Silver Dollar City, Inc. v. Kitsmiller Construction Co.

931 S.W.2d 909, 1996 Mo. App. LEXIS 1605, 1996 WL 544221
CourtMissouri Court of Appeals
DecidedSeptember 25, 1996
Docket20186
StatusPublished
Cited by34 cases

This text of 931 S.W.2d 909 (Silver Dollar City, Inc. v. Kitsmiller Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silver Dollar City, Inc. v. Kitsmiller Construction Co., 931 S.W.2d 909, 1996 Mo. App. LEXIS 1605, 1996 WL 544221 (Mo. Ct. App. 1996).

Opinions

BARNEY, Presiding Judge.

On remand by this Court, Appellant Kit-smiller Construction Company, Inc., (Kitsmil-[911]*911ler) now appeals the judgment of the Circuit Court of Christian County, Missouri, in a declaratory judgment action originally brought by Silver Dollar City, Inc., (SDC) arising from a purported construction contract entered into between the parties herein.

In its judgment the hearing court held invalid certain arbitration provisions contained in a disputed construction contract. The hearing court determined that the contract itself was void in that it did not reflect a “meeting of the minds” of the parties be-, cause the contracting parties could not be identified with reasonable certainty. We reverse and remand.

I.

BACKGROUND

This suit began on April 10, 1992, when SDC filed a two count petition against Kit-smiller. It averred that Kitsmiller was demanding arbitration of a claim against SDC for $341,482.17 aidsing from a purported construction contract heretofore entered into by the parties providing for concrete construction work.1

In its Count I, SDC sought relief and an express declaration that the arbitration provisions be held unenforceable and requested that arbitration be permanently stayed. In Count II, SDC prayed for injunctive relief, barring Kitsmiller from pursuing arbitration.

Kitsmiller counterclaimed, requesting that the parties be required to submit to binding arbitration of Kitsmiller’s claim.

In time, both parties respectively moved for summary judgment.

The prior hearing court held that Kitsmil-ler was not entitled to arbitration since its exclusive remedy was Chapter 429, RSMo 1986, as amended (mechanics’ lien).

On appeal in Silver Dollar City v. Kitsmiller Const. Co., 874 S.W.2d 626 (Mo.App.1994), this Court determined that since SDC was the “Architect” under the terms of the disputed contract, but was not licensed or registered as one, the arbitration provisions contained in the disputed contract were otherwise valid and were not waived by Kitsmil-ler’s failure to submit its claim against SDC to the “Architect” of the project.

Secondly, this Court determined that the provision in the disputed contract, which stated that the alleged contract would be governed by the law of the place where the project was placed, did not mean that Missouri’s equitable mechanics’ lien procedure would override the arbitration provisions of the contract and result in the mechanics’ lien enforcement proceeding being the exclusive remedy for Kitsmiller.

This Court remanded the case stating that: “If the trial court finds the Contract void or, for some other reason, unenforceable, there is obviously no valid arbitration provision. ... However, if the trial court finds the Contract is binding on the parties, Kit-smiller is entitled to an order compelling arbitration [per terms of the contract].” Silver Dollar City, 874 S.W.2d at 537.

As further background, other ancillary actions have taken place between the parties herein.

On February 10, 1992, Kitsmiller filed a mechanic’s lien against the Grand Palace in the office of the Clerk of the Circuit Court of Taney County.2 Additionally, Kitsmiller filed a demand for arbitration with the American Arbitration Association, in Case No. 57 110 [912]*9120018 92, to which SDC responded by entering a general appearance without consenting to the jurisdiction of the arbitration tribunal. SDC then pled, inter alia, that the purported contract was ‘Void, has been voided, or is revocable upon the law or in equity.”

II.

KITSMILLER’S ALLEGATIONS OF HEARING COURT ERROR

Kitsmiller posits five major points of error. We address only Point One since it is disposi-tive herein. Kitsmiller argues that the hearing court erred when it determined that there was no contract entered into between the parties herein.

III.

TERMS OF THE DISPUTED CONTRACT

The first page of the disputed agreement was dated June 27, 1991, and denominated SDC as the “Owner” and Kitsmiller and Vin-yard Construction Co., Inc., JV (Vinyard) as the “Contractor.”3 It provided that the Contractor was to perform certain concrete construction work on the “Grand Palace” theater project in Branson, Missouri, and in return SDC promised to pay the Contractor $648,656.00. The disputed contract also contained an arbitration provision.4

A factual dispute centers around the signature portion of the purported contract wherein only Rick Todd, the representative of “Owner”, SDC, and Cary A, Paschke, Project Manager of “Contractor”, Kitsmiller, have signed the document. No other signatures or parties appear on the page. Unlike the face sheet, the name “Vinyard” is not found.

IV.

CONTENTIONS OF THE PARTIES

In the instant hearing and on appeal herein, SDC contends that it was contracting with a joint venture consisting of Kitsmiller and Vinyard and not Kitsmiller alone.5 It alleges that it did so because Kitsmiller lacked the financial strength to be engaged in such a project alone and was unable to put up the necessary performance, labor and material bond without Vinyard’s financial assistance. SDC makes allegations of misrepresentation on the part of Kitsmiller and Vinyard when they held themselves out to be jointly involved in the project, knowing they would not be.

SDC further contends that in contracting with the joint venture it did so because of Vinyard’s expertise in “tilt up” concrete work6, since Kitsmiller had little or no experience in this type of work. SDC also contends that the term “Kitsmiller” or “Kitsmil-ler Construction Co., Inc.,” was a shorthand method for describing the joint venture. Therefore, when the term “Kitsmiller Construction Co., Inc.,” was used in the signature portion of the disputed document, SDC interpreted the term to mean the joint venture of Kitsmiller and Vinyard, without which it would never have entered into the contract.

SDC steadfastly denies that it knew that Kitsmiller and Vinyard were not engaged in [913]*913a joint venture project and freely accepted Kitsmiller’s work on the project. SDC contends that it was not until Kitsmiller removed itself from the project about October 17,1991, after a series of disputes had arisen between SDC and Kitsmiller that SDC came upon this knowledge.7

In this latest court hearing forming the basis for this appeal, SDC was allowed to amend its original declaratory petition by interlineation to assert that the contract in question did “not reflect the mutual assent, or the meeting of the minds, of the parties hereto, and [was] void.” Over objection of Kitsmiller, the hearing court allowed SDC to amend the pleadings to conform to the evidence consistent with the prior theories pled.

Kitsmiller, on the other hand, maintains that SDC was always aware of Kitsmiller’s sole involvement in the project and that SDC’s project manager, Wayne Brodt, had specifically authorized Kitsmiller to proceed on its own without a performance bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pietoso, Inc. v. Republic Services, Inc.
4 F.4th 620 (Eighth Circuit, 2021)
Greg Hall v. Lowell Fox and Gina Fox
Missouri Court of Appeals, 2014
Hall v. Fox
426 S.W.3d 23 (Missouri Court of Appeals, 2014)
2 MIKES, INC. v. TURNING LEAF PROPERTIES, LLC, Defendant-Respondent.
423 S.W.3d 860 (Missouri Court of Appeals, 2014)
Houston v. Crider
317 S.W.3d 178 (Missouri Court of Appeals, 2010)
Tom's Agspray, LLC v. Cole
308 S.W.3d 255 (Missouri Court of Appeals, 2010)
Guidry v. Charter Communications, Inc.
269 S.W.3d 520 (Missouri Court of Appeals, 2008)
Herd v. American SEC. Ins. Co.
556 F. Supp. 2d 992 (W.D. Missouri, 2008)
Whitehill v. Whitehill
218 S.W.3d 579 (Missouri Court of Appeals, 2007)
Sherman v. Deihl
193 S.W.3d 863 (Missouri Court of Appeals, 2006)
Pride v. Lewis
179 S.W.3d 375 (Missouri Court of Appeals, 2005)
Shurgard Storage Centers v. Lipton-U. City, LLC
394 F.3d 1041 (Eighth Circuit, 2005)
Jerry Mitchell v. Henry Wiley
106 F. App'x 517 (Eighth Circuit, 2004)
Don King Equipment Co. v. Double D Tractor Parts, Inc.
115 S.W.3d 363 (Missouri Court of Appeals, 2003)
Shervin v. Huntleigh Securities Corp.
85 S.W.3d 737 (Missouri Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
931 S.W.2d 909, 1996 Mo. App. LEXIS 1605, 1996 WL 544221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silver-dollar-city-inc-v-kitsmiller-construction-co-moctapp-1996.