Killian Construction Co. v. Tri-City Construction Co.

693 S.W.2d 819, 1985 Mo. App. LEXIS 3353
CourtMissouri Court of Appeals
DecidedMay 14, 1985
DocketWD 35032
StatusPublished
Cited by24 cases

This text of 693 S.W.2d 819 (Killian Construction Co. v. Tri-City Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Killian Construction Co. v. Tri-City Construction Co., 693 S.W.2d 819, 1985 Mo. App. LEXIS 3353 (Mo. Ct. App. 1985).

Opinion

SHANGLER, Judge.

The plaintiff Killian Construction Company subcontracted with the defendant TriCity Construction Company to complete certain portions of the work Tri-City, as general construction contractor, agreed to perform for the United States Army Corps of Engineers. The suit by Killian against Tri-City pleaded four causes of action: Count I, for the balance owed under the contract; Count II, for the reasonable value of extra work done and accepted; Count III, for reimbursement for the cost of money borrowed to complete the subcontract project; Count IV, for punitive damages for the tortious breach of the subcontract. The defendant Tri-City counterclaims for breach of contract.

The court submitted Counts I, II, and III to the jury, and directed a verdict against Killian on Count IV. The jury found for plaintiff Killian on Count I [$54,000], found for defendant Tri-City on Count II, and found for plaintiff Killian on Count III [$35,000]. The jury found for the plaintiff Killian on the defendant Tri-City counterclaim. The appeal is by Tri-City from the judgments entered in favor of Killian on Counts I and III.

The construction of the Truman Dam in Henry County made necessary the relocation of roads in the vicinity, now threatened with inundation. On June 23, 1977, TriCity Construction Company undertook the relocation project as general construction contractor for the United States Army Corps of Engineers. The weather was inclement that first year, and Tri-City did not accomplish much under the general contract. Tri-City then determined to subcontract a portion of the relocation project, and on June 7, 1978, contracted with B & K Excavation for that purpose. B & K was a partnership of the Bam Construction Company and the Killian Construction Company. On August 17, 1978, the amount of work was modified by a supplemental agreement. The work did not progress well, due in measure to the lack of skill of the subcontract project overseer, Butts [president of Bam Construction Company, a B & K partner], some laggardly preparatory performance by Tri-City, and other reasons. The partnership was terminated on December 15, 1978, and Butts assigned the subcontract interest to Killian — and Tri-City acceded. Killian then engaged one Carr, an engineer, to supervise the remainder of the relocation project. On August 2, 1979, the original subcontract was once again modified by another supplemental agreement. The amount of work to be done was again redefined, and the completion date was extended to October 14,1979. The work was actually completed in December of 1979, and was given final approval, in quadrants, by the Corps of Engineers in April of 1980.

The subcontract between Tri-City and Killian [as does the general contract between the Army Corps of Engineers and *823 Tri-City 1 ] defines performance in terms of unit quantity and payment in terms of unit price. Section 2 of the subcontract describes the scope of the work Killian undertakes to perform:

Estimated Description of Work Quantity Unit Unit Price Amount
Common Excavation 82,015 CY 0.75 $ 61,511.25
Rock Excavation 36,280 CY 3.00 108,840.00
Embankment 236,590 CY 0.95 224,760.50
Aggregate Surfacing 16,001.7 Ton 4.50 72,007.65
Seeding & Mulching 100 Acres 400.00 40,000.00
$507,119.40

Thus, the subcontract terms render the amount as an estimated sum: that is, a calculation based on a projected quantity of work to be furnished at a fixed unit price. The subcontract provided for partial payment to Killian by the month during the work progress, computed on the basis of the engineer estimate of the work quantity performed, but the final payment was due according to the work units actually “completed by the subcontractor based on the engineer’s completed unit quantities” and subject to the final approval and acceptance of the subcontractor work by the Corps of Engineers [Subcontract, § 3 Payment(&) ]. The relocation project was completed by Killian in December of 1979. The subcontractor submitted the pay estimate of $27,187.39 for work done that December, but Tri-City never remitted. 2 That default [according to Killian] left him without the means to pay suppliers and other creditors. In May of 1980, Tri-City agreed to release sufficient funds to pay sixty percent of the amounts of the debts [except for the claim of International Harvester, still in litigation, for the cost of certain leases of construction equipment]. Killian then negotiated a bank loan and paid the balances owed on the debts. The International Harvester suit was settled by payment from Tri-City [the named defendant] of $12,000. Killian was still without final payment from Tri-City at the time of suit.

The performance assumed by Killian under the subcontract was to complete a project already begun by Tri-City under the original general contract with the Corps of Engineers. A term of the subcontract [§ 25.1] recites:

Tri-City Corporation has been paid for the following quantities of work as listed below:
Common Excavation 45,265 CY
Rock Excavation 0
Embankment 38,090 CY
Aggregate Surfacing 498.3 Tons
[emphasis added]

The relocation project was completed by Killian in December of 1979. The Corps of Engineers then computed the earthwork by survey, and verified the quantities [among the others] for final payment to Tri-City as:

*824 Description Unit Final Quantity Amount
Common Excavation CY 153,382 $122,705.60
Rock Excavation CY 23,150 85,655.00
Embankment CY 262,110 327,637.50
Aggregate Surfacing CY 16,500 82,500.00

This determination of final payment quantities was transmitted to the general contractor Tri-City by the Corps of Engineers on April 22, 1980, although full payment was not remitted until May of 1981. Tri-City made no further payment to Killian, however, other than as partial liquidation of the supplier accounts and to discharge the International Harvester claim against Killian.

The Tri-City records reflect that, after payment of $42,184.51 on the supplier accounts and to discharge the International Harvester litigation, a balance of $40,-366.12 remained owed to Killian on the completed subcontract. 3 To compute that balance, Tri-City subtracted from the final quantity determined by the Corps of Engineers as actually 'performed as to each work item [i.e., common excavation, rock excavation, etc.] the estimated quantity

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charlotte Jean Kerr v. The Curators of the University of Missouri
512 S.W.3d 798 (Missouri Court of Appeals, 2016)
Kozeny Wagner, Inc. v. Simplex Grinnell, Lp
330 S.W.3d 507 (Missouri Court of Appeals, 2010)
Ray Klein, Inc. v. Kerr
272 S.W.3d 896 (Missouri Court of Appeals, 2008)
Duvall v. Maxey
249 S.W.3d 216 (Missouri Court of Appeals, 2008)
Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc.
171 S.W.3d 81 (Missouri Court of Appeals, 2005)
Felton v. Hulser
957 S.W.2d 394 (Missouri Court of Appeals, 1997)
State v. Sutherland
939 S.W.2d 373 (Supreme Court of Missouri, 1997)
Bolivar Insulation Co. v. R. Logsdon Builders, Inc.
929 S.W.2d 232 (Missouri Court of Appeals, 1996)
Rhodes v. Blair
919 S.W.2d 561 (Missouri Court of Appeals, 1996)
Lindsey Masonry Co. v. Jenkins & Associates Inc.
897 S.W.2d 6 (Missouri Court of Appeals, 1995)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
Dana Commercial Credit Corp. v. Cukjati
880 S.W.2d 612 (Missouri Court of Appeals, 1994)
Wulfing v. Kansas City Southern Industries, Inc.
842 S.W.2d 133 (Missouri Court of Appeals, 1992)
Ahrens & McCarron, Inc. v. Mullenix Corp.
793 S.W.2d 534 (Missouri Court of Appeals, 1990)
Renick v. City of Maryland Heights
767 S.W.2d 339 (Missouri Court of Appeals, 1989)
St. Louis County v. Missouri State Employees' Retirement System
765 S.W.2d 357 (Missouri Court of Appeals, 1989)
Gasser v. John Knox Village
761 S.W.2d 728 (Missouri Court of Appeals, 1988)
Albers v. Hemphill Contracting Co.
740 S.W.2d 660 (Missouri Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
693 S.W.2d 819, 1985 Mo. App. LEXIS 3353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/killian-construction-co-v-tri-city-construction-co-moctapp-1985.