Fuhler v. Gohman & Levine Construction Co.

142 S.W.2d 482, 346 Mo. 588, 1940 Mo. LEXIS 436
CourtSupreme Court of Missouri
DecidedJuly 23, 1940
StatusPublished
Cited by23 cases

This text of 142 S.W.2d 482 (Fuhler v. Gohman & Levine Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fuhler v. Gohman & Levine Construction Co., 142 S.W.2d 482, 346 Mo. 588, 1940 Mo. LEXIS 436 (Mo. 1940).

Opinion

*594 DOUGLAS, J.

This is an equitable mechanics’ lien action brought under the statute (Sec. 3180, R. S. 1929, Ann. Stat., p. 5008) for the adjudication in one suit of the rights of all claimants against the premises at Gravois and Ellenwood Avenues in the City of St. - Louis known as the Granada Theatre and Apartment Building. Suit was filed by George J. Fuhler, a subcontractor, for material furnished and for work and labor done on the building. Defendant, Gohman & Levine Construction Company, was also a subcontractor. Other parties included Harry Waldron, doing business as Waldron Wrecking Company and Martin A. Federer, both subcontractors, who are also lien claimants and who are respondents here.

While the suit was pending the property was foreclosed and at the foreclosure sale on or about July 8, 1930, it was purchased by the Royal Neighbors of America, a corporation. Thereafter, on November 6, 1931, the Royal Neighbors on its application was made a party defendant. A referee was appointed on November 2, 1932, to try all the issues and commenced hearing evidence on January 11, 1933. He filed his report on December 1, 1936, recommending judgments for the lien claimants, and on December 20, 1937, the court confirmed the report of the -referee and entered judgment for $26,066.22 in favor of the plaintiff Fuhler; for $9,846.60 in favor of defendant Federer; for $1,570.80 in favor of defendant Waldron; such judgments to be secured by liens against the premises. Royal Neighbors, the owner of the premises^ has appealed.

The general contract for the building was between the then owner and R. Levine & Company. The Gohman & Levine Construction Company had the original contract for the masonry, cement and concrete work. The project seems to have been to a certain extent a family affair as R. Levine was the president of the company which owned the property. He was also president of R. Levine & Company, the general contractor. He was also president of the Gohman & Levine Construction Company. Gohman was vice-president of the latter company and *595 in active charge of the building construction. Plaintiff Fuhler was a subcontractor under the Gohman & Levine Construction Company for certain of the masonry and concrete work. The contract, in the sum of $91,292, incorporated by reference certain plans and specifications for the work “prepared by E. P. Rupert of Chicago, Ill., architect, and signed by him,” These plans and specifications were presented to the Building Commissioner of St. Louis at the time a building permit was applied for, but the permit was issued on the condition that they be revised. Immediately, the construction company was authorized to contract for extra work with subcontractors. ‘In a few months the building permit was revoked. In order to obtain a new one a number of changes were made in the work completed at that time and in the plans for the future work. There was testimony that the plans and specifications called for in the contract were not used and that the work proceeded on the orders of Gohman. Gohman’s authority is not questioned. These plans are not set out in the record before us. The plaintiff has treated the contract as abandoned and the referee has found this to be a fact from the evidence. The plaintiff fully completed his work and made demand for the balance due him which was refused.

This is not a case where the contractor has failed to complete his contract or has breached it and refused to fulfill it. The plaintiff has sued in quantum meruit for the reasonable value of his work and labor. Under the circumstances we do not know how 'else he might have brought his action.' The law is well established that where a contractor is prevented by the other party from fulfilling a building contract he may recover reasonable compensation for his work and labor regardless of the contract price. [Kelly v. Rowane, 33 Mo. App. 440; Dempsey v. Lawson, 76 Mo. App. 522; McCullough v. Baker, 47 Mo. 401; Ehrlich v. The Aetna Life Insurance Co., 88 Mo. 249.]

This rule is applicable in this ease. Here the contractor made no breach of his contract. He performed work demanded of him, different and beyond that contemplated in the old contract which, was abandoned, under a new implied contract. The fact that the plaintiff may have set up as a book-keeping item the amount specified in the original contract and then added the extras does not alter the true situation.

It follows that the plaintiff’s lien claim cannot be subject to the charge that it is not a “just and true” account required by the statute because it is in excess of the contract price of the abandoned contract. It was not only proper but it was necessary to itemize the account. [Schroeter Bros. Hdw. Co. v. Croatian “Sokol” Gymnastic Assn., 332 Mo. 440, 58 S. W. (2d) 995.] Similar charges against the lien filed by Federer may be disregarded for the same reasons.

Another charge against the account is based on the fact that in setting out the reasonable values of the items ten per cent for over *596 head and another ten per cent for profit were included over the actual cost. There was ample testimony, undisputed, that the various charges as claimed were proper and reasonable. The case relied on by appellant, Bradley Heating Co. v. Thomas M. Sayman, etc. . (Mo.), 201 S. W. 864, is not pertinent. In that case, Judge Graves purged from the judgment an allowance for the builders’ profit. The evidence did not show that the profit was reasonable. However in a later case, Johnston v. Star Bucket Pump Co., 274 Mo. 414, 202 S. W. 1143, Judge Graves said he had not decided in the Bradley Heating Co. case, the’question of the true rule on the measure of recovery where the owner had breached the contract. In the Johnston case it was shown that the prices charged were reasonable but in excess of the actual cost to the contractor. On this subject Judge Graves said: “In the instant case the plaintiff by plain proof showed the reasonable value of the materials and labor furnished. That this value so shown was greater than plaintiff paid his subcontractors does not .change the situation. Plaintiff ivas entitled, in this action in quantum meruit, to the benefits of his bargain. He is only required to show the reasonable value, as such is shown in any other action in quantum meruit. He is not precluded by what he pays for material and labor. . . . Proof of what he paid is of course admissible on the question of reasonable value, but is not conclusive thereof.” While neither the opinion in the above case nor that in the Bradley Heating Co. case received a carrying vote except in the result we hereby approve and adopt what has just been quoted. Kansas City Structural Steel Co. v. Athletic Building Assn., 297 Mo. 615, 249 S. W. 922, is not in point because there an item of profit was claimed in addition to the reasonable value of the amount charged. In holding that such item could not be recovered in a quantum meruit action the decision relied on the Bradley Heating Co. ease.

Where the contractor has been free from fault he should not be penalized so long as he can prove that a charge including a profit is reasonable. This must have been considered when the rule of the measure of damages was stated in Kelly v. Rowane, 33 Mo. App. 440, supra, relied on by Judge Graves.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WEST CENTRAL CONCRETE, LLC v. Reeves
310 S.W.3d 778 (Missouri Court of Appeals, 2010)
Dave Kolb Grading, Inc. v. Lieberman Corp.
837 S.W.2d 924 (Missouri Court of Appeals, 1992)
Kranz v. Centropolis Crusher, Inc.
630 S.W.2d 140 (Missouri Court of Appeals, 1982)
S & R Builders & Suppliers, Inc. v. Marler
610 S.W.2d 690 (Missouri Court of Appeals, 1980)
Vonder Haar Concrete Co. v. Edwards-Parker, Inc.
561 S.W.2d 134 (Missouri Court of Appeals, 1978)
Peerless Supply Co. v. Industrial Plumbing & Heating Co.
460 S.W.2d 651 (Supreme Court of Missouri, 1970)
Woodley v. Esslinger
458 S.W.2d 869 (Missouri Court of Appeals, 1970)
Isaac v. Koenig
447 S.W.2d 818 (Missouri Court of Appeals, 1969)
H. B. Deal Construction Co. v. Labor Discount Center, Inc.
418 S.W.2d 940 (Supreme Court of Missouri, 1967)
Henges Co. v. Doctors' North-Roads Building, Inc.
409 S.W.2d 489 (Missouri Court of Appeals, 1966)
Schreck v. Parker
388 S.W.2d 538 (Missouri Court of Appeals, 1965)
K-V Builders, Inc. v. Thomas
353 S.W.2d 130 (Missouri Court of Appeals, 1962)
Schwartz v. Shelby Construction Company
338 S.W.2d 781 (Supreme Court of Missouri, 1960)
Wilson v. Berning
293 S.W.2d 151 (Missouri Court of Appeals, 1956)
Hertel Electric Company v. Gabriel
292 S.W.2d 95 (Missouri Court of Appeals, 1956)
Surf Properties v. Markowitz Bros.
75 So. 2d 298 (Supreme Court of Florida, 1954)
Bailey v. Interstate Airmotive, Inc.
219 S.W.2d 333 (Supreme Court of Missouri, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
142 S.W.2d 482, 346 Mo. 588, 1940 Mo. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fuhler-v-gohman-levine-construction-co-mo-1940.