Steinberg v. Fleischer

706 S.W.2d 901, 1986 Mo. App. LEXIS 3797
CourtMissouri Court of Appeals
DecidedMarch 11, 1986
Docket47597
StatusPublished
Cited by27 cases

This text of 706 S.W.2d 901 (Steinberg v. Fleischer) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steinberg v. Fleischer, 706 S.W.2d 901, 1986 Mo. App. LEXIS 3797 (Mo. Ct. App. 1986).

Opinion

CRANDALL, Presiding Judge.

Plaintiffs, Erwin E. Steinberg and Jack Tyrer, d/b/a Gravois Associates, brought, an action against defendants, Alfred J. Fleischer, et al., d/b/a Fleisher-Seeger Construction Co., for breach of a construction contract. Defendants counterclaimed based on theories of breach of contract, quantum meruit, negligence and fraud. Defendants appeal from the judgment, in a jury-tried case, in favor of plaintiffs on their claim for damages in the amount of $137,000 and in favor of plaintiffs on defendants’ counterclaim. We affirm in part and reverse and remand in part.

The evidence established that, on December 7, 1977, plaintiffs entered into a contract with defendants to construct a supermarket. The contract called for completion within nine months, which was later extended to ten months. The construction contract consisted of a standard form prepared by the American Institute of Architects (AIA). The parties agreed to modify the form contract by deleting (1) the phrase excusing the date of completion because of “adverse weather conditions” 1 and (2) the section providing for an equitable adjustment in the contract sum if “concealed *904 conditions” below the surface of the ground were encountered during construction. 2 Defendants commenced site preparation work immediately, but then stopped all work until late March of 1978 due to severe winter weather. In April, a subcontractor hit rock while digging a new sewer line. The rock had to be blasted. In June, excavation of the building site began, but then another subcontractor encountered difficulties compacting the soil. A myriad of other problems surfaced. In December 1978, work resumed and the building was substantially completed on October 10, 1979.

In their first point, defendants contend that the trial court erred in granting partial summary judgment in favor of plaintiffs on the issue of defendants’ liability for breach of contract.

In reviewing the trial court’s ruling on a motion for summary judgment the appellate court must scrutinize the record in the light most favorable to the party against whom judgment was rendered, resolving all doubts in favor of that party. First Nat. Bank of St. Charles v. Chemical Products, Inc., 637 S.W.2d 373, 375 (Mo.App.1982). When a party is confronted with a motion for summary judgment supported by affidavits, he must set forth specific facts showing that there is a genuine issue of fact for trial. Clayton Brokerage Co. v. Raleigh, 679 S.W.2d 376, 379 (Mo.App.1984).

In their motion for partial summary judgment, plaintiffs alleged that defendants failed to comply with Article 8.3.2 3 of the General Conditions of the contract; and therefore any excuse defendants might have had for delay beyond the date specified for completion in the contract was waived. In support thereof, plaintiffs submitted the architect’s affidavit and one defendant’s deposition testimony which acknowledged that no such requests had been made. Defendants, in their response to the motion for summary judgment, urged that written requests should not be required when the delay was caused solely by the other party. Additionally, in their supplemental response to summary judgment and in their motion for reconsideration, defendants countered that progress letters had been written to plaintiff-owner, not plaintiff-architect. They claimed that these letters were effective as requests for extensions of time and that the owner’s failure to respond to these letters was tantamount to acquiescense to the delays. Defendants also argued that the contract was unenforceable because, based on deposition testimony, plaintiffs had fraudulently induced them to enter the contract by failing to disclose either the existing subsurface conditions at the building site or the architect’s ownership interest in the project.

The meaning of Article 8.3.2 is plain on its face. In Herbert & Brooner Construction Co. v. Golden, 499 S.W.2d 541, 549 (Mo.App.1973), the court interpreted the same contractual provision, stating:

[I]t is incumbent upon the contractor, in order to avail of an extension of time ... to lay claim therefor at the time and within the time and manner stipulated. Otherwise no such extension of time is available to him on the grounds of waiver ... in the very face of a provision *905 stiplating a precise time.... (Citations omitted.)

The contract in this case, although a “standard” contract, was freely negotiated. The parties could have included any reasonable terms dealing with construction delays that they thought appropriate. Having agreed on the terms, they ordinarily would be bound by them. The question here is whether defendants have raised any factual issues which would preclude strict enforcement of Article 8.3.2 of the contract. In considering that question, we look to the record at the time the motion for summary judgment was submitted.

Defendants argue, inter alia, that plaintiffs fraudulently misrepresented the subsoil conditions at the time of entering into the contract. If, in fact, there was fraud in the inducement there could be no legally enforceable contract. Fraud avoids all contracts, where it can be shown that, but for the fraud, the defrauded party would not have entered into the contract. Taggart v. School Dist. No. 52, Carroll County, 339 Mo. 223, 96 S.W.2d 335, 337 (Mo.1936). In the present case, it was for the jury to decide whether representations were made, whether the representations were false, and whether defendants were entitled to rely on the representations. See, e.g., Essex v. Getty Oil Co., 661 S.W.2d 544, 550-551 (Mo.App.1983). Plaintiffs’ fraudulent inducement was therefore a genuine issue of fact for trial.

If the facts establish that plaintiffs fraudulently induced defendants to contract, the next question is whether defendants’ actions after discovering the fraud constituted a waiver. Waiver can be found in either the words or actions of defendants. To be construed as an implied waiver, defendants’ acts must be so manifestly consistent with and indicative of an intention to renounce a particular right or benefit that no other reasonable explanation of their conduct is possible. Meyer v. Brown, 312 S.W.2d 158, 162 (Mo.App.1958).

The evidence submitted at the time of the motion for summary judgment established that defendants did not walk off the job; they remained and substantially completed the project. If defendants, with full knowledge of the material facts, chose to honor the contract they may have waived the fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Navy, LLC v. South Lakeview Plaza I, LLC
Missouri Court of Appeals, 2023
Steelhead Townhomes, L.L.C. v. Clearwater 2008 Note Program, LLC
537 S.W.3d 855 (Missouri Court of Appeals, 2017)
Craig Outdoor v. Wally Kelly
Eighth Circuit, 2008
Smith v. Hammons
63 S.W.3d 320 (Missouri Court of Appeals, 2002)
deKallos v. Weis
941 S.W.2d 630 (Missouri Court of Appeals, 1997)
MCI Metro Access Transmission Services., Inc. v. City of St. Louis
941 S.W.2d 634 (Missouri Court of Appeals, 1997)
In Re Estate of Hayes
941 S.W.2d 630 (Missouri Court of Appeals, 1997)
Uhle v. Tarlton Corp.
938 S.W.2d 594 (Missouri Court of Appeals, 1997)
Silver Dollar City, Inc. v. Kitsmiller Construction Co.
931 S.W.2d 909 (Missouri Court of Appeals, 1996)
Vogler v. Real Earth United States Enterprises, Inc.
907 S.W.2d 377 (Missouri Court of Appeals, 1995)
Fru-Con Construction Co. v. Southwestern Redevelopment Corp. II
908 S.W.2d 741 (Missouri Court of Appeals, 1995)
Sunset Pools of St. Louis, Inc. v. Schaefer
869 S.W.2d 883 (Missouri Court of Appeals, 1994)
Citizens Bank of Appleton City v. Schapeler
869 S.W.2d 120 (Missouri Court of Appeals, 1993)
Howe v. Lever Bros. Co.
851 S.W.2d 769 (Missouri Court of Appeals, 1993)
Fitch v. J.A. Tobin Construction Co.
829 S.W.2d 497 (Missouri Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
706 S.W.2d 901, 1986 Mo. App. LEXIS 3797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steinberg-v-fleischer-moctapp-1986.