Trinity Products, Inc., Plaintiff-Appellee/cross v. Burgess Steel, L.L.C., Defendant-Appellant/cross

486 F.3d 325, 62 U.C.C. Rep. Serv. 2d (West) 904, 2007 U.S. App. LEXIS 10787, 2007 WL 1309028
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 7, 2007
Docket06-2252, 06-2365
StatusPublished
Cited by22 cases

This text of 486 F.3d 325 (Trinity Products, Inc., Plaintiff-Appellee/cross v. Burgess Steel, L.L.C., Defendant-Appellant/cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Products, Inc., Plaintiff-Appellee/cross v. Burgess Steel, L.L.C., Defendant-Appellant/cross, 486 F.3d 325, 62 U.C.C. Rep. Serv. 2d (West) 904, 2007 U.S. App. LEXIS 10787, 2007 WL 1309028 (8th Cir. 2007).

Opinion

LOKEN, Chief Judge.

Burgess Steel, L.L.C. (Burgess), hired Trinity Products, Inc. (Trinity), to fabricate two steel towers. After the first tower was erected, the owner rejected it because the base plate was warped. Burgess directed Trinity to fabricate and deliver a replacement. At the end of the project, *329 Trinity sued for the balance of the contract price and for extra work not covered by the contract, primarily the value of the replacement tower. Burgess counterclaimed for breach of contract. The dispute is governed by the Missouri Uniform Commercial Code. The district court granted Trinity summary judgment of $102,958 on its contract claim and dismissed Burgess’s counterclaims. After trial, the jury awarded Trinity $60,660 for extra work. The court awarded Trinity $114,649.73 in attorneys’ fees but denied prejudgment interest and an additur. Burgess appeals the adverse judgment, and Trinity cross appeals the denial of an additur and prejudgment interest. We reverse the grant of summary judgment, vacate the award of attorneys’ fees, affirm the jury verdict, and remand.

I. Background

The general contractor hired Burgess to erect two 75-foot, 125-ton steel towers on top of a two-story building in midtown Manhattan. Burgess hired Trinity to fabricate the towers in St. Louis and deliver them to the New York City job site. The contract price as amended by three change orders was $601,896. Trinity’s two-page sale agreement was accepted by Burgess, with significant hand-written modifications, on March 5, 2003.

To fabricate each tower, Trinity welded a seven-foot square base plate, two inches thick, to the foot of the tower column. The towers when erected would be bolted to the building’s girder connections through holes in the steel base plates. While welding the base plate to the first tower (referred to by the parties as the north tower), Trinity’s welders and welding inspectors present at Trinity’s St. Louis workplace on behalf of Burgess 1 noticed that the base plate was warping. Efforts to eliminate the warping during the final welding were unsuccessful. After further discussions with the Burgess inspectors, Trinity shipped the completed north tower to a storage facility in Pennsylvania on April 16 and requested early payment, a variance from the applicable letter of credit that required inspection and approval by Burgess. A Burgess field superintendent inspected the tower in Pennsylvania and reported the warped base plate. As requested by Burgess, Trinity’s Vice President and Sales Manager sent Burgess a letter stating, “The war-page will not affect the base plate to girder connection in any way.” Burgess then paid for the tower.

Burgess erected the tower when it arrived at the Manhattan job site on May 23. The warped base plate caused gaps between the base plate and the girder of 3/4 to 1-1/16 inches. Burgess promptly advised Trinity, “it appears that base plates have not been fabricated in accordance with ... fabrication tolerances,” and advised the project’s engineer of record of the issue. Though Trinity and Burgess proposed procedures to flatten the base plate, on June 5 the engineer of record, acting on behalf of the owner and the general contractor, declared that these procedures were not acceptable and concluded: “We are loosing [sic] valuable time. We should proceed with the replacement of the column.”

Burgess removed the north tower and it was shipped back to St. Louis at Trinity’s expense. Burgess directed Trinity to fabricate a second north tower as well as the south tower called for by the contract. *330 For these two towers, Trinity developed a more thorough sequence of base plate welding procedures and reduced the size of the “fillet welds” from 5/8 inch to 5/16 inch, which reduced distortion-causing heat during the welding process. The second north tower and the south tower were delivered and successfully erected. Both Trinity and Burgess incurred significant unanticipated expenses in completing their parts of the project.

Trinity commenced this action in Missouri state court, asserting a breach of contract claim for the unpaid balance of the contract price (Count I), and a quantum meruit claim for the fair value of “extra work” requested and accepted by Burgess, primarily the second north tower (Count IV). After removing, Burgess asserted breaches of contract by Trinity— primarily the faulty first north tower— both as damage counterclaims and as defenses to Trinity’s claims.

The district court granted summary judgment dismissing the counterclaims on the ground that Burgess did not assert these claims in the time period specified in the contract. For the same reason, the court granted Trinity summary judgment on Count I, awarding $102,958 as the unpaid contract balance. The case then proceeded to trial on Count IV, the extra work claims. The jury returned a verdict in Trinity’s favor on four of the five extra work claims, awarding $60,660 in damages. The district court awarded Trinity $114,649.73 in attorneys fees on Count I but denied prejudgment interest on both counts and an additur on Count IV. Burgess appeals the summary judgment rulings, the jury verdict, and the award of attorneys fees. Trinity cross appeals the denial of prejudgment interest and addi-tur. We conclude: (i) summary judgment was improperly granted on Count I and the counterclaims; (ii) the jury verdict on Count IV is not tainted by the erroneous summary judgment ruling or by other errors alleged by Burgess on appeal; (iii) the district court properly denied Trinity an additur on Count IV; and (iv) the denial of prejudgment interest must be affirmed in part, reversed in part, and remanded in part. Accordingly, we vacate portions of the final judgment and the fee award and remand for further proceedings on Count I and the Burgess counterclaims consistent with the jury verdict.

II. The Summary Judgment Ruling

A. The principal focus of the parties’ claims and counterclaims in this case was the first north tower that was delivered to the Manhattan job site, erected, and then rejected by the engineer of record as unacceptably defective. The district court granted summary judgment dismissing Burgess’s counterclaims and defenses solely on the ground that its notice of these claims was untimely. We review the grant of summary judgment de novo. See Baum v. Helget Gas Products, Inc., 440 F.3d 1019, 1022 (8th Cir.2006) (standard of review). The parties agree that the substantive law of Missouri governs this diversity case.

A provision on the first page of the Trinity/Burgess sales contract stated: “Any claim(s) for damaged or incorrect material must be made in writing within five (5) days of receipt of material to be considered valid.” The second page, entitled TERMS AND CONDITIONS OF SALE GOODS, included a different provision:

If the goods which are being sold hereunder are defective, the Seller, at its sole option, will either repair the goods, replace the goods, or will take back the goods and refund to the Purchaser any purchase price that the Purchaser may have paid for the goods. If the Purchas *331

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tom Dunne, Jr. v. Resource Converting, LLC
991 F.3d 931 (Eighth Circuit, 2021)
Torres v. Cronin
W.D. New York, 2019
G&G Mech. Constructors, Inc. v. Jeff City Indus., Inc.
549 S.W.3d 492 (Missouri Court of Appeals, 2018)
Hagen v. Siouxland Obstetrics & Gynecology, P.C.
23 F. Supp. 3d 991 (N.D. Iowa, 2014)
American Bank of St. Paul v. TD Bank, N.A.
713 F.3d 455 (Eighth Circuit, 2013)
Kozeny Wagner, Inc. v. Simplex Grinnell, Lp
330 S.W.3d 507 (Missouri Court of Appeals, 2010)
Best Buy Stores, L.P. v. Developers Diversified Realty Corp.
715 F. Supp. 2d 871 (D. Minnesota, 2010)
Dynasteel Corporation v. Black & Veatch Corporation
698 F. Supp. 2d 1170 (W.D. Missouri, 2010)
Jason Klein v. Goodyear Tire & Rubber Co.
310 F. App'x 950 (Eighth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
486 F.3d 325, 62 U.C.C. Rep. Serv. 2d (West) 904, 2007 U.S. App. LEXIS 10787, 2007 WL 1309028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-products-inc-plaintiff-appelleecross-v-burgess-steel-llc-ca8-2007.