Bolivar Insulation Co. v. R. Logsdon Builders, Inc.

929 S.W.2d 232, 1996 Mo. App. LEXIS 1069, 1996 WL 330495
CourtMissouri Court of Appeals
DecidedJune 17, 1996
Docket20089, 20164
StatusPublished
Cited by12 cases

This text of 929 S.W.2d 232 (Bolivar Insulation Co. v. R. Logsdon Builders, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolivar Insulation Co. v. R. Logsdon Builders, Inc., 929 S.W.2d 232, 1996 Mo. App. LEXIS 1069, 1996 WL 330495 (Mo. Ct. App. 1996).

Opinion

PARRISH, Judge.

This appeal arose from litigation over construction of a commercial building. R. Logs-don Contracting, Inc., (Logsdon) appeals the amount of interest, rate of interest and the amount of attorney’s fees it was awarded on Count II of its crossclaim against W.M. Kryger Co., Carsten Auto Glass, Inc., and Carsten Auto Glass Service, Inc., (collectively referred to as “Owner”) and the part of the judgment that found for Owner and awarded damages on Count I of Owner’s crossclaim against Logsdon. This court reverses the amount of interest awarded Logsdon on Count II of its crossclaim and the rate of interest allowed; reverses the award in favor of Owner on Count I of Owner’s crossclaim against Logsdon and remands with directions as to those claims. The judgment is affirmed in all other respects.

Logsdon entered into a contract with Owner in which Logsdon agreed to construct a commercial building for Owner to use in its automobile glass business. Construction of the building was begun in late spring 1989. It was completed at the end of December 1989, or during the first part of January *234 1990. Owner took possession of the building during December 1989.

Logsdon obtained the services of a subcontractor, King Electric Co., Inc., (King) for part of the work required by the construction contract. In addition to performing work pursuant to its subcontract agreement with Logsdon, King performed work on the building directly for and at the request of Owner. Disputes arose between Logsdon and Owner and between King and Owner concerning amounts Owner owed for the work done by the contractors.

While the construction was in progress, Owner requested various changes and additions to the work required by the building plans. At the time Owner requested the first change, Logsdon and Owner agreed that Logsdon would maintain a record of additional work required by reason of Owner’s changes and additions. Logsdon was to submit one payment request for that work when the project was completed. When the project was completed, Logsdon provided Owner with a “list of extras” for the additional work.

Owner responded by preparing its own list. Owner’s list included a review of items submitted by Logsdon and various credits Owner claimed it was entitled to receive from Logsdon. Logsdon then prepared a revised list and submitted a request for payment. The request for payment was prepared on the same form Logsdon used to request periodic payments throughout the course of construction. Owner made no payment for the extras Logsdon submitted.

Logsdon thereafter filed a statement of mechanic’s lien on the property where the building was located, followed by an action to enforce the lien. See §§ 429.080 1 and 429.170. Logsdon’s action against Owner included two additional counts, one for breach of contract and one in quantum meruit. It was consolidated with a suit to enforce a mechanic’s lien that a material supplier, Bolivar Insulation Co. (Bolivar Insulation), had previously filed. See § 429.280.

After Logsdon’s action had been consolidated with the one brought by Bolivar Insulation, King filed suit against Owner contending Owner had failed to pay King for work done in addition to what its contract with Logsdon required. King alleged that the work for which it sought payment had been performed specifically at Owner’s request. King’s action was consolidated with those of Bolivar Insulation and Logsdon.

Bolivar Insulation dismissed the action it brought against Owner prior to trial. Trial proceeded on Logsdon’s and King’s claims against Owner and on a crossclaim Owner filed against Logsdon. The trial court entered judgment as follows:

King’s claim against Owner Judgment for King in the amount of $3,184.71 with prejudgment interest in the amount of $1,270.96 representing interest from May 14,1990, at the rate of 9% per annum
Logsdon’s claims ' against Owner Count I — Judgment for Owner
Count II — Judgment for Logsdon in the amount of $21,097 plus prejudgment interest on $11,187 of that amount at the rate of 9% per annum from January 5,1990; interest on judgment at the rate of 9% per annum after November 7, 1994; attorney fees of $5,000
Count III -- Judgment for Owner
Owner’s claims against Logsdon Count I -- Judgment for Owner in the amount of $1,396.72 with prejudgment interest in the amount of $557.20 representing interest from May 14,1990, at the rate of 9% per annum
Count II -- Judgment for Logsdon

Logsdon’s appeal is directed to (1) the amount of interest the trial court awarded on damages allowed Logsdon in the judgment rendered in its favor on Count II of its claim against Owner; (2) the amount of attorney’s fees the trial court awarded Logsdon on its *235 claim against Owner; and (3) the award of damages to Owner on its claim against Logs-don.

The Trial

The trial that produced the judgment from which Logsdon appeals took five days to complete and was interrupted by lengthy continuances. It commenced February 24, 1994. Opening statements and testimony from two witnesses were heard that day. Trial was to resume February 25; however, the witness whose testimony had been interrupted by the overnight adjournment was ill and could not appear. The trial court continued the case. Trial was scheduled to resume on May 26. On May 20 the trial court granted a motion for continuance. It rescheduled the remainder of the trial for July 28 and 29.

Trial resumed July 28 and 29 but was not completed. It resumed August 25, then was adjourned to September 2. Trial was completed that date and the case taken under submission.

Logsdon presents six claims of trial court error in its appeal. Points I, II and IV are directed to the amount of prejudgment interest the trial court awarded Logsdon on Count II of its crossclaim against Owner. Point III is directed to the trial court’s limitation of postjudgment interest to 9% rather than a contract rate of 18% per annum. Point V contends the trial court erred in limiting the amount of attorney’s fees awarded Logsdon to $5,000. Point VI is directed to the part of the judgment that found in favor of Owner on Count I of its crossclaim against Logsdon.

Prejudgment Interest

After the trial court entered judgment in this case, Owner filed a motion for new trial and an alternative motion to amend the judgment. The trial court granted the alternative motion and filed an “Amended Judgment.” The amended judgment included the findings:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jack Henry & Associates, Inc. v. BSC, Inc.
487 F. App'x 246 (Sixth Circuit, 2012)
Kozeny Wagner, Inc. v. Simplex Grinnell, Lp
330 S.W.3d 507 (Missouri Court of Appeals, 2010)
Cannon General Contractors, Inc. v. Mock
302 S.W.3d 772 (Missouri Court of Appeals, 2010)
Far East Services Corp. v. Tracker Marine, L.L.C.
246 S.W.3d 486 (Missouri Court of Appeals, 2007)
Jerry Bennett Masonry Contractor, Inc. v. CROSSLAND CONST. CO., INC.
213 S.W.3d 733 (Missouri Court of Appeals, 2007)
Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc.
171 S.W.3d 81 (Missouri Court of Appeals, 2005)
McKinney v. State Farm Mutual Insurance
123 S.W.3d 242 (Missouri Court of Appeals, 2003)
Nichols v. Preferred Risk Group
44 S.W.3d 886 (Missouri Court of Appeals, 2001)
Bitting v. Central Pointe Condominium Board of Managers
970 S.W.2d 898 (Missouri Court of Appeals, 1998)
McCormack v. Stewart Enterprises, Inc.
956 S.W.2d 310 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
929 S.W.2d 232, 1996 Mo. App. LEXIS 1069, 1996 WL 330495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolivar-insulation-co-v-r-logsdon-builders-inc-moctapp-1996.