Uhle v. Tarlton Corp.

938 S.W.2d 594, 1997 Mo. App. LEXIS 20, 1997 WL 3314
CourtMissouri Court of Appeals
DecidedJanuary 7, 1997
Docket69673, 69674, 69695
StatusPublished
Cited by9 cases

This text of 938 S.W.2d 594 (Uhle v. Tarlton Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uhle v. Tarlton Corp., 938 S.W.2d 594, 1997 Mo. App. LEXIS 20, 1997 WL 3314 (Mo. Ct. App. 1997).

Opinion

GRIMM, Judge.

In this commercial litigation involving renovation of a budding, the jury awarded plain-tiffysubcontractor $100,000 on its quantum meruit claim against defendant/general contractor. It also awarded defendant a similar judgment on its breach of contract claim against third party defendant/owner of the building.

All parties appeal. Plaintiff alleges the trial court erred in granting defendant’s summary judgment motion. It contends it should have been permitted to pursue its breach of contract claim.

Defendant and third party defendant appeal the judgments entered on the jury verdicts. They contend that the trial court erred in overruling their motions for directed verdict.

We affirm the granting of the summary judgment. We reverse the judgments entered on the jury verdicts.

I. Background

In the summer of 1988, third party defendant Board of Education, owner of Cleveland NJROTC High School, and defendant Tarl-ton Corporation, 1 a general contractor, entered into a contract for the school’s renovation. At that time, defendant entered into a subcontract with plaintiff Apple Electric Company 2 to furnish the electrical work required by the contract. The Board did not have a contract with plaintiff.

Under the contract, the building renovation was to be substantially completed by May 5,1989. Final completion was due June 2,1989.

The subcontract between plaintiff and defendant utilized a “Standard Subcontract Agreement” developed by the Associated General Contractors of America and other associations. In the agreement, plaintiff agreed to provide all labor and materials for “the ELECTRICAL WORK necessary for the renovation” of the school “in accordance with the drawings and specifications” prepared by the architect. Further, concerning change orders, the agreement stated that plaintiff would:

Make any and all changes or deviations from the original plans and specifications without nullifying the original contract when specifically ordered to do so in writ- *596 mg by [defendant]. [Plaintiff] prior to the commencement of this revised work, shall submit promptly to [defendant] written copies of the cost or credit proposed for such revised work in a manner consistent with the Contract Documents.

The renovation project did not go smoothly. There were problems from the beginning. During the course of the project, defendant and plaintiff modified the subcontract by executing twenty-three change orders. Plaintiffs project manager signed change orders one through eleven. The other change orders were signed by a vice president of the company.

All of the change orders were on a pre-printed form. Each was dated and identified the project. The preprinted form then read, ‘You are directed to make the following change to this P.O./Subcontract:.” At this point, typed language appeared. For example, change order number 7 read “For furnishing the necessary labor, material, tools and equipment for reinstallation of electric cords removed from stage lighting as per your verbal quote of 10-6-88, for the increased lump sum amount of THREE HUNDRED SEVENTY FIVE DOLLARS ($375.00).”

The preprinted form then continued, reading “All other terms and conditions of the subject P.OySubcontract referred to above shall remain unchanged and in full effect.” Following this were entries showing the original subcontract price, the net change from previous change orders, the total subcontract sum prior to this change order, the amount changed by this change order, and the new subcontract sum including this change order. The change orders were signed by representatives of plaintiff and defendant.

Defendant prepared all of the change orders. All entries on the forms were either preprinted or typewritten, except for signatures. On two of the orders, handwritten entries were made.

Defendant issued the first of the two, change order 8, on May 19, 1989. Plaintiffs project manager accepted it on July 19. On the change order, the project manager wrote, “jRevised schedule dates are per our letter of June 20,1989.” (emphasis added).

A June 20 letter proposed completion dates for various areas of the project, with the latest date being July 28. In addition, the letter indicated “increased costs associated with these dates” totalling $39,621.21. This letter was signed by plaintiffs project manager.

On June 26, plaintiffs vice president wrote defendant. His letter asked defendant to disregard project manager’s June 20 letter. Also, the vice president sent plaintiff another letter dated June 20. This letter was similar to the project manager’s letter, except it did not include any request for additional costs.

At trial, project manager testified that he had “secondhand” information that his June 20 letter had been withdrawn due to defendant’s “contractual coercion.” He said the coercion was defendant’s objection to receiving a “claim letter on their project.” He said he heard that defendant’s representative told plaintiffs vice president that a progress payment would not be made unless he withdrew the claim letter.

The second order with a handwritten entry, change order 11, issued by defendant on July 12 and accepted by plaintiff on July 21, was a “no cost” change order. The typed portion of the order provides:

This is a no cost change order extending the contract time on the Renovation Work portion of the contract by sixty three (63) calendar days. This time extension is a result of the changes in the contract work to date.
Completion for the renovation work is changed from May 5, 1989 to July 7,1989. The above is in accordance with the Owner’s Change Order No. 20.

Plaintiffs project manager struck through the words, “from May 6, 1989 to July 7, 1989.” He added, “Schedule dates are changed in accordance with Apple Electric’s letter dated June 20, 1989.” (emphasis added).

Plaintiff completed its work by the end of September, 1989. The original subcontract amount was $572,500. The change orders increased this to $873,503.45. The Board *597 paid that amount to defendant, who in turn paid it to plaintiff.

Plaintiff sued defendant, alleging two causes of action: breach of contract and quantum meruit. Plaintiff alleged that defendant either breached or abandoned the subcontract due to cardinal changes, delays, and fundamental alterations of the contract beyond its original scope.

In its breach of contract count, plaintiff sought reimbursement for productivity loss and inefficiency, additional direct costs, extended overhead costs, cost of capital, ten percent profit, and cost of claims preparation. It alleged these costs totaled $480,-144.80. In its quantum meruit count, it sought judgment for $480,150.80.

Prior to trial, plaintiff admitted that the subcontract, modified by the change orders, encompassed the entire scope of plaintiffs work on the renovation project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115 (Missouri Court of Appeals, 2013)
Gill Construction, Inc. v. 18th & Vine Authority
157 S.W.3d 699 (Missouri Court of Appeals, 2005)
Jerome Group, Inc. v. Cincinnati Ins. Co.
257 F. Supp. 2d 1217 (E.D. Missouri, 2003)
Friar v. Statutory Trustees of Kirkwood Sports Ass'n
959 S.W.2d 808 (Missouri Court of Appeals, 1997)
Mathis v. Jones Store Co.
952 S.W.2d 360 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
938 S.W.2d 594, 1997 Mo. App. LEXIS 20, 1997 WL 3314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uhle-v-tarlton-corp-moctapp-1997.