Hayes Drilling, Inc. v. Curtiss-Manes Construction Co.

715 S.W.2d 295, 1986 Mo. App. LEXIS 4581
CourtMissouri Court of Appeals
DecidedAugust 26, 1986
DocketNo. WD 37709
StatusPublished
Cited by2 cases

This text of 715 S.W.2d 295 (Hayes Drilling, Inc. v. Curtiss-Manes Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hayes Drilling, Inc. v. Curtiss-Manes Construction Co., 715 S.W.2d 295, 1986 Mo. App. LEXIS 4581 (Mo. Ct. App. 1986).

Opinion

PRITCHARD, Judge.

Appellant School District hired an architectural firm, Wm. B. Ittner, Inc., to assist in the planning and design of a new high school building to be located in Mokane, Missouri. The architectural firm and the structural engineer on the project needed to know the approximate location of bedrock on the site, so the School District [296]*296employed the Klockow firm to conduct soil borings and make a report. Klockow made 20 borings in the general vicinity of where piers, 117 in all, were to be put down according to subsequent specifications prepared by Ittner, and Klockow’s logs of soil borings were attached to the specifications.

Curtiss-Manes was the general contractor to whom the School District awarded the job on its low bid of $4,647,000. That bid included a base bid of $19,800 and a unit price bid for removal of obstructions of $800 per cubic yard submitted by subcontractor Hayes for drilling the piers. Prior to the award of the general contract, respondent’s Jene Hayes cursorily reviewed the pier drilling specifications. He acknowledged that the Klockow boring logs contained 18 references to “auger scrapings” and numerous references to “gravel in auger cuttings”, “hard to drill” and “very hard to drill”, but they did not lead him to believe that there might be difficult subsurface conditions. Hayes did acknowledge that the term “auger scraping” meant to him that Klockow had hit rock and had heard the auger scraping as it passed through the obstruction. He did not ask Klockow for an explanation. The specifications gave the pier drilling contractor the right to perform test borings on its own as its own expense, but Hayes decided that since the logs showed no subsurface water, no test borings needed to be done prior to bidding. Hayes had done work on projects in the Jefferson City and Columbia areas, and had recently finished a job at the Calloway Nuclear Plant, near to Mok-ane, where it was forced to use a rock auger (below described) to bore through difficult subsurface materials common to the area.

The specifications provided by the architect divided the work and the payment to the pier drilling contractor into two parts, the first part being a base bid (the $19,800) computed on the number of drilled piers, their design length from top to bottom, and their diameters. It included a bell-shaped excavation at the bottom of each shaft and the removal of six inches of rock from the bedrock when it was reached. The second part provided for unit prices for greater or lesser depths of excavation, bell volumes and for excavation of obstructions. The architect later issued an addendum to the specifications, Item No. 6, to clarify paragraph 8.06 of Section C, unit prices which provided: “The unit price quoted for ‘obstructions’ shall be used to adjust the contract work for removal of obstructions as defined in 3.02 P (Pgs. 2D-6 and 2D-7) and rock removed from the bottom of the shaft to obtain satisfactory bearing.” Page 2D-6 covers obstructions: “1. If rock, boulders or other unforeseen obstructions are encountered which cannot be removed by standard drilled pier excavation methods, and if such obstructions are not indicated by available subsurface data, removal of such obstructions will be paid for in accordance with the terms of the Contract relative to changes in the work. Standard excavation methods include conventional earth auger, pengo bit, stepped taper bit, teeth on auger or other attachments to auger. 2. Remove such obstructions by hand labor using air-powered tolls (sic), core barrels with drilled pier drilling equipment, or by other safe methods recognized in the construction industry. The Owner’s representative must be notified upon encountering any obstruction which cannot be removed with the equipment specified. Further removal of obstructions shall be made only upon the direction of the Owner’s representative. The Owner’s representative shall reach an agreement with the Contractor as to the volume of the obstruction removed. For the purpose of payment, all such obstructions shall be considered as rock. * * * 4. The work of this Section includes demolition and removal of rock, boulders, concrete, masonry and other subsurface obstructions which are indicated by the Contract Documents, or by the subsurface exploration data and such work will be considered a change in the work.”

Hayes started the excavation work for piers on September 30,1980, with Klockow, the owner’s inspector being present, using an earth auger which was capable of drill[297]*297ing small boulders, gravel and chert, which could have caused the scraping sound noted on Klockow’s logs. On the second day of drilling, Hayes encountered rock which caused the earth auger with teeth on it to spin and go no farther. The drilling operator immediately called Klockow and advised him that he had gone down as far as he could with an earth auger and asked him what he should do, and that he had encountered rock but it was not all over the hole. Klockow told him that he had to go on down farther. Klockow was looking for solid (bed) rock, which had the proper weight-bearing capacity, and which (then) had to be drilled down another six inches.

The drilling operator then changed to a rock auger. Thomas Lee Taylor, a manufacturer of augers for 17 years, originally made earth augers which had a grader blade bolted onto it, and then was upgraded by placing teeth on it, but it will not cut rock, as will no earth auger with all improvements thereon over the 17 years Taylor had been in business. If the rock is smooth or solid, an earth auger with teeth will just spin around, jerk, and the blade could be broken and torn up. Taylor testified that the rock auger, upon which he had patents, was entirely different from an earth auger. The difference is in both the type of teeth and the configuration. The rock auger has a starter pilot bit with carbide on it, and the teeth are distributed so that it will scrape into the rock and crush it. It is not a standard drilling device unless rock is being drilled, and it is too slow and time-consuming for earth drilling. A core barrel drill serves a similar purpose as a rock auger, but requires a seam so that its teeth may break off chunks of rock no larger than six inches, which go into the barrel and then are lifted to the surface.

Hayes’ foreman, Spurlock, told Klockow that he should shoot the elevations because it (what he had struck) was rock which would be paid for under the contract. The elevation measurement was taken (apparently down to the rock which was struck), and Spurlock drilled with the rock auger down to good rock, and measurements were again taken and checked by Klockow. Klockow first agreed that the debris was rock, and then said it was not rock, and when Spurlock filled out the drilled shaft log, noting how much additional rock over the 6 inches of the base contract was removed, Klockow refused to sign it because he believed it would be a contract. Copies of the daily logs, with the amount of rock removed noted, were given to Klockow, who apparently chose not to tell the owner about them because he did not believe they were obstructions.

Upon learning that Klockow felt that Hayes should not get extra payment for using its rock auger, it stopped drilling. On October 3, 1980, a meeting was held at the site with Jene Hayes, two persons from Curtiss-Manes, the School District’s Superintendent, Darrel Lee, and Ittner’s on-site architect, Tom Kuehling, and a Mr. Satter-field, being present. Hayes told those present that he believed he should be paid for rock removal when he had to use his rock auger.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HERION COMPANY, Plaintiff-Respondent v. TANEY COUNTY, MISSOURI
514 S.W.3d 620 (Missouri Court of Appeals, 2017)
County Asphalt Paving Co. v. 1861 Group, Ltd.
851 S.W.2d 577 (Missouri Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
715 S.W.2d 295, 1986 Mo. App. LEXIS 4581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hayes-drilling-inc-v-curtiss-manes-construction-co-moctapp-1986.