Oliver L. Taetz, Inc. v. Groff

253 S.W.2d 824, 363 Mo. 825, 1953 Mo. LEXIS 522
CourtSupreme Court of Missouri
DecidedJanuary 9, 1953
Docket42894
StatusPublished
Cited by43 cases

This text of 253 S.W.2d 824 (Oliver L. Taetz, Inc. v. Groff) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oliver L. Taetz, Inc. v. Groff, 253 S.W.2d 824, 363 Mo. 825, 1953 Mo. LEXIS 522 (Mo. 1953).

Opinion

*834 TIPTON, J.

This is an equitable mechanic’s lien suit brought by the respondent, Oliver L. Taetz, Inc., a corporation, in the circuit court of Franklin County, to recover a judgment against the appellants Ursula Groff and Spencer Groff, (hereinafter referred to as Groff), and Louis B. Eckelkamp, Inc., a corporation, (hereinafter referred to as Eckelkamp), for the balance due respondent for the construction of a building located at the junction of highways 50, 66 and 100, to have the judgment' declared and adjudged to be a mechanic’s lien upon the building, improvements and the land, and to have the lien declared a priority over a deed of trust held by the Bank of Washington. J. D. Shepard, doing business as J. D. Shepard Eadio and Electrical Service, was a subcontractor who did the electrical installations. He was joined as a defendant and he filed a cross bill.

*835 The trial court- appointed Hon. Walter Wehrle as referee to try the issues except as to the issue of cancelling a lease on the property %hich was granted to Eckelkamp by Groff for a-term of years. As to that issue a separate trial and judgment were ordered. In the main, the court approved the referee’s report and rendered a judgment in favor of respondent and against Groff and Eckelkamp in the sum of $80,740.17, with-a lien against the property and leasehold described in respondent’s petition for $79,878.10. The lien was declared superior to the deed of trust held by the Bank of Washington- which secured a note executed by Groff for $30,000, -except for the sum of $8,000 that paid a prior deed of trust. Eckelkamp was given a judgment for $700 on his cross-claim against respondent: The Bank- of Washington was [827] given a judgment on its cross-claim against respondent in the sum of $55,265.21 and J. D. Shepard was given a judgment, against respondent in the sum of $2,027.26. These sums were to be paid out of respondent’s judgment, and a lien was rendered in favor of respondent and against Groff and Eckelkamp. Both have appealed. ■ . . -

There was formerly a building that was used as a restaurant and filling station on the tract of land -in question but it was destroyed by fire in February, 1948. On April 29,'1948, respondent , entered into a written contract with the appellants to erect a- new building on this site suitable for a restaurant and other related businesses. The contract provided that the building was-to be built in accordance, with plans which were to be drawn by George F. Hayden, architect.. -This contract also contained the following provisions:

“6. The Parties of the Second Part shall pay the -Party of the First Part for the performance of -the work-.under this agreement as follows: On the 8th and 23rd day of. each month the Party of the First Part shall prepare a. statement showing -the amount paid out by the Party of the First Part for all labor incorporated in the work hereunder during the preceding period, and within three (3) -days thereafter, the Parties of the Second Part .shall pay to the-Party of the First Part the amount of such statement,, plus an amount equal to eight per cent (8%) of the amount of stich statement to cover'social security costs, workmen’s compensation -and liability insurance incidental to the performance of the work under this agreement. -

“7. In addition to the aforementioned sum' so paid for labor and at the same time the Parties- of the Second Part shall pay to the Party of the First Part the amount of all statements-.-fór all materials and sub-contracts furnished .or ordered' by Party of the First Part; Parties of the Second Part or their agents or representatives, and on the- 8th and 23rd of each month -as aforesaid, the Party of the First Part shall add to the-statement submitted to the Parties of the Second Part the value- of all materials and sub-contracts incorporated -into the work during the preceding period and the Parties of the Second. Part shall *836 pay-to the Party of the First Part a sum of ten (10) per cent on the aggregate of the value of said material, labor and sub-contracts as a profit; and in addition thereto the Parties of the Second Part shall pay to the Party of the First Part the sum equal to four (4) per cent on the aggregate value of said labor and material and sub-contracts as an overhead expense.”

On the date the contract was executed, the respondent began the construction of the building. At that time there was in existence only a pencil sketch of the building and it was estimated that it would cost approximately $65,000. However, after the plans were drawn by architect Hayden it was estimated the building would cost between $160,000 and $180,000.

As the work progressed the respondent submitted its statements for the cost of labor and the value of the building materials and supplies, plus the percentages provided for in the construction contract to appellants twice a month. These statements were paid until October 8, 1948. At that time Oliver Taetz discussed the non-payment of the statements with the appellants and then learned that the Groffs were the owners in fee of the land, and that on April 8, 1948, they had leased this land to Eekelkamp. He then found out that there was a disagreement between Groff and Eekelkamp about the lease and for that reason respondent had not been paid. Taetz was requested to furnish him with a segregation statement of certain items of labor and materials used in the construction from the beginning of the work to that time. Eekelkamp agreed to pay $50 for this clerical work. About the same time, respondent was requested to show on the statements presented to appellants the items ordered by Eekelkamp and the items ordered by Groff. Apparently this was requested for the purpose of keeping an account between Eekelkamp and Groff. After this request, respondent’s statements [828] were all made out to the “New Diamonds Account.” If the items shown were ordered by Eekelkamp, his name was also shown on the statement. The statements that showed items not ordered by Eekelkamp bore the name of “New Diamonds Account” and the name of Groff. It was not explained to Taetz why appellants wanted the statements made out in this manner. Respondent borrowed approximately $55,000 from the Bank of Washington to complete the building.

Respondent sublet the brick work in connection with the construction of the new Diamonds building to Thomas R. Pratt, a brick contractor from Farmington, Missouri, and the electrical work to J. D. Shepard, doing business as J. D. Shepard Radio and Electrical Services.

To shorten the record before the referee, it was stipulated by the parties to this action that the items of this account about which Oliver Taetz testified would be considered as if he had testified that they were used in the 'Construction of the building, and the amount *837 charged would be treated as if he had testified that the' charge was reasonable. During the course of this opinion, we will observe this stipulation and will not state that there is evidence that the various materials and labor were used in the construction, and will assume that there is evidence that the charge was reasonable.

Other necessary facts will be stated in the course of the opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bates County Redi-Mix, Inc. v. Windler
162 S.W.3d 98 (Missouri Court of Appeals, 2005)
Classic Kitchens & Interiors v. Johnson
110 S.W.3d 412 (Missouri Court of Appeals, 2003)
Brownstein v. Rhomberg-Haglin & Associates, Inc.
824 S.W.2d 13 (Supreme Court of Missouri, 1992)
Glasco Electric Co. v. Best Electric Co.
751 S.W.2d 104 (Missouri Court of Appeals, 1988)
Bresnan v. Basic Electric Co.
721 S.W.2d 3 (Missouri Court of Appeals, 1986)
Waddington v. Wick
652 S.W.2d 147 (Missouri Court of Appeals, 1983)
Kranz v. Centropolis Crusher, Inc.
630 S.W.2d 140 (Missouri Court of Appeals, 1982)
S & R Builders & Suppliers, Inc. v. Marler
610 S.W.2d 690 (Missouri Court of Appeals, 1980)
Boyer Lumber, Inc. v. Blair
510 S.W.2d 738 (Missouri Court of Appeals, 1974)
Reed Schmidt & Associates, Inc. v. Carafiol Furniture Co.
469 S.W.2d 876 (Missouri Court of Appeals, 1971)
Negley B. Calvin, Inc. v. Cornet
427 S.W.2d 741 (Missouri Court of Appeals, 1968)
Boyd v. Margolin
421 S.W.2d 761 (Supreme Court of Missouri, 1967)
Cooper v. Norman
424 S.W.2d 347 (Missouri Court of Appeals, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
253 S.W.2d 824, 363 Mo. 825, 1953 Mo. LEXIS 522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oliver-l-taetz-inc-v-groff-mo-1953.