Kozeny Wagner, Inc. v. Simplex Grinnell, Lp

330 S.W.3d 507, 2010 WL 3551401
CourtMissouri Court of Appeals
DecidedSeptember 14, 2010
DocketED 94157
StatusPublished

This text of 330 S.W.3d 507 (Kozeny Wagner, Inc. v. Simplex Grinnell, Lp) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kozeny Wagner, Inc. v. Simplex Grinnell, Lp, 330 S.W.3d 507, 2010 WL 3551401 (Mo. Ct. App. 2010).

Opinion

CLIFFORD H. AHRENS, Judge.

Kozeny Wagner appeals the circuit court’s summary judgment denying prejudgment interest on Kozeny’s damages for breach of contract by Simplex Grinnell. We affirm.

Background

Kozeny and Simplex were parties to a construction subcontract agreement pursuant to which Simplex, as subcontractor, was to install a fire protection system for Kozeny, as general contractor, on a construction project involving a residential hall at the University of Missouri-St. Louis (UMSL). Within a year after Simplex installed the sprinkler pipes, multiple leaks caused extensive damage to the building. An inspection revealed that Simplex had used a solvent that caused the pipes to weaken, crack, and eventually rupture. Kozeny incurred $724,066.12 in repairs to the building and reparations to UMSL. 1 This amount does not include the costs of replacing the fire protection system furnished pursuant to the subcontract agreement.

Kozeny filed suit alleging that Simplex had breached the parties’ subcontract agreement by performing its work in a defective manner. The parties entered into a settlement agreement pursuant to which Simplex agreed to pay Kozeny’s actual damages ($724,066.12) minus an out *509 standing receivable owed to Simplex ($46,-696.53) for a total of $677,372.59. The parties did not resolve, however, the matter of whether prejudgment interest was recoverable on that amount pursuant to section 408.020 RSMo. Kozeny asserted its claim for prejudgment interest before the trial court, and Simplex moved for partial summary judgment seeking to preclude it. The trial court granted Simplex’s motion without comment, and this appeal followed.

Standard of Review

Appellate review of summary judgment is de novo, viewing the record in the light most favorable to the party against whom judgment was entered. ITT Commercial Fin. Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376 (Mo.1993).

Discussion

“Prejudgment interest serves at least two purposes: (1) it helps compensate plaintiffs for the true cost of money damages they have incurred, and (2) where liability and the amount of damages are fairly certain, it promotes settlement and deters an attempt to benefit unfairly from the inherent delays of litigation.” Twin River Const. Co., Inc. v. Public Water Dist. No. 6, 653 S.W.2d 682, 695 (Mo.App.1983). Section 408.020 allows creditors to recover interest at a rate of nine percent “when no other rate is agreed upon, for all moneys after they become due and payable, on written contracts, and on accounts after they become due and demand of payment is made.” A party is entitled to prejudgment interest on damages for breach of contract if the amount is liquidated or readily ascertainable by reference to recognized standards. Midwest Asbestos Abatement Corp. v. Brooks, 90 S.W.3d 480, 486 (Mo.App. E.D.2002). This rule is grounded on the premise that, if the person liable does not know the amount he owes, he should not be considered in default because of his failure to pay. Hernandez v. Westoak Realty & Inv., Inc., 771 S.W.2d 876, 882 (Mo.App.1989). “The award of prejudgment interest in a case in which section 408.020 is applicable is not a matter of court discretion.” Baris v. Layton, 43 S.W.3d 390, 398 (Mo.App.2001). “When the damages for a claim of breach of contract are fixed or readily ascertainable and a sufficient demand is made, Missouri law compels the award of prejudgment interest.” Trinity Products, Inc. v. Burgess Steel L.L.C., 486 F.3d 325, 335 (8th Cir.2007).

Kozeny asserts that the trial court erred in denying its claim for prejudgment interest because it met the statutory requirements in that: its claim was based on a written contract where no other rate was agreed upon; the amount of damages was liquidated; and the amount became due and payable when Kozeny demanded payment. 2 Simplex concedes that the amount is liquidated and demand for payment was made but denies that the amount is “due and payable on” the parties’ subcontract agreement.

In essence, the parties dispute the meaning of the word “on” in the statutory language “on written contracts.” Kozeny interprets “on” to mean “resulting from” the parties’ agreement, while Simplex interprets “on” to mean “pursuant to” the document. Our research compels the conclusion that Simplex states the traditional view. Restatement 2nd Contracts § 354 explains the general principle:

*510 Interest is recoverable for the non-payment of money once payment has become due and there has been a breach. This rule applies to debts due for money lent, goods sold or services performed, including installments due on a construction contract. The sum due is sufficiently definite if it is ascertainable from the terms of the contract, as where the contract fixes a price per unit of performance, even though the number of units performed must be proved and is subject to dispute. The same is true, even if the contract does not of itself create a money debt, if it fixes a money equivalent of the performance. It is also true, even if the contract does not fix a money equivalent of the performance, if such an equivalent can be determined from established market prices.

In the building construction context, a claim for prejudgment interest typically accompanies a contractor’s demand for payment for work performed, and the availability of interest hinges primarily on whether the amount owed was liquidated and occasionally on whether or when sufficient demand for payment was made. 3 Nationwide, a voluminous body of law illustrates this scenario, and Missouri cases are in accord. For example, in Burger v. Wood, 446 S.W.2d 436 (Mo.App.1969), a contractor was entitled to prejudgment interest on amounts due for work it performed for homeowners. In Jerry Bennett Masonry v. Crossland Const., 171 S.W.3d 81 (Mo.App.2005), a subcontractor was entitled to prejudgment interest on amounts due for work it performed for the general contractor. In Bolivar Insulation Co. v. R. Logsdon Builders, Inc., 929 S.W.2d 232 (Mo.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baris v. Layton
43 S.W.3d 390 (Missouri Court of Appeals, 2001)
Midwest Asbestos Abatement Corp. v. Brooks
90 S.W.3d 480 (Missouri Court of Appeals, 2002)
Hernandez v. Westoak Realty & Investment, Inc.
771 S.W.2d 876 (Missouri Court of Appeals, 1989)
Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc.
171 S.W.3d 81 (Missouri Court of Appeals, 2005)
Bolivar Insulation Co. v. R. Logsdon Builders, Inc.
929 S.W.2d 232 (Missouri Court of Appeals, 1996)
Iota Management Corp. v. Boulevard Investment Co.
731 S.W.2d 399 (Missouri Court of Appeals, 1987)
Children International v. Ammon Painting Co.
215 S.W.3d 194 (Missouri Court of Appeals, 2006)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Burger v. Wood
446 S.W.2d 436 (Missouri Court of Appeals, 1969)
Denton Construction Co. v. Missouri State Highway Commission
454 S.W.2d 44 (Supreme Court of Missouri, 1970)
A.G. Edwards & Sons, Inc. v. Drew
978 S.W.2d 386 (Missouri Court of Appeals, 1998)
Killian Construction Co. v. Tri-City Construction Co.
693 S.W.2d 819 (Missouri Court of Appeals, 1985)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
Watters v. Travel Guard International
136 S.W.3d 100 (Missouri Court of Appeals, 2004)
St. John's Bank & Trust Co. v. Intag, Inc.
938 S.W.2d 627 (Missouri Court of Appeals, 1997)
Ken Cucchi Construction, Inc. v. O'Keefe
973 S.W.2d 520 (Missouri Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
330 S.W.3d 507, 2010 WL 3551401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kozeny-wagner-inc-v-simplex-grinnell-lp-moctapp-2010.