Midwest Asbestos Abatement Corp. v. Brooks

90 S.W.3d 480, 2002 Mo. App. LEXIS 2142, 2002 WL 31415971
CourtMissouri Court of Appeals
DecidedOctober 29, 2002
DocketED 80158
StatusPublished
Cited by7 cases

This text of 90 S.W.3d 480 (Midwest Asbestos Abatement Corp. v. Brooks) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Asbestos Abatement Corp. v. Brooks, 90 S.W.3d 480, 2002 Mo. App. LEXIS 2142, 2002 WL 31415971 (Mo. Ct. App. 2002).

Opinion

PAUL J. SIMON, P.J.

Sonya Rae Brooks, d/b/a D & S Wrecking and D & S Hauling, Excavating and Demolition (D & S) appeals the trial court’s judgment awarding attorney’s fees and pre-judgment interest in favor of Mid *482 west Asbestos Abatement Corporation (Midwest).

D & S entered into a contract with the State of Missouri Highway and Transportation Commission (Commission) to demolish several homes in St. Louis, St. Charles, Jefferson and Franklin counties as part of the Highway 141 extension project. Pursuant to this contract D & S furnished a labor and material bond provided by Cumberland Casualty Insurance Company (Surety) in the amount of $750,918.25.

As part of the contract D & S agreed to remove or abate asbestos found in the homes. D & S sought to subcontract the asbestos removal, and entered into a written contract with Midwest wherein Midwest agreed to provide the necessary labor, equipment and materials for removal of 7,200 square feet of friable asbestos-containing material, and 36,000 square feet and 25 linear feet of Category 2 non-friable asbestos-containing material. The contract did not provide for the removal of any Category 1 non-friable asbestos-containing floor tile or mastic.

The contract provided that D & S would bear responsibility for additional compensation to Midwest in accordance with Midwest’s normal fee schedule if the actual conditions or extent of asbestos removal differed from those initially anticipated by the parties. The contract also provided for a 1.5% per month interest charge on past due accounts. Paragraph ten of the agreement provided that “[D & S] agrees to pay all of [Midwest]’s attorney’s fees, expenses, litigation costs and [Midwestj’s staff time; provided [Midwest] prevails to any extent by settlement or otherwise”.

Before construction began the parties discovered the project would require removal of non-friable Category 1 asbestos-containing floor tile and mastic that had not been specifically provided for in the contract. Todd Strong, a duly authorized agent of the Commission, instructed D & S to remove the floor tile and mastic. On this basis D & S orally agreed they would pay Midwest to remove the materials. Tim Rabbitt, Midwest’s vice-president of operations, reduced the terms of the oral contract to writing and signed the document on Midwest’s behalf. Rabbitt gave the contract to D & S, but D & S did not sign the contract. Acting on D & S’s oral assertions, Midwest commenced removal and submitted separate invoices to D & S for the Category 1 removal. D & S in turn submitted the invoices to the Commission. The Commission denied payment of the invoices. The Commission took the position that the payments it had already tendered to D & S pursuant to the general contract provided for the possibility of expenses incurred in connection with Category 1 removal. D & S refused to pay the invoices themselves. Consequently, Midwest ceased all Category 1 removal operations under the oral agreement. To that point Midwest rendered services in the amount of $29,301.52 removing the Category 1 asbestos according to the invoices submitted to D & S.

Midwest filed a five-count petition alleging breach of the oral contract (Count I), an amount due on the account (Count II), recovery in quantum meriut (Count III), and breach of the original written contract resulting in loss of profits and seeking an award of pre-judgment interest and attorney’s fees (Count IV). In the fifth and final count Midwest claimed the Surety was hable for contribution under the bond paid by D & S. Midwest also sought attorney’s fees and pre-judgment interest on all outstanding sums. Except in Count IV, Midwest contended the Public Prompt Pay Act, Section 34.057 RSMo 1999 (all further references hereinafter shall be referred to as RSMo 1999 unless otherwise indicated), authorized an award of attorney’s fees and *483 pre-judgment interest. Sitting without a jury, the trial court found in favor of Midwest on Counts I, II and III, but found in favor of D & S on Count IV. The trial court awarded Midwest $29,301.52 in damages plus $15,818.00 in pre-judgment interest calculated at a rate of 1.5% from the dates of the invoices and $14,805.00 in attorney’s fees. According to the trial court, the agreement and Section 431.180 formed the basis for the award of interest and attorney’s fees. Finally, as to Count V the trial court found the Surety liable under the bond for “the same” damages, interest and attorney’s fees entered against D & S. D & S’s appeal concerns only the pre-judgment interest and attorney’s fees portion of the trial court’s judgment.

We will affirm the judgment of the trial court unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc.1976). We view the evidence in the light most favorable to the judgment. Id. We must defer to the trial court on factual issues and cannot substitute our judgment for that of the trial judge. H.S. v. Board of Regents, Southeast Missouri State University, 967 S.W.2d 665, 671 (Mo.App. E.D.1998). However, we independently evaluate the trial court’s conclusions of law. St. Louis County v. B.A.P., 18 S.W.3d 397, 404 (Mo.App. E.D.2000).

In its first point on appeal D & S argues the trial court lacked the statutory and contractual authority to award attorney’s fees and pre-judgment interest pursuant to Midwest’s breach of written and oral contract claims (Counts I & IV). D <& S in effect adduces a three-part argument to support this point. First, D & S correctly points out that since the Commission hired D & S the work performed amounted to a public works project governed by the Public Prompt Pay Act, Section 34.057. In spite of the public nature of the project, however, the trial judge erroneously relied on the Private Prompt Pay Act, Section 431.180, as the statutory authority for the award of pre-judgment interest and attorney’s fees. Accordingly, D & S maintains the trial court used an improper basis to make the award. Second, D & S argues that, even assuming the trial judge had relied on the Public Prompt Pay Act, the statute does not permit an award of pre-judgment interest in a breach of contract action absent a showing of bad faith on the part of the general contractor. Finally, D & S argues that the trial court could not have relied on the contract itself as a basis for awarding pre-judgment interest and attorney’s fees because Midwest requested interest and fees pursuant to the contract only in its loss of profits claim with respect to which the trial court found against Midwest and in favor of D & S.

We first address the trial court’s erroneous citation to the Private Prompt Pay Act. We agree with Midwest that the mistaken citation should be ignored so as to address the substantive merits of the trial court’s decision to award pre-judgment interest and attorney’s fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyington v. Bryan
174 So. 3d 347 (Court of Civil Appeals of Alabama, 2014)
Kozeny Wagner, Inc. v. Simplex Grinnell, Lp
330 S.W.3d 507 (Missouri Court of Appeals, 2010)
Tolar Constr., LLC v. Kean Elec. Co., Inc.
944 So. 2d 138 (Supreme Court of Alabama, 2006)
State ex rel. Nixon v. Koonce
173 S.W.3d 277 (Missouri Court of Appeals, 2005)
City of Sullivan v. Truckstop Restaurants, Inc.
142 S.W.3d 181 (Missouri Court of Appeals, 2004)
Leo Journagan Construction Co. v. City Utilities of Springfield
116 S.W.3d 711 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
90 S.W.3d 480, 2002 Mo. App. LEXIS 2142, 2002 WL 31415971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-asbestos-abatement-corp-v-brooks-moctapp-2002.