Farmington Building Supply Co. v. L. D. Pyatt Construction Co.

627 S.W.2d 648, 1981 Mo. App. LEXIS 3264
CourtMissouri Court of Appeals
DecidedDecember 8, 1981
Docket42861
StatusPublished
Cited by12 cases

This text of 627 S.W.2d 648 (Farmington Building Supply Co. v. L. D. Pyatt Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmington Building Supply Co. v. L. D. Pyatt Construction Co., 627 S.W.2d 648, 1981 Mo. App. LEXIS 3264 (Mo. Ct. App. 1981).

Opinion

SMITH, Presiding Judge.

Defendants Dickerson appeal from the action of the trial court adjudging their residential property subject to a material-men’s lien in favor of plaintiff which supplied materials to the general contractor on credit for the construction of defendants’ home. 1

Defendants first contend that plaintiff failed to file a “just and true account” of the amount due as required by Sec. 429.080, RSMo 1978. This argument is based upon the fact that the account attached to the statement did not specifically identify items which were returned to plaintiff for credit. It is accepted that the lien law is remedial in nature and should be liberally construed. Roy F. Stamm Electric Co. v. Hamilton-Brown Shoe Co., 350 Mo. 1178, 171 S.W.2d 580 (banc 1943) [9]. Such liberal construction does not relieve a lien claimant from the necessity of reasonably and substantially complying with the statutory requirements. Putnam v. Heathman, 367 S.W.2d 823 (Mo.App.1963) [3-5]. Substantial compliance with the requirement to file a “just and true account” is a condition precedent to the right to establish a lien against the property. Putnam v. Heathman, supra, [6]. However, a lien statement may be regarded as “just and true” even if it includes non-lienable items if the inclusion is the result of honest inadvertence or oversight without intent to defraud and if the lienable and non-lienable items can be separated. Sears, Roebuck & Co. v. Seven Palms Motor Inn, 530 S.W.2d 695 (Mo. banc 1975) [6],

Here certain returned (and therefore non-lienable) items were listed in the account, but the total of the account reflects that, in fact, credit was given for the returned items. The account total does, therefore, accurately reflect the lienable charges. The trial court found that plaintiff had filed a “just and true” account of the indebtedness. Our review is that prescribed by Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976) [1 — 3]. The trial court’s finding could be based either upon a finding that failure to specifically delineate non-lienable items for credit was an unintentional inadvertence or upon a finding that the non-lienable items were not actually included in the account because not included in the total. 2 Either finding is supported by the evidence and we find no error. See, Sec. 429.210, RSMo 1978, A. E. Birk & Son Plumbing & Heating Inc. v. Malan Construction Co., 548 S.W.2d 611 (Mo.App.1977).

We arrive at the same conclusion in reference to one group of items included in the lien statement but found by the trial court not to have been incorporated into the house. The total of those items was less than $100 of the almost $11,000 claim. Additionally, the evidence did not unequivocal *651 ly establish that the items, which were delivered to the contractor and designated for defendants’ house, were not actually incorporated into defendants’ house. Their inclusion reflects at most an error or inadvertence of a minor nature made in good faith and insufficient to void plaintiff’s lien. Hydraulic-Press Brick Co. v. Green, 177 Mo.App. 308, 164 S.W. 250 (1914) [6]; Ulrich v. Osborn, 106 Mo.App. 492, 81 S.W. 228 (1904).

Defendants further contend that the evidence was insufficient to establish that the materials set forth in the lien statement were actually used or incorporated in the construction of defendants’ house. The thrust of the lien statute is to allow a lien for those materials which enter into the construction of the building and thereby become a part of its value. The lien claimant has the burden of establishing that the materials sold actually entered into the construction of the building. Tallman Co. v. Villmer, 133 S.W.2d 1085 (Mo.App.1939) [2], However, it is not required that the claimant prove that “every stick” was actually observed going into the structure. E. R. Darlington Lumber Co. v. Harris, 107 Mo. App. 148, 80 S.W. 688 (1904); Boyer Lumber, Inc. v. Blair, 510 S.W.2d 738 (Mo.App.1974) [6]; Kansas City Electrical Supply Company v. Bomar Electric Company, Inc., 581 S.W.2d 411 (Mo.App.1979) [3, 4],

Here the original contractor testified that many of plaintiff’s sales tickets for building materials designated for the Dickerson job site were signed by the contractor’s employees and that such signatures were a representation that the materials were either picked up by the employee or received at the job site. The contractor also testified that, based upon his knowledge of the work done, he was sure that everything shown on the sales tickets (except the items heretofore discussed) were used to construct the Dickerson house or should have been. The lien statement was based upon the sales tickets. Plaintiff’s manager testified that many of the items, particularly the large orders, were delivered to the job site. The contractor testified that all materials used in the house, except for a few small items, such as nails, were purchased from plaintiff. The evidence was sufficient to support the trial court’s finding that the materials were in fact used to construct defendants’ house.

Defendants also contend that the trial court erred in finding that plaintiff’s lien was timely filed. Under Sec. 429.080, plaintiff, which was not an original contractor, was required to file its lien statement “within four months, after the indebtedness shall have accrued.” There is no dispute that the four-month period is applicable. Plaintiff’s lien statement was filed on April 13, 1978. The last item on its account was allegedly supplied December 14, 1977. The statement was, on that basis, filed on the last day of the four-month period.

The trial court made a finding that the lien statement was filed “within six months of the provision of the last item in said account . . . . ” The court obviously utilized the wrong limitation period. Plaintiff introduced a sales ticket reflecting that it supplied a $7.59 sink rim on Dec. 14. Mrs. Dickerson testified that the sink, including rim, was complete on December 10, 1977. Plaintiff’s records indicated that a stainless steel sink as well as a center waste and S trap were returned for credit on Dec. 14. These items appear on a sales slip dated Dec. 8. Mrs. Dickerson testified that the stainless steel sink was at the house prior to Dec. 10, that she advised the workmen that it was not what she had ordered, and that the colored sink she had ordered was then installed with sink rim by Dec. 10. Plaintiff’s records do not indicate a colored sink was supplied, so it may be presumed that the sink installed came from somewhere else.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bates County Redi-Mix, Inc. v. Windler
162 S.W.3d 98 (Missouri Court of Appeals, 2005)
Channing v. Brindley-Sullivan, Inc.
855 S.W.2d 463 (Missouri Court of Appeals, 1993)
Lockett v. Musterman
854 S.W.2d 831 (Missouri Court of Appeals, 1993)
Westerhold v. Mullenix Corp.
777 S.W.2d 257 (Missouri Court of Appeals, 1989)
Garavaglia v. J.L. Mason of Missouri, Inc.
733 S.W.2d 53 (Missouri Court of Appeals, 1987)
Bresnan v. Basic Electric Co.
721 S.W.2d 3 (Missouri Court of Appeals, 1986)
Marriage of Katz v. Katz
708 S.W.2d 816 (Missouri Court of Appeals, 1986)
Twin Bridges Const. Co., Inc. v. Ferner
700 S.W.2d 534 (Missouri Court of Appeals, 1985)
Hartman Home Center, Inc. v. Bo Bri Do Homes, Inc.
652 S.W.2d 172 (Missouri Court of Appeals, 1983)
Mitchell Engineering Co. v. Summit Realty Co.
647 S.W.2d 130 (Missouri Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
627 S.W.2d 648, 1981 Mo. App. LEXIS 3264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmington-building-supply-co-v-l-d-pyatt-construction-co-moctapp-1981.