Silver Dollar City, Inc. v. Kitsmiller Construction Co.

874 S.W.2d 526, 1994 Mo. App. LEXIS 449, 1994 WL 80356
CourtMissouri Court of Appeals
DecidedMarch 15, 1994
Docket18910
StatusPublished
Cited by9 cases

This text of 874 S.W.2d 526 (Silver Dollar City, Inc. v. Kitsmiller Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silver Dollar City, Inc. v. Kitsmiller Construction Co., 874 S.W.2d 526, 1994 Mo. App. LEXIS 449, 1994 WL 80356 (Mo. Ct. App. 1994).

Opinion

CROW, Judge

The question is whether Kitsmiller Construction Company, Inc. (“Kitsmiller”), a Missouri corporation, is entitled to arbitration of a claim by it against Silver Dollar City, Inc. (“SDC”), a Missouri corporation. The dispute arises from a written agreement between the two dated June 27,1991, wherein Kitsmiller promised to perform certain *528 work on a construction project and SDC promised to pay Kitsmiller $648,656. The agreement contained an arbitration provision, quoted infra.

This suit began April 10, 1992, when SDC filed a two-count petition against Kitsmiller. The petition averred Kitsmiller was demanding arbitration of a claim against SDC for $341,432.17. By count I, SDC sought relief including a declaration that the arbitration provision was, for sundry reasons, unenforceable, together with an order that arbitration “be terminated and permanently stayed.” In count II, SDC prayed for an injunction barring Kitsmiller from pursuing arbitration.

Kitsmiller counterclaimed, asking that SDC be required to submit to binding arbitration of Kitsmiller’s claim.

Both parties ultimately moved for summary judgment. The trial court held Kit-smiller was not entitled to arbitration and that its exclusive remedy was chapter 429, RSMo 1986, as amended (mechanics’ lien). Kitsmiller appeals.

The June 27, 1991, agreement (“the Contract”) designates SDC as “the Owner” and Kitsmiller as “the Contractor.” 1 The Contract identifies the project as: “Grand Palace.” The Contract also states, “The Architect is: Silver Dollar City, Inc.”

Three provisions in the Contract are pertinent to the issues confronting us. The provisions are:

10.5 The Architect will interpret and decide matters concerning performance under and requirements of the Contract Documents on written request of either the Owner or Contractor. The Architect will make initial decisions on all claims, disputes or other matters in question between the Owner and Contractor, but will not be liable for results of any interpretations or decisions rendered in good faith. The Architect’s decisions in matters relating to aesthetic effect will be final if consistent with the intent expressed in the Contract Documents. All other decisions of the Ar-chiteet, except those which have been waived by making or acceptance of final payment, shall be subject to arbitration upon the written demand of either party.
10.8 All claims or disputes between the Contractor and the Owner arising out or relating to the Contract, or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise and subject to an initial presentation of the claim or dispute to the Architect as required under Paragraph 10.5. Notice of the demand for arbitration shall be filed in writing with the other party to this Agreement and with the American Arbitration Association and shall be made within a reasonable time after the dispute has arisen. The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. Except by written consent of the person or entity sought to be joined, no arbitration arising out of or relating to the Contract Documents shall include, by consolidation, joinder or in any other manner, any person or entity not a party to the Agreement under which such arbitration arises, unless it is shown at the time the demand for arbitration is filed that (1) such person or entity is substantially involved in a common question of fact or law, (2) the presence of such person or entity is required if complete relief is to be accorded in the arbitration, (3) the interest or responsibility of such person or entity in the matter is not insubstantial, and (4) such person or entity is not the Architect or any of the Architect’s employees or consultants. The agreement herein among the parties to the Agreement and any other written agreement to arbitrate referred to herein shall be specifically enforceable under applicable law in any court having jurisdiction thereof. *529 19.1 The Contract shall be governed by the law of the place where the Project is located.

While Kitsmiller was working on the project, disputes arose regarding change orders, progress of the work, payment of vendors and subcontractors, and other subjects. Kit-smiller eventually left the project site on or about October 21, 1991.

One of the facts established by the pleadings is: “[Kitsmiller], under date of December 20, 1991, served a Notice of Intent to File Mechanic’s Lien.”

On February 10, 1992, Kitsmiller filed a mechanic’s lien against the Grand Palace in the office of the Clerk of the Circuit Court of Taney County 2 in the sum of $341,432.17.

Kitsmiller thereafter filed a “Demand for Arbitration” with the American Arbitration Association. The document is dated February 11, 1992. It avers, inter alia:

Nature of Dispute: Contract dispute for breach of contract in connection with Grand Palace project ... for delayed and withheld payments, for delayed and withheld change orders and payments for extra/additional work performed at [SDC’s] request, for acceleration and lost efficiency costs, expenses and damages due to changed and increased scope of work and incomplete plans, and for delays, bad faith, hinderance, interference and lack of cooperation on the part of [SDC].

As to the relief sought, the document states: “$341,432.17, plus interest. Award to be enforced as Judgment of Mechanic’s Lien in Circuit Court of Taney County, Missouri.”

SDC’s motion for summary judgment alleges: “[0]n February 21, 1992, [SDC] filed its answer to [Kitsmiller’s] demand to the American Arbitration Association.” In its brief, Kitsmiller acknowledges this.

The record contains an affidavit of SDC’s “Vice President-Finance and Treasurer” stating that by letter dated April 3,1992, the American Arbitration Association declared it would proceed with arbitration unless stayed by court order. The affidavit further states the American Arbitration Association submitted a list of potential arbitrators and that unless SDC responded by April 13, 1992, it would be deemed to have approved all of them. This evidently prompted SDC to file the instant suit which, as reported earlier, was commenced April 10, 1992.

On May 14, 1992, Braiders Steel Co., Inc., filed in the Circuit Court of Taney County a petition to enforce a mechanic’s Ken against the Grand Palace, naming as defendants Tulsa Steel Mfg. Company, Inc., and SDC. That action was assigned number CV792-265CC. We henceforth refer to it as “case 265.”

SDC filed a motion in ease 265 praying that KitsmiKer be joined as a party per § 429.280, RSMo 1986. On July 2,1992, that motion was granted.

On August 5 or 6, 1992, KitsmiKer filed a cross-claim and counterclaim in case 265.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Nephew
367 S.W.3d 127 (Missouri Court of Appeals, 2012)
Fiordelisi v. Mt. Pleasant, LLC
254 S.W.3d 120 (Missouri Court of Appeals, 2008)
Bowers v. Hiland Dairy Co.
132 S.W.3d 260 (Missouri Court of Appeals, 2004)
Dunn Industrial Group, Inc. v. City of Sugar Creek
112 S.W.3d 421 (Supreme Court of Missouri, 2003)
Estate of Burford ex rel. Bruse v. Edward D. Jones & Co.
83 S.W.3d 589 (Missouri Court of Appeals, 2002)
HitCom Corp. v. Flex Financial Corp.
4 S.W.3d 618 (Missouri Court of Appeals, 1999)
Silver Dollar City, Inc. v. Kitsmiller Construction Co.
931 S.W.2d 909 (Missouri Court of Appeals, 1996)
NOS Communications, Inc. v. Robertson
936 F. Supp. 761 (D. Colorado, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
874 S.W.2d 526, 1994 Mo. App. LEXIS 449, 1994 WL 80356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silver-dollar-city-inc-v-kitsmiller-construction-co-moctapp-1994.