Tolar Constr., LLC v. Kean Elec. Co., Inc.

944 So. 2d 138, 2006 WL 1361127
CourtSupreme Court of Alabama
DecidedMay 19, 2006
Docket1041448 and 1041510
StatusPublished
Cited by23 cases

This text of 944 So. 2d 138 (Tolar Constr., LLC v. Kean Elec. Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tolar Constr., LLC v. Kean Elec. Co., Inc., 944 So. 2d 138, 2006 WL 1361127 (Ala. 2006).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 140

Tolar Construction, LLC ("Tolar"), appeals from an order of the DeKalb Circuit Court denying its motion for a new trial and granting the motion of Kean Electric Company, Inc. ("Kean"), for an award of attorney fees, interest, and other costs. Kean cross-appeals from the aspect of that order setting the date on which interest began to accrue. We affirm the trial court's judgment.

Facts and Procedural History
Tolar is a general contracting company primarily specializing in the construction of large buildings such as school buildings. In March 2000, Tolar submitted a bid to, and secured a general contract from, the Fort Payne Board of Education for an *Page 141 expansion of Wills Valley Elementary School, located in Fort Payne.

In the course of determining the amount of bid to submit, Tolar sought bids from numerous subcontractors for performance of various components of the expansion project. Kean was the winning subcontractor for electrical services, and it and Tolar entered into an electrical-subcontract agreement ("the subcontract"), which provided that Tolar would pay Kean a specified sum for its services upon completion and acceptance of the electrical work.1 The date specified in the subcontract for Kean's completion of the electrical work was January 18, 2001.

In June 2000, Tolar began work on the expansion project; Kean began work as scheduled in August. The project proceeded smoothly until November, when the Board of Education informed Tolar that the roof for which materials had been ordered and on which work had already begun was not the roof the Board of Education intended for the school. More than a month elapsed before the roof situation was resolved, during which much of the scheduled electrical work was delayed. During this period, Kean found it necessary to withhold its normal complement of workers from the site; it sent just a few individuals each day to complete what little work could be accomplished pending resolution of the roof problem.

Tolar had to remove the roof it had already constructed and begin construction of a second roof. Weather conditions delayed this work until January 3, 2001, when Tolar was finally able to begin removing the roof underlayment. Within a few weeks, the roof was essentially completely replaced, and Kean began devoting more manpower to the electrical work. The roof delay, however, rendered impossible Kean's completion of its work by January 18, 2001.

Although Tolar understandably did not find fault with Kean for not having completed its work by January 18, the project manager for Tolar eventually began to voice some frustration with Kean's allegedly slow completion time. Correspondence increased between Lyle Kean, president of Kean, and representatives of Tolar, as each company began to complain about the deficient nature of the other's work. On April 27, 2001, Tolar's project superintendent hand-delivered a letter to Lyle Kean informing him that Kean needed to complete its work by the afternoon of May 3. On May 14, the project superintendent hand-delivered to Lyle Kean another letter, dated May 12; although that letter is not contained in the record, it has been represented to have essentially ordered Kean "to get off [the] job and do not come back." After completing some minor remedial measures, Kean complied with this order. Other than $3,000 paid to Kean by Tolar at an indeterminate point during the project, Tolar never paid Kean for its work.

On January 7, 2003, Kean sued Tolar in the DeKalb Circuit Court, alleging breach of contract and fraud. Tolar filed an answer generally denying the allegations and filed a counterclaim alleging that Kean had breached the subcontract. Tolar's counterclaim sought, among other relief, attorney fees pursuant to a provision in the subcontract. Kean answered Tolar's counterclaim by general denial and amended its own complaint to add a count seeking "interest costs, attorneys fees and reasonable expenses" under Ala. Code 1975, § 8-29-1 *Page 142 et seq., officially designated the Deborah K. Miller Act by the Alabama Legislature ("the Miller Act"). Tolar answered this amendment by a general denial. Because the meaning and interaction of certain provisions of the Miller Act are at the heart of most of the issues contested on appeal, we set those provisions out at this point:

Section 8-29-3(d), Ala. Code 1975, provides:

"If the owner, contractor, or subcontractor does not make payment in compliance with this chapter [`Chapter 29. Timely Payments to Contractors and Subcontractors'], the owner, contractor, or subcontractor shall be obligated to pay his or her contractor, subcontractor, or sub-subcontractor interest at the rate of one percent per month (12% per annum) on the unpaid balance due."

Section 8-29-4 provides, in part:

"(a) Nothing in this chapter shall prevent the owner, contractor, or subcontractor from withholding application and certification for payment for any of the following reasons if there is a bona fide dispute over one or more of the following:

"(1) Unsatisfactory job progress.

"(2) Defective construction not remedied.

"(3) Disputed work.

"(4) Third party claims filed or reasonable evidence that a claim will be filed.

"(5) Failure of the contractor, subcontractor, or sub-subcontractor to make timely payments for labor, equipment, and materials.

"(6) Property damage to owner, contractor, or subcontractor.

"(7) Reasonable evidence that the contract, subcontract, or sub-subcontract cannot be completed for the un-paid balance of the contract or contract sum.

"(b) In the event that there is a bona fide dispute over all or any portion of the amount due on a progress payment from the owner, contractor, or subcontractor then the owner, contractor, or subcontractor may withhold payment in an amount not to exceed 2 times the disputed amount."

Section 8-29-6 provides:

"A contractor, subcontractor, or sub-subcontractor may file a civil action solely against the party contractually obligated for the payment of the amount claimed to recover the amount due plus the interest accrued in accordance with this chapter. If the court finds in the civil action that the owner, contractor, or subcontractor has not made payment in compliance with this chapter, the court shall award the interest specified in this chapter in addition to the amount due. In any such civil action, the party in whose favor a judgement is rendered shall be entitled to recover payment of reasonable attorneys' fees, court costs and reasonable expenses from the other party."

The case went to trial before a jury on March 7, 2005. At the close of Kean's case-in-chief, the trial court granted Tolar's motion for a judgment as a matter of law as to Kean's fraud claim.

Midday on March 9, the court and counsel agreed that Kean's claims pursuant to § 8-29-6, for attorney fees, interest, and expenses, and Tolar's claim for attorney fees, sought pursuant to a provision therefor in the subcontract, would be determined by the court, and the jury would be so advised. On March 10, immediately after the lunch recess and immediately preceding the time appointed for closing arguments, counsel renewed discussions with the court concerning how attorney *Page 143

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyington v. Bryan
174 So. 3d 347 (Court of Civil Appeals of Alabama, 2014)
Baker v. Miller
143 So. 3d 754 (Supreme Court of Alabama, 2013)
Diamond Conc. Slabs v. Andalusia-Opp, 2100114 (ala.civ.app. 8-12-2011)
103 So. 3d 73 (Court of Civil Appeals of Alabama, 2011)
Leroy Bandy and David Russell v. City of Birmingham.
73 So. 3d 1233 (Supreme Court of Alabama, 2011)
Jefferson County v. Suzanne Birchfield.
142 So. 3d 556 (Court of Civil Appeals of Alabama, 2011)
O'Rear v. B.H.
69 So. 3d 106 (Supreme Court of Alabama, 2011)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)
Wehle v. Bradley
49 So. 3d 1203 (Supreme Court of Alabama, 2010)
Edwards v. Kia Motors of America, Inc.
8 So. 3d 277 (Supreme Court of Alabama, 2008)
Exxon Mobil Corp. v. ALA. DEPT. OF CONSERVATION AND NATURAL RESOURCES
986 So. 2d 1093 (Supreme Court of Alabama, 2007)
Rogers & Willard, Inc. v. Harwood
999 So. 2d 912 (Court of Civil Appeals of Alabama, 2007)
CLEBURNE COUNTY COM'N v. Norton
979 So. 2d 766 (Supreme Court of Alabama, 2007)
Green v. Estate of Nance
971 So. 2d 38 (Court of Civil Appeals of Alabama, 2007)
Ex Parte Ward
957 So. 2d 449 (Supreme Court of Alabama, 2006)
Goolesby v. KOCH FARMS, LLC.
955 So. 2d 422 (Supreme Court of Alabama, 2006)
Munnerlyn v. ALABAMA DEPT. OF CORRECTIONS
946 So. 2d 436 (Supreme Court of Alabama, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
944 So. 2d 138, 2006 WL 1361127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tolar-constr-llc-v-kean-elec-co-inc-ala-2006.