Air Cooling & Energy, Inc. v. Midwestern Construction Co. of Missouri, Inc.

602 S.W.2d 926, 1980 Mo. App. LEXIS 2754
CourtMissouri Court of Appeals
DecidedAugust 4, 1980
DocketWD 30812
StatusPublished
Cited by19 cases

This text of 602 S.W.2d 926 (Air Cooling & Energy, Inc. v. Midwestern Construction Co. of Missouri, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air Cooling & Energy, Inc. v. Midwestern Construction Co. of Missouri, Inc., 602 S.W.2d 926, 1980 Mo. App. LEXIS 2754 (Mo. Ct. App. 1980).

Opinion

MANFORD, Judge.

This is an original proceeding by subcontractor for declaratory judgment interpreting liability of parties relative to an excavating contract. The parties stipulated either could move for summary judgment. Appellant, by motion to Rule 74.04, sought summary judgment. Respondents also sought summary judgment and trial court entered judgment for both respondents. This appeal followed. The judgment is affirmed.

Appellant charges the trial court erred in (1) its finding that appellant was not entitled to recovery on either theory of breach of contract, breach of warranty or quantum meruit, (2) its finding that removal of the rock was not extra work or an unforeseen physical condition outside the agreement of the parties, and (3) its finding that appellant was obligated to make an independent interpretation of subsurface conditions or that such finding should have established the existence of an ambiguous contractual situation which should have been resolved against respondents.

Review of this matter is limited by Rule 73.01 as interpreted by Murphy v. Carron, 536 S.W.2d 30 (Mo.banc 1976). Review is of an equitable nature upon both the evidence and the law, see Tockman v. Shower Doors, Inc., 568 S.W.2d 74 (Mo.App. 1978). The judgment should be affirmed regardless of the theory upon which it is based insofar as upon the law and evidence, such judgment could have been properly reached on any reasonable theory, see Snadon v. Gayer, 566 S.W.2d 483 (Mo.App. 1978).

The instant case was tried to the court upon the pleadings, a stipulation of facts and documents pertaining to the contract in dispute. The record does not reveal a request by any of the parties for findings of fact and conclusions of law and such is not required of the trial court if not requested, see Skinner v. Henderson, 556 S.W.2d 730 (Mo.App.1977). When findings and conclusions are not requested, all fact issues are to be considered found in accordance with the result reached by the trial court, see Marriage of Badalamenti, 566 S.W.2d 229 (Mo.App.1978).

The trial court herein, in its judgment, entered what it termed its conclusions in support of the judgment.

*928 The evidence reveals Jackson County (hereinafter referred to as County) desired to have constructed for public use, a beach area and bath house in Fleming Park, which contains Lake Jaeomo. The county, by its governing body, solicited formal public bids for the work. Respondent, Midwestern Construction Co. of Missouri, Inc. (hereafter referred to as Midwestern) secured the low bid as general contractor. Midwestern, in turn, contracted with appellant for appellant’s removal of subsurface soil and material for the purpose of installing various “pipes, lines and underground mains”. Appellant, as the excavating subcontractor, was to excavate a “force main trench” and a “water line trench” running approximately parallel to each other. Specifications were prepared by the consulting engineers, George Butler and Associates (hereafter referred to as Engineer). In conjunction with the preparation of specifications, Engineer contracted with Layne-Western Co. to have soil borings made for design purposes. These borings were made and logs thereof were prepared. The logs indicated at boring no. 4, “Refusal was encountered at 1.1 feet.”

Appellant relied upon the boring logs by its own choice. As the work proceeded, appellant struck rock for a distance of some 150-200 feet along the trench areas. Appellant sought a change order, requesting reimbursement for the cost of rock removal claimed to be encountered between borings no. 4 and no. 7. The change order and extra payment were refused upon recommendation by the Engineer.

Appellant seeks recovery of $9,558.18 for labor and materials claimed as extra and unforeseen work. Respondents declined payment, contending the agreement between the parties excluded any liabilities for such costs as they were not extra and unforeseen as claimed. The dispute centers upon the agreement between the parties and the interpretation to be given thereto.

The trial court within its judgment concluded:

“1. Under its contract, the plaintiff was required to excavate all materials of whatever nature and whatever substances encountered within the limits of the project including rock.
2. Test boring results were specifically excluded from the contract, and the work performed by plaintiff in excavation of 150 to 200 feet of rock was not ‘extra work’ under the contract. The rock encountered by the excavation was not an ‘unforeseen physical condition’ as contemplated under the contract.
3. The plaintiff had no right to rely on the borings obtained for design purposes and was obligated to make an independent interpretation of subsurface conditions.
4. Plaintiff is not entitled to any further or additional compensation from either defendant.
5. Plaintiff is not entitled to recover on the basis of quantum merit [sic], breach of warranty or breach of contract.”

Appellant’s first and second points of alleged error are taken up together, as they interrelate to the same evidence, and there is no evidence on the record to support the allegation of breach of contract. This leaves the question: Is appellant, in the alternative, entitled to recover upon a theory of warranty or upon the theory of quantum meruit? In considering this question, it is necessary to simultaneously address point (2) raised by appellant.

The matter of warranty will be first discussed. The stipulation of facts reveal appellant relied upon the test boring logs. The evidence, by stipulation, further reveals that the contract between respondent Midwestern (as general contractor) and appellant (as subcontractor) was subject to the original contract between Midwestern and the County. That contract provided the following pertinent provisions:

“a. (General Conditions Section 6.11) ‘Contractor agrees to bind specifically every subcontractor to the applicable terms and conditions of the contract documents for the benefit of owner.’ * * *
*929 c. (Specifications, General Requirements, paragraph 1-4, entitled sub-surface investigation)
‘A. Subsurface data has been obtained for design purposes.
B. Copies of such data will be made available on request from the engineer, George E. Butler & Associates, Inc.
C. Neither the owner nor the engineer will be responsible for the completeness of accuracy of data so furnished.
D. The bidder shall make his own interpretations of this available information and.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan v. City of Cotter
2009 Ark. 457 (Supreme Court of Arkansas, 2009)
FOUNDATION INTERN. v. ET Ige Const.
78 P.3d 23 (Hawaii Supreme Court, 2003)
McNeill v. Community Title Co.
11 S.W.3d 863 (Missouri Court of Appeals, 2000)
St. Anthony's Medical Center v. H.S.H.
974 S.W.2d 606 (Missouri Court of Appeals, 1998)
Uhle v. Tarlton Corp.
938 S.W.2d 594 (Missouri Court of Appeals, 1997)
Cook v. State
821 S.W.2d 600 (Court of Criminal Appeals of Texas, 1991)
Murphy v. City of Springfield
738 S.W.2d 521 (Missouri Court of Appeals, 1987)
Hayes Drilling, Inc. v. Curtiss-Manes Construction Co.
715 S.W.2d 295 (Missouri Court of Appeals, 1986)
Sanders Co. Plumbing & Heating, Inc. v. City of Independence
694 S.W.2d 841 (Missouri Court of Appeals, 1985)
City of Columbia v. Paul N. Howard Co.
707 F.2d 338 (Eighth Circuit, 1983)
Mickels v. Henderson
642 S.W.2d 661 (Missouri Court of Appeals, 1982)
Crockett v. Morelock
608 S.W.2d 530 (Missouri Court of Appeals, 1980)
Watkins v. Johnson
606 S.W.2d 493 (Missouri Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
602 S.W.2d 926, 1980 Mo. App. LEXIS 2754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-cooling-energy-inc-v-midwestern-construction-co-of-missouri-inc-moctapp-1980.