Bates County Redi-Mix, Inc. v. Windler

162 S.W.3d 98, 2005 Mo. App. LEXIS 296, 2005 WL 405846
CourtMissouri Court of Appeals
DecidedFebruary 22, 2005
DocketWD 63152
StatusPublished
Cited by2 cases

This text of 162 S.W.3d 98 (Bates County Redi-Mix, Inc. v. Windler) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates County Redi-Mix, Inc. v. Windler, 162 S.W.3d 98, 2005 Mo. App. LEXIS 296, 2005 WL 405846 (Mo. Ct. App. 2005).

Opinion

RONALD R. HOLLIGER, Judge.

Bates County Redi-Mix, Inc., (“Bates”) appeals from a judgment denying it a mechanic’s lien against property owned by Michelle Cole. It is undisputed that Bates furnished concrete to the subcontractor of a general contractor hired by Cole. The *100 concrete was improperly installed, rendering the entire foundation unusable and necessitating that it be completely .torn out and replaced. In a case of first impression, Bates asks, as an innocent material-man, to be awarded a lien for its material, even though the material it supplied was never incorporated into the final structure and added no value to the property. We hold that Bates was entitled to a mechanic’s lien upon Cole’s property and reverse and remand with directions that the trial court enter judgment in favor of Bates on its hen claim.

Facts And Procedural Background

Michelle Cole purchased land in Bates County upon which she intended to place a manufactured home. The manufactured home needed to be set upon a basement foundation, and she contracted with Loren Windier, as general contractor, to erect the foundation. Windier, in turn, engaged Mr. Beers 1 as a subcontractor to construct concrete forms and to pour the concrete for the project. Windier also contracted with Bates County Redi-Mix, who would supply the concrete for the basement foundation.

Bates delivered concrete to the construction site on November 15, 1999, and December 2, 1999. Shortly thereafter, it was discovered that the basement foundation was unsuitable for installation of the manufactured home. In places, the basement walls were out of plumb by several inches. In other places, the walls bowed significantly. The basement, as a whole, was also wider than much of the manufactured home. The construction methods introduced dry joints 2 that would be prone to water leakage. There were also parts of the foundation, such as frost footings, and adjacent structures, such as retaining walls, that were not poured at all. Thus, the work performed was both defective and incomplete.

There was no claim that any of these problems were due to the materials supplied by Bates or that those materials were in any way unsuitable. Instead, all of these deficiencies were due to errors made by Beers in setting up the concrete forms for the project and mistakes made by him during the pouring of the concrete into the forms.

Windier and Beers suggested possible ways of correcting the deficiencies in the work. However, Cole concluded that those suggestions would not resolve the problems in a satisfactory manner. Therefore, she instructed Windier to completely remove the foundation. The foundation was completely demolished and transported off Cole’s land. Cole later obtained the services of a different contractor who built a replacement foundation. Cole ultimately placed her manufactured home on the second foundation.

Cole did not pay Windier for either labor or materials for the work on the original foundation. Windier stopped payment on a check provided to Bates for the concrete it supplied and Bates’ services in pumping the concrete. The check, in the amount of $4,065.47, was returned unpaid. Windier subsequently paid Bates a portion of that amount as restitution arising out of criminal charges, leaving an unpaid balance due to Bates in the amount of $2,914.47 for its materials and services.

Bates timely provided Cole notice of its intent to seek a mechanic’s lien on the property for the unpaid balance. It filed *101 suit to perfect its lien on June 2, 2000. The matter proceeded to trial, and the trial court initially entered judgment in favor of Bates. Cole and her mortgagor subsequently filed a motion for new trial. Upon that motion, the trial court concluded that its original judgment was in error and set it aside.

The trial court’s final judgment, issued on July 24, 2003, found that Bates was not entitled to a mechanic’s lien against Cole’s property because the concrete it supplied was completely removed from the property and was not incorporated in any manner in the rebuilt foundation. Bates now appeals.

Discussion

Bates raises two points in the present appeal. In its first point, it argues that the trial court erred in denying its claim for a mechanic’s lien because its lien interest attached to the property at the time it provided materials that were used in the construction of the original basement and foundation on Cole’s property. In its second point, Bates contends that, even if it was not entitled to a mechanic’s lien against the finished structure on Cole’s property, given that none of the Bates-supplied concrete was used in its construction, the trial court erred by refusing to recognize that it had a valid lien against the land itself. We find Bates’ first point to be dispositive.

As a bench-tried case, our review of the trial court’s judgment is conducted under the Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976), standard of review. See Ken Cucchi Constr. Inc. v. O’Keefe, 973 S.W.2d 520, 523 (Mo.App.1998). In both points on appeal, Bates contends that the trial court misapplied the law in reaching its judgment. With regard to conclusions of law, we conduct our review independently and do not defer to the trial court. See Barry Serv. Agency Co. v. Manning, 891 S.W.2d 882, 887 (Mo.App.1995). Of course, determining the correct legal conclusion depends upon the operative facts before the court. In determining what the facts before the court were, we view the evidence in the light most favorable to the judgment, disregarding all contrary evidence. See Ken Cucchi Constr., 973 S.W.2d at 524.

Mechanic’s liens were unknown at common law and exist purely as a creature of statute. 3 Section 429.010 provides, in relevant part:

Any person who shall do or perform any work or labor upon, or furnish any material, fixtures, engine, boiler or machinery for any building, erection or improvements upon land, or for repairing the same, ... under or by virtue of any contract with the owner or proprietor thereof, or his agent, trustee, contractor or subcontractor, ... upon complying with the provisions of sections 429.010 to 429.340, shall have for his work or labor done, or materials, ... a lien upon such building, erection or improvements, and upon the land belonging to such owner or proprietor on which the same are situated, ... to secure the payment of such work or labor done, or materials ... furnished[.]

This section has remained substantially unchanged since 1855, save for amendments expanding the classes of claimants covered (such as nurserymen) or other minor, technical, changes. See Chap. 109 Section 1, RSMo 1855. 4 The mechanic’s *102

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
162 S.W.3d 98, 2005 Mo. App. LEXIS 296, 2005 WL 405846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-county-redi-mix-inc-v-windler-moctapp-2005.