 16 periodical estimates but it refused to pay estimates No. 17 and No. 18. Authority’s refusal to pay these estimates, was not due to any act or fault of Evans.

Upon such refusal, Baumann shut down the job and on January 29, 1969 he notified Evans in writing, “We are ceasing all operations on the above project as of 4:30 p. m. January 31, 1969, due to the architect’s and owner’s continued default and breach of contract.” At this time the total construction was about 90% completed and Baumann had paid Evans $64,614.20 under the subcontract. There is no dispute as to this amount nor of the fact that on January 31, 1969 Evans had furnished materials and work and labor under its subcontract (and the rewiring above referred to) in a total amount of $80,516.74, thus leaving an unpaid balance due to Evans of $15,902.54.

The record before us shows that Evans made demand upon Baumann for the payment of this balance, but payment was refused. On March 19, 1969, Evans also made a written demand upon United for the payment of this balance. The claims manager for United testified that upon receipt of this demand, the company took no independent action to determine its liability' to Evans under the bond, other than to turn the matter over to Baumann’s attorney for defense. It made no effort to pay or settle the Evans claim, apparently in reliance upon the financial capability of Bau-mann to discharge “his obligations without the assistance of his surety”. United would “therefore leave the settlement discussions on these amounts to Mr. Baumann and his attorney”. No payment was made on the Evans account and this suit was filed.

The court below made extensive findings of fact and conclusions of law and entered a judgment in favor of the plaintiffs and against the defendants for the penal amount of the performance bond, to be satisfied upon the payment by the defendants of $15,902.54 plus the sum of $3,106.30 for interest at the rate of 6% from March 19, 1969 together with costs, and a further judgment against United and in favor of Evans in the amount of $6,719.25 which represented $1,590.25 for statutory penalty for vexatious delay, $5,000.00 attorney’s fee and $129.00 attorney’s expense.

It is from this judgment that this appeal was taken.

The first point raised by appellants is that, because of the terms of the contract between Baumann and Evans (and by reference the terms of the contract between Baumann and Authority) no payment was due Evans for work completed and materials furnished, but not compensated for on January 31, 1969. The basis for such position is that the monthly estimates furnished by Baumann to Authority for the period involved had not been approved or paid.

Appellants completely misconceive .the nature of this action. This is clearly not a suit upon a contract calling into application the principles of contract law relied upon by appellants. Although the execution of the Baumann-Evans contract is alleged the cause of action stated, is a classical example of a suit based upon quantum meruit, for work, labor and material furnished by Evans to Baumann, based upon an implied promise to pay the reasonable value thereof. Such implied promise is imposed by law in the circumstances of this case.

*439 In Paragraph 8 of Count I, in Evans’ petition, it is alleged:

“The reasonable value of the labor and materials supplied and performed under said contract in accordance with Evans bid, and which was done at Baumann’s request and under aforesaid contract was * * * (Emphasis supplied)

The evidence in this record is undisputed that the electrical subcontract with Evans was terminated by Baumann on January 31, 1969 when Baumann “Shut down the job” and thus Evans was prevented from completing his work thereunder. While the reason for Baumann’s action is somewhat obscure, it stemmed from his difficulties with Authority and not from any actions or default of Evans. Likewise, no challenge is made as to the reasonable value of the Evans work and labor and materials furnished to January 31, 1969, nor that $15,902.54 had not been paid. Indeed, this figure is supported by Baumann’s periodical estimate number 18 to Authority and by Baumann’s pending litigation against Authority.

Under such circumstances, Evans had the choice of suing upon a breach of his express contract or upon an implied contract in quantum meruit. The rule is thus stated in Rodgers v. Levy, 199 S.W.2d 79, l.c. 81 (Mo.App.1947):

“It being plaintiff’s contention that defendants wrongfully prevented him from completing the contract, he had a choice of standing on his express contract or of suing on quantum meruit for the value of the labor and materials he had furnished. That such is the law is well settled. . . . We construe plaintiff’s cause of action to be based on quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Legg v. Certain Underwriters at Lloyd's of London
18 S.W.3d 379 (Missouri Court of Appeals, 1999)
State Ex Rel. Webb v. Hartford Casualty Insurance Co.
956 S.W.2d 272 (Missouri Court of Appeals, 1998)
Marcomb v. Hartford Fire Insurance Co.
934 S.W.2d 17 (Missouri Court of Appeals, 1996)
Hopkins v. American Economy Insurance Co.
896 S.W.2d 933 (Missouri Court of Appeals, 1995)
Lindsey Masonry Co. v. Jenkins & Associates Inc.
897 S.W.2d 6 (Missouri Court of Appeals, 1995)
Howard Construction Co. v. Teddy Woods Construction Co.
817 S.W.2d 556 (Missouri Court of Appeals, 1991)
Rosenberg v. Missouri Title Guaranty Co.
764 S.W.2d 684 (Missouri Court of Appeals, 1988)
Ott v. Crews
830 F.2d 773 (Seventh Circuit, 1987)
Dodge v. Fidelity & Deposit Co.
778 P.2d 1236 (Court of Appeals of Arizona, 1986)
Craig v. Iowa Kemper Mutual Insurance Co.
565 S.W.2d 716 (Missouri Court of Appeals, 1978)
Hay v. Utica Mutual Insurance Co.
551 S.W.2d 954 (Missouri Court of Appeals, 1977)
Kay v. Metropolitan Life Insurance Co.
548 S.W.2d 629 (Missouri Court of Appeals, 1977)
Barnhill v. Barnhill
547 S.W.2d 858 (Missouri Court of Appeals, 1977)
State Ex Rel. United States Fidelity & Guaranty Co. v. Walsh
540 S.W.2d 137 (Missouri Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
512 S.W.2d 436, 1974 Mo. App. LEXIS 1496, Counsel Stack Legal Research, https://law.counselstack.com/opinion/housing-authority-of-clinton-ex-rel-evans-electrical-construction-co-v-moctapp-1974.